Move tree away from driveway |
|
|
|
-- |
-- |
Broken bonus room window is here |
On site needs to be installed |
|
-- |
-- |
Add a few more rocks to the front after driveway is poured |
|
|
-- |
-- |
Few upstairs doors missing |
arrived 7/18 |
|
-- |
-- |
Add additional sod to the front yard |
|
|
-- |
-- |
Refrigerator is in garage other appliances still needed |
|
|
-- |
-- |
This driveway needs expanded 8/10 |
|
|
-- |
-- |
Patch a few large concrete holes in basement? |
Tom |
|
-- |
-- |
Cover carpet quickly |
Jill |
|
-- |
-- |
Trim doors that rub carpet |
|
|
-- |
-- |
Trim the boards that will go under the kitchen cabinets |
Denny |
|
-- |
-- |
Dining chandelier and powder bath light fixture needed |
They arrived, Electrician |
|
-- |
-- |
Few light switch plate covers needed |
Electrician |
|
-- |
-- |
Buyer wants to close ASAP |
What is our best estimate? |
|
-- |
-- |
Stain steps |
Happening today- Monday 9/9 |
|
-- |
-- |
Deadbolt is missing on back patio door |
And deck door |
|
-- |
-- |
Living room light fixture needed |
Electrician |
|
-- |
-- |
Globe is missing from kitchen pendant light. Was it damaged? |
It was damaged. Can we order another one? On order9/9 KK |
|
-- |
-- |
Trim around areas were cabinets are now installed |
George |
|
-- |
-- |
Install mirrors |
Joe |
|
-- |
-- |
CODED LOCKBOX 6767 |
|
|
-- |
-- |
Few lightbulbs needed 9/11 |
Jill |
|
-- |
-- |
Deadbolt missing in all doors |
Joe |
|
-- |
-- |
Adjust closet doors |
Jill |
|
-- |
-- |
Replace cabinet top |
Fred - on order |
|
-- |
-- |
Door stopper outside of powder bath |
Paul |
|
-- |
-- |
Shelf needed in fridge arrived missing |
Courtney or Jill |
|
-- |
-- |
Trim doors that hit carpet. Quite a few. |
George |
|
-- |
-- |
Trim boards to make even on deck |
Tom |
|
-- |
-- |
Push dirt up to side of driveway |
Pettit |
|
-- |
-- |
Pressure wash front of townhouse |
Jill |
|
-- |
-- |
Repaint garage |
Painter |
|
-- |
-- |
Paint touch up |
Painter |
|
-- |
-- |
Black dining light needs installed silver is currently installed |
Electrician |
|
-- |
-- |
Extend vinyl under bump out |
Gap - Davenport |
|
-- |
-- |
Make pocket door easier to close |
George |
|
-- |
-- |
Patch holes powder bath |
Painter |
|
-- |
-- |
Patch gap at stair transition strip |
Denny |
|
-- |
-- |
Nail back of trim on kitchen island |
George |
|
-- |
-- |
Remove paint on vinyl plank |
Painter |
|
-- |
-- |
Caulk shower head |
Painter |
|
-- |
-- |
Adjust bathroom door hall bath. Hard to close. |
George |
|
-- |
-- |
Replace scratched hvac cover |
Jill |
|
-- |
-- |
Few tray ceiling spots need sanded touched up |
Painter. I think this has been completed. |
|
-- |
-- |
|
|
|
-- |
-- |
Some patching needs to be done where the trim was nailed to the back of the kitchen island |
|
|
-- |
-- |
Remove ladder from master bedroom |
|
|
-- |
-- |
Kate - need buyer contact info |
|
|
-- |
-- |
Dionna (540)421-7865. Dianna.k@hotmail.com |
|
|
-- |
-- |
Ruvim (231)409-7493. ruvimpostaychuk@icloud.com |
|
|
-- |
-- |
Seed and straw by driveway |
Pettit |
|
-- |
-- |
Ratified Contract? (0) 04.18.2024 |
|
|
-- |
-- |
$2500 Deposit Received (0) 07.25.2024 |
|
|
-- |
-- |
Association Packet Requested (0) 04.18.2024 |
|
|
-- |
-- |
Association Packet Received (0) 04.19.2024 |
|
|
-- |
-- |
Selections Meeting (0) 08.05.2024 |
Friday, August 2 at 2:30 PM |
|
-- |
-- |
Selections Sheet Signed (0) 08.06.2024 |
|
|
-- |
-- |
Amendment for Upgrades (B,S,L,T,BCP) (0) 08.07.2024 |
8/5: sent to Morgan |
|
-- |
-- |
Deposit For Upgrades Received (0) 08.07.2024 |
|
|
-- |
-- |
Building Permit (30) 01.04.2024 |
|
|
-- |
-- |
Order Roof & Floor Trusses (1) 03.14.2024 |
|
|
-- |
-- |
Order Windows & Doors (0) 04.25.2024 |
|
|
-- |
-- |
Stake Out Home (1) 01.04.2024 |
|
|
-- |
-- |
Excavate (2) 01.04.2024 |
|
|
-- |
-- |
Inspection (Footers) (1) 02.08.2024 |
|
|
-- |
-- |
Inspection (Concrete Wall) (1) 02.08.2024 |
|
|
-- |
-- |
Pour Footers (1) 02.08.2024 |
|
|
-- |
-- |
Set Forms (2) 02.08.2024 |
|
|
-- |
-- |
Pour Foundation Walls (1) 02.19.2024 |
|
|
-- |
-- |
Plumb Slab (2) 03.14.2024 |
|
|
-- |
-- |
Inspection (Plumbing Under Slab) (1) 03.14.2024 |
|
|
-- |
-- |
Inspection (Conduit Under Slab) (1) 03.14.2024 |
|
|
-- |
-- |
Prepare Slab (1) 03.14.2024 |
|
|
-- |
-- |
Inspection (Slab) (1) 03.14.2024 |
|
|
-- |
-- |
Inspection (Drain Tile) (0) 04.25.2024 |
|
|
-- |
-- |
Pour Slab (1) * 03.14.2024 |
|
|
-- |
-- |
Settlement Agent Confirmed (0) 03.14.2024 |
|
|
-- |
-- |
Framing I (9) 04.18.2024 |
|
|
-- |
-- |
Order Steps (0) 04.25.2024 |
|
|
-- |
-- |
Order Tubs / Showers (0) 04.25.2024 |
|
|
-- |
-- |
Framing II (8) 04.18.2024 |
|
|
-- |
-- |
Framing III (8) * 04.18.2024 |
|
|
-- |
-- |
Verify Window & Roof Structure (0) 04.25.2024 |
|
|
-- |
-- |
Install Stairs (0) 04.18.2024 |
|
|
-- |
-- |
Windows & Doors (0) 04.25.2024 |
|
|
-- |
-- |
House Number and Status in Window (0) 04.27.2024 |
|
|
-- |
-- |
Roofing (0) 04.25.2024 |
in process 4/19 |
|
-- |
-- |
Order Cabinets (0) 08.12.2024 |
|
|
-- |
-- |
Order Appliances (0) 08.12.2024 |
|
|
-- |
-- |
Deck (0) 06.22.2024 |
|
|
-- |
-- |
Gutters (0) 06.22.2024 |
|
|
-- |
-- |
Driveway (0) 07.17.2024 |
|
|
-- |
-- |
Patio (0) 06.22.2024 |
|
|
-- |
-- |
Privacy Divider / Fence (0) 07.24.2024 |
in process 7/20 |
|
-- |
-- |
Sod / Seed / Landscaping (0) 08.03.2024 |
|
|
-- |
-- |
HVAC Rough In (4) 04.27.2024 |
In process 4/24 |
|
-- |
-- |
Inspection (Rough In HVAC) (1) 05.29.2024 |
|
|
-- |
-- |
Rough In Microwave Vent (0) 04.27.2024 |
|
|
-- |
-- |
Plumbing Rough In (4) 05.22.2024 |
In process 5/18 |
|
-- |
-- |
Inspection (Rough In Plumbing) (1) 05.29.2024 |
|
|
-- |
-- |
Electric Rough In (4) 05.22.2024 |
|
|
-- |
-- |
Inspection (Rough In Electric) (1) 05.29.2024 |
|
|
-- |
-- |
Inspection (Deck Piers) (0) 08.03.2024 |
|
|
-- |
-- |
Inspection (Framing) (1) 05.29.2024 |
|
|
-- |
-- |
Exterior Vinyl (0) * 06.22.2024 |
|
|
-- |
-- |
Exterior Stone (0) 07.13.2024 |
|
|
-- |
-- |
Insulation (2) 05.29.2024 |
|
|
-- |
-- |
Inspection (Insulation) (1) 06.03.2024 |
|
|
-- |
-- |
Inspection (Electric Service) (0) 08.05.2024 |
|
|
-- |
-- |
Set Electric Meter (0) 08.06.2024 |
|
|
-- |
-- |
Inspection (Main Sewer Line) (0) 04.04.2024 |
|
|
-- |
-- |
Inspection (Main Water Line) (0) 04.04.2024 |
|
|
-- |
-- |
Order Interior Doors & Trim (0) 06.10.2024 |
|
|
-- |
-- |
Drywall (Hang) (4) * 06.12.2024 |
In process 6/5 |
|
-- |
-- |
Loan Approval (0) 08.29.2024 |
|
|
-- |
-- |
Deed Preparation (0) 08.12.2024 |
|
|
-- |
-- |
Drywall (Tape, Block, Skim, Sand) (6) * 06.19.2024 |
In process 6/12 |
|
-- |
-- |
Paint 1 (1) 06.22.2024 |
|
|
-- |
-- |
Garage Door (0) 06.22.2024 |
|
|
-- |
-- |
House Numbers (0) 07.24.2024 |
|
|
-- |
-- |
Mailbox (0) 08.12.2024 |
|
|
-- |
-- |
Cabinet Installation (2) * 09.07.2024 |
Arriving Sep 4, Deliver Sep 5, Install Sep 6 |
|
-- |
-- |
Granite Installation (1) * 09.11.2024 |
Tue, Sep 10 |
|
-- |
-- |
Interior Trim - Install (3) 07.20.2024 |
In process 7/17. Few upstairs doors missing to complete this task. |
|
-- |
-- |
Order Plumbing / Lighting Fixtures (0) 07.29.2024 |
|
|
-- |
-- |
Interior Trim - Paint (1) 07.20.2024 |
|
|
-- |
-- |
Luxury Vinyl Plank (3) * 08.14.2024 |
In process 8/7 |
|
-- |
-- |
Luxury Vinyl Tile (0) 08.10.2024 |
|
|
-- |
-- |
Paint 2 (3) 08.10.2024 |
In process 8/7 |
|
-- |
-- |
Cover Floors (1) 08.28.2024 |
|
|
-- |
-- |
Deliver Plumbing / Lighting Fixtures (0) 07.11.2024 |
|
|
-- |
-- |
Shoe Moulding (0) 08.28.2024 |
|
|
-- |
-- |
Shelving, Door Knobs, Fire Extinguisher (0) 08.29.2024 |
In process of shelving 8/18 |
|
-- |
-- |
Install Coded Lockbox (add extra keys) (0) 09.07.2024 |
|
|
-- |
-- |
Pay Water / Sewer Taps (0) 08.05.2024 |
|
|
-- |
-- |
Set Water Meter (0) 08.05.2024 |
|
|
-- |
-- |
Electric Trim Out (3) 08.28.2024 |
In process 8/24 |
|
-- |
-- |
Ceiling Fans (0) 08.28.2024 |
|
|
-- |
-- |
HVAC Trim Out (1) 09.07.2024 |
|
|
-- |
-- |
Blower Door Test (1) 09.16.2024 |
|
|
-- |
-- |
Plumbing Trim Out (2) 09.12.2024 |
Almost complete 9/11 |
|
-- |
-- |
Install Appliances (0) * 09.12.2024 |
On site and ready to install when cabinets arrive |
|
-- |
-- |
Paint 3 (2) * 08.18.2024 |
|
|
-- |
-- |
Carpet (2) 08.18.2024 |
In process 8/14 |
|
-- |
-- |
Appraiser Confirms Construction Completion (0) 09.18.2024 |
Monday, September 16 |
|
-- |
-- |
Inspection (Final HVAC) (1) 09.16.2024 |
|
|
-- |
-- |
Inspection (Final Plumbing) (1) 09.16.2024 |
|
|
-- |
-- |
Inspection (Final Electric) (1) 09.16.2024 |
|
|
-- |
-- |
Inspection (Final Building) (2) * 09.18.2024 |
Tuesday sept 17 |
|
-- |
-- |
Pre Walk Through (0) 09.12.2024 |
|
|
-- |
-- |
Stain Hardwood Stairs (1) 09.12.2024 |
|
|
-- |
-- |
Cleaning (1) 09.16.2024 |
|
|
-- |
-- |
Certificate of Occupancy (1) * 09.20.2024 |
|
|
-- |
-- |
C.O. to Lender (0) 09.20.2024 |
|
|
-- |
-- |
Schedule Closing (0) 09.18.2024 |
|
|
-- |
-- |
Buyer Walk Through (1) 09.16.2024 |
Sunday, September 15, 1:30 PM |
|
-- |
-- |
Payment for Upgrades (0) 09.12.2024 |
|
|
-- |
-- |
Keys to Settlement Agent (0) 09.12.2024 |
|
|
-- |
-- |
Review Settlement Statement (0) 09.17.2024 |
|
|
-- |
-- |
Jerry Signs Closing Documents (0) 09.18.2024 |
|
|
-- |
-- |
Request Trash Tote From POA Manager (0) 08.08.2024 |
|
|
-- |
-- |
Closing (1) 09.23.2024 |
Brittany @ West View Title - Fri, Sep 20 |
|
-- |
-- |
Remove Coded Lockbox (0) 09.28.2024 |
|
|