37 ADDR
CONGERS-2 - 68  ::  1391 Appaloosa Court
[ BUILD: 20232174 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
TO DO
---
UPGRADES
---
CRITICAL PATH
---
TO DO - COMPLETED OR DELETED
Stop putting tarps in windows. Clearly Courtney
Patch, garage door trim holes Davenport
Odd design on the back of the kitchen island? Doesn’t look natural. Fred has ordered a new panel - 7/31
Missing a few transition slips at luxury vinyl plank Eric
Pretty large gap in the bonus room, vanity between the vanity and the cultured marble top Fred
Cover all carpeted areas Jill
Powder bath needs light Electrician
Side molding needed around island George
CODED LOCKBOX 6868
I think the fan blades and the master bathroom need to be flipped the other way so they are solid black Bedroom - electrician
Second coat of paint needed on front door Painter
Cable cover needed in garage
Install screens and screen doors Jill
Install drain in bonus bathroom tub Plumber
I think the wrong color trim has been installed along the master bathroom vanity. George
Install door to bonus bathroom. George
Home Inspection - Thu, Aug 22, 9AM Bruce
Remove extra screens from garage Jill
Install screen doors
Nail whiteboard to back patio door Tom
put screens on doors tom
Repair damaged top deck board
Trim bottom of doors bedroom doors, bedroom closet doors, bsmt utility
Paint handrails
Bonus room utility door is the only one that still needs to be trimmed George
Bonus bathroom needs to be re-cleaned Jill
Paint touchup needed on side of bonus room, vanity Jill - cabinet touch up with paint pen
Caulk side splash on bonus vanity Painter
Clean paint off the LVP in closet under first set of stairs Painter
Paint overspray kit plate under lower cabinet next to exterior wall Painter
Very dusty hardware and kitchen surfaces need to be re-wiped Jill
we clean bathtub in hall bath. Jill
Remove glue or drywall mud from shower wall Jill
Caulk the sides splash in the hall bath Painter
Paint, touchup hall, bath, vanity Painter
Closet doors upstairs bedrooms, need to be wiped, cleaned as well as paint touchup Jill
Caulk inside splash master bath Painter
Paint, touchup, master bath, vanity, kickplate, and shoe. And clean paint off side of cabinet. Painter
Put attic access door in place Jill
Remove ladder from master closet Jill
Ceiling fan blade color still needs to be flipped Electrician
Replace handrail on deck Premier
Repaint front door
Trim side of closet door in bonus room
Trim side of door going into bonus bathroom
Adjust door to master closet or adjust lock
Trim closet, doors, rubbing against each other and upstairs bedroom
Send digital copy Buyer Packet?
Patch holes around garage trim Davenport
Adjust door George
UPGRADES - COMPLETED
    Finished Walk Out Bonus Room  
    Finished Bonus Bathroom  
    Amendment to increase price by $16,100  
CRITICAL PATH - COMPLETED
-- -- Ratified Contract? (0)  03.16.2024    
-- -- $2500 Deposit Received (0)  03.20.2024    
-- -- Association Packet Requested (0)  03.16.2024    
-- -- Association Packet Received (0)  03.20.2024    
-- -- Selections Meeting (0)  04.16.2024     4/11 at 4:30
-- -- Selections Sheet Signed (0)  04.28.2024     4/16: sent to Lisa
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  05.12.2024     4/28: sent to Lisa
-- -- Deposit For Upgrades Received (0)  05.12.2024    
-- -- Building Permit (30) *   02.19.2024    
-- -- Order Roof & Floor Trusses (1)  04.18.2024    
-- -- Order Windows & Doors (0)  05.18.2024    
-- -- Stake Out Home (1)  01.04.2024    
-- -- Excavate (2)  01.04.2024    
-- -- Inspection (Footers) (1)  02.08.2024    
-- -- Inspection (Concrete Wall) (1)  02.08.2024    
-- -- Pour Footers (1) *   02.08.2024    
-- -- Set Forms (2)  02.08.2024    
-- -- Pour Foundation Walls (1)  02.08.2024    
-- -- Plumb Slab (2)  03.14.2024    
-- -- Inspection (Plumbing Under Slab) (1)  03.14.2024    
-- -- Inspection (Conduit Under Slab) (1)  03.14.2024    
-- -- Prepare Slab (1)  03.14.2024    
-- -- Inspection (Slab) (1)  03.14.2024    
-- -- Inspection (Drain Tile) (0)  06.10.2024    
-- -- Pour Slab (1) *   03.14.2024    
-- -- Settlement Agent Confirmed (0)  05.15.2024    
-- -- Framing I (9)  04.18.2024    
-- -- Order Steps (0)  04.18.2024    
-- -- Order Tubs / Showers (0)  04.18.2024    
-- -- Framing II (8)  04.18.2024    
-- -- Framing III (8) *   04.18.2024    
-- -- Verify Window & Roof Structure (0)  04.25.2024    
-- -- Install Stairs (0) *   04.18.2024    
-- -- Windows & Doors (0) *   04.27.2024    
-- -- House Number and Status in Window (0)  04.27.2024    
-- -- Roofing (0) *   04.27.2024    
-- -- Order Cabinets (0)  06.07.2024    
-- -- Order Appliances (0)  07.10.2024     Ordered 5/28
-- -- Deck (0)  06.22.2024    
-- -- Gutters (0)  06.22.2024    
-- -- Driveway (0) *   07.13.2024    
-- -- Patio (0)  05.08.2024    
-- -- Privacy Divider / Fence (0) *   07.24.2024     in process 7/20
-- -- Sod / Seed / Landscaping (0)  07.20.2024    
-- -- HVAC Rough In (4)  04.27.2024     In process 4/24
-- -- Rough In Microwave Vent (0)  05.01.2024    
-- -- Plumbing Rough In (4)  05.15.2024     In process 5/11
-- -- Electric Rough In (4)  05.18.2024     In process 5/15
-- -- Inspection (Rough In HVAC) (1)  05.22.2024    
-- -- Inspection (Rough In Plumbing) (1)  05.22.2024    
-- -- Inspection (Rough In Electric) (1)  05.22.2024    
-- -- Inspection (Framing) (1) *   05.22.2024    
-- -- Inspection (Deck Piers) (0)  07.29.2024    
-- -- Exterior Vinyl (0) *   06.22.2024    
-- -- Exterior Stone (0)  06.22.2024    
-- -- Insulation (2) *   05.22.2024    
-- -- Inspection (Insulation) (1)  06.01.2024    
-- -- Inspection (Electric Service) (0)  07.11.2024    
-- -- Set Electric Meter (0) *   08.06.2024    
-- -- Inspection (Main Sewer Line) (0)  04.04.2024    
-- -- Inspection (Main Water Line) (0)  04.04.2024    
-- -- Order Interior Doors & Trim (0)  06.10.2024    
-- -- Drywall (Hang) (4) *   06.01.2024    
-- -- Loan Approval (0)  04.04.2024     Cash
-- -- Deed Preparation (0)  07.29.2024    
-- -- Drywall (Tape, Block, Skim, Sand) (6) *   06.19.2024     In process 6/15
-- -- Paint 1 (1)  06.22.2024     In process 6/19
-- -- Garage Door (0)  06.22.2024    
-- -- House Numbers (0)  07.24.2024    
-- -- Mailbox (0)  08.03.2024    
-- -- Cabinet Installation (2) *   07.07.2024     Mon, July 1. On site 6/30
-- -- Granite Installation (1) *   07.07.2024    
-- -- Interior Trim - Install (3) *   06.30.2024     In process 6/26
-- -- Order Plumbing / Lighting Fixtures (0)  07.29.2024    
-- -- Interior Trim - Paint (1)  07.07.2024    
-- -- Luxury Vinyl Plank (3) *   07.20.2024    
-- -- Luxury Vinyl Tile (0)  08.03.2024     In process 7/20
-- -- Paint 2 (3)  07.13.2024    
-- -- Cover Floors (0)  08.07.2024    
-- -- Deliver Plumbing / Lighting Fixtures (0)  07.11.2024    
-- -- Shoe Moulding (0)  08.10.2024     In process 8/7
-- -- Shelving, Door Knobs, Fire Extinguisher (1) *   08.14.2024     In process 8/7
-- -- Install Coded Lockbox (add extra keys) (0)  08.08.2024    
-- -- Pay Water / Sewer Taps (0)  08.05.2024    
-- -- Set Water Meter (1) *   08.05.2024    
-- -- Electric Trim Out (3) *   08.03.2024     In process 7/26
-- -- Ceiling Fans (0)  07.24.2024     Master
-- -- HVAC Trim Out (1) *   08.14.2024    
-- -- Blower Door Test (1)  08.15.2024    
-- -- Plumbing Trim Out (2) *   08.10.2024     In process 8/7
-- -- Install Appliances (0) *   07.26.2024    
-- -- Paint 3 (2) *   08.03.2024    
-- -- Carpet (2)  08.03.2024    
-- -- Appraiser Confirms Construction Completion (0)  08.26.2024    
-- -- Inspection (Final HVAC) (0)  08.15.2024    
-- -- Inspection (Final Plumbing) (0)  08.15.2024    
-- -- Inspection (Final Electric) (0)  08.15.2024    
-- -- Inspection (Final Building) (4) *   08.24.2024     Aug 21
-- -- Pre Walk Through (0)  08.21.2024    
-- -- Stain Hardwood Stairs (1) *   08.07.2024     In process 8/3
-- -- Cleaning (1)  08.18.2024    
-- -- Certificate of Occupancy (1) *   08.28.2024    
-- -- C.O. to Lender (0)  08.28.2024    
-- -- Schedule Closing (0)  08.29.2024    
-- -- Buyer Walk Through (1) *   08.28.2024     Tuesday at 4:30 PM
-- -- Payment for Upgrades (0)  08.19.2024    
-- -- Keys to Settlement Agent (0)  08.19.2024    
-- -- Review Settlement Statement (0)  08.29.2024    
-- -- Jerry Signs Closing Documents (0)  08.29.2024    
-- -- Request Trash Tote From POA Manager (0)  08.08.2024    
-- -- Closing (1)  09.05.2024     Brittany @ West View Title, Wed, Sep 4 at 4:30 PM
-- -- Remove Coded Lockbox (0)  09.05.2024