-- |
-- |
Trim out garage |
|
|
|
|
Microwave vented to exterior
|
|
|
|
Pine grade painted steps
|
|
|
|
Luxury vinyl tile upgrade to gardenia marble
|
|
Fri |
Sep 20 |
Sod / Seed / Landscaping (0)
|
|
|
Fri |
Sep 20 |
Loan Approval (0)
|
|
|
Fri |
Sep 20 |
Deed Preparation (0)
|
|
|
Fri |
Sep 20 |
Cabinet Installation (2)
|
Arriving week of Oct 10 |
|
Tue |
Sep 24 |
Granite Installation (1)
|
|
|
Wed |
Sep 25 |
Luxury Vinyl Plank (3)
|
|
|
Mon |
Sep 30 |
Luxury Vinyl Tile (0)
|
|
|
Mon |
Sep 30 |
Cover Floors (1)
|
|
|
Tue |
Oct 1 |
Deliver Plumbing / Lighting Fixtures (0)
|
|
|
Tue |
Oct 1 |
Shoe Moulding (0)
|
|
|
Tue |
Oct 1 |
Shelving, Door Knobs, Fire Extinguisher (0)
|
In process 9/18 |
|
Tue |
Oct 1 |
Install Coded Lockbox (add extra keys) (0)
|
|
|
Tue |
Oct 1 |
Electric Trim Out (3)
|
|
|
Fri |
Oct 4 |
Ceiling Fans (0)
|
|
|
Fri |
Oct 4 |
Blower Door Test (1)
|
|
|
Mon |
Oct 7 |
Plumbing Trim Out (2)
|
|
|
Wed |
Oct 9 |
Install Appliances (0)
|
|
|
Wed |
Oct 9 |
Paint 3 (2)
|
|
|
Fri |
Oct 11 |
Carpet (2)
|
|
|
Tue |
Oct 15 |
Appraiser Confirms Construction Completion (0)
|
|
|
Tue |
Oct 15 |
Inspection (Final HVAC) (1)
|
|
|
Wed |
Oct 16 |
Inspection (Final Plumbing) (1)
|
|
|
Thu |
Oct 17 |
Inspection (Final Electric) (1)
|
|
|
Fri |
Oct 18 |
Inspection (Final Building) (2)
|
|
|
Tue |
Oct 22 |
Pre Walk Through (0)
|
|
|
Tue |
Oct 22 |
Stain Hardwood Stairs (1)
|
|
|
Wed |
Oct 23 |
Cleaning (1)
|
|
|
Thu |
Oct 24 |
Certificate of Occupancy (1)
|
|
|
Fri |
Oct 25 |
C.O. to Lender (0)
|
|
|
Fri |
Oct 25 |
Schedule Closing (0)
|
|
|
Fri |
Oct 25 |
Buyer Walk Through (1)
|
|
|
Mon |
Oct 28 |
Payment for Upgrades (0)
|
|
|
Mon |
Oct 28 |
Keys to Settlement Agent (0)
|
|
|
Mon |
Oct 28 |
Review Settlement Statement (0)
|
|
|
Mon |
Oct 28 |
Jerry Signs Closing Documents (0)
|
|
|
Mon |
Oct 28 |
Request Trash Tote From POA Manager (0)
|
|
|
Mon |
Oct 28 |
Closing (1)
|
Terry @ Eagle Title |
|
Tue |
Oct 29 |
Remove Coded Lockbox (0)
|
|
|
|
-- |
-- |
3x6 deck instead of patio - 10x12 deck above. 53-56. 10wx9d below deck as option |
|
|
-- |
-- |
Can only be 10x10 deck |
|
|
-- |
-- |
There’s a few windows missing in each of these units. |
|
|
-- |
-- |
Pretty large gap above the patio door here as well |
|
|
-- |
-- |
Are we building further? If not, can we clean up trash and construction items for showings? |
|
|
-- |
-- |
Things to do for showings: general construction trash, and contractor trash cleanup, install doorknob on back deck door so people can go outside, install handrails |
|
|
-- |
-- |
Expanded driveway installed 8/28 |
|
|
-- |
-- |
(need to charge a buyer for driveway upgrade) |
|
|
-- |
-- |
Ratified Contract? (0)
09.08.2024 |
|
|
|
|
Microwave vented to exterior
|
|
|
|
Pine grade painted steps
|
|
|
|
Luxury vinyl tile upgrade to gardenia marble
|
|
-- |
-- |
$2500 Deposit Received (0)
09.12.2024 |
|
|
-- |
-- |
Association Packet Requested (0)
09.08.2024 |
|
|
-- |
-- |
Association Packet Received (0)
09.14.2024 |
|
|
-- |
-- |
Selections Meeting (0)
09.11.2024 |
|
|
-- |
-- |
Selections Sheet Signed (0)
09.12.2024 |
9/11: sent to Kozhin |
|
-- |
-- |
Amendment for Upgrades (B,S,L,T,BCP) (0)
09.13.2024 |
9/12: sent to Jerry |
|
-- |
-- |
Deposit For Upgrades Received (0)
09.11.2024 |
|
|
-- |
-- |
Building Permit (30)
02.19.2024 |
|
|
-- |
-- |
Order Roof & Floor Trusses (1)
05.23.2024 |
|
|
-- |
-- |
Order Windows & Doors (0)
06.19.2024 |
|
|
-- |
-- |
Stake Out Home (1)
02.19.2024 |
|
|
-- |
-- |
Excavate (2)
02.19.2024 |
|
|
-- |
-- |
Inspection (Footers) (1)
02.19.2024 |
|
|
-- |
-- |
Inspection (Concrete Wall) (1)
02.19.2024 |
|
|
-- |
-- |
Pour Footers (1)
02.19.2024 |
|
|
-- |
-- |
Set Forms (2)
04.18.2024 |
|
|
-- |
-- |
Pour Foundation Walls (1)
04.18.2024 |
|
|
-- |
-- |
Plumb Slab (2)
04.18.2024 |
|
|
-- |
-- |
Inspection (Plumbing Under Slab) (1)
04.18.2024 |
|
|
-- |
-- |
Inspection (Conduit Under Slab) (1)
04.18.2024 |
|
|
-- |
-- |
Prepare Slab (1)
04.18.2024 |
|
|
-- |
-- |
Inspection (Slab) (1)
04.18.2024 |
|
|
-- |
-- |
Inspection (Drain Tile) (0)
04.18.2024 |
|
|
-- |
-- |
Pour Slab (1)
04.18.2024 |
|
|
-- |
-- |
Settlement Agent Confirmed (0)
09.13.2024 |
|
|
-- |
-- |
Framing I (9)
04.22.2024 |
|
|
-- |
-- |
Order Steps (0)
05.23.2024 |
|
|
-- |
-- |
Order Tubs / Showers (0)
06.19.2024 |
|
|
-- |
-- |
Framing II (8)
05.13.2024 |
|
|
-- |
-- |
Framing III (8)
05.23.2024 |
|
|
-- |
-- |
Verify Window & Roof Structure (0)
05.23.2024 |
|
|
-- |
-- |
Install Stairs (0)
05.23.2024 |
|
|
-- |
-- |
Windows & Doors (0)
07.13.2024 |
|
|
-- |
-- |
House Number and Status in Window (0)
07.20.2024 |
|
|
-- |
-- |
Roofing (0)
06.16.2024 |
|
|
-- |
-- |
Order Cabinets (0)
09.11.2024 |
|
|
-- |
-- |
Order Appliances (0)
08.12.2024 |
|
|
-- |
-- |
Deck (0)
07.13.2024 |
|
|
-- |
-- |
Gutters (0)
08.28.2024 |
|
|
-- |
-- |
Driveway (0)
08.28.2024 |
|
|
-- |
-- |
Patio (0)
07.13.2024 |
|
|
-- |
-- |
Privacy Divider / Fence (0)
09.04.2024 |
|
|
-- |
-- |
HVAC Rough In (4)
06.05.2024 |
in process 6/1 |
|
-- |
-- |
Inspection (Rough In HVAC) (1)
07.07.2024 |
|
|
-- |
-- |
Rough In Microwave Vent (0)
06.05.2024 |
|
|
-- |
-- |
Plumbing Rough In (4)
06.15.2024 |
In process 6/5 |
|
-- |
-- |
Inspection (Rough In Plumbing) (1)
07.07.2024 |
|
|
-- |
-- |
Electric Rough In (4)
06.19.2024 |
In process 6/15 |
|
-- |
-- |
Inspection (Rough In Electric) (1)
07.07.2024 |
|
|
-- |
-- |
Inspection (Deck Piers) (0)
09.05.2024 |
|
|
-- |
-- |
Inspection (Framing) (1)
07.07.2024 |
|
|
-- |
-- |
Exterior Vinyl (0)
08.07.2024 |
|
|
-- |
-- |
Exterior Stone (0)
09.04.2024 |
In process 8/7 |
|
-- |
-- |
Insulation (2)
06.30.2024 |
|
|
-- |
-- |
Inspection (Insulation) (1)
07.13.2024 |
|
|
-- |
-- |
Inspection (Electric Service) (0)
09.05.2024 |
|
|
-- |
-- |
Set Electric Meter (0)
09.17.2024 |
|
|
-- |
-- |
Inspection (Main Sewer Line) (0)
04.04.2024 |
|
|
-- |
-- |
Inspection (Main Water Line) (0)
04.04.2024 |
|
|
-- |
-- |
Order Interior Doors & Trim (0)
07.20.2024 |
|
|
-- |
-- |
Drywall (Hang) (4)
07.07.2024 |
|
|
-- |
-- |
Drywall (Tape, Block, Skim, Sand) (6)
07.13.2024 |
|
|
-- |
-- |
Paint 1 (1)
07.20.2024 |
In process 7/17 |
|
-- |
-- |
Garage Door (0)
08.14.2024 |
|
|
-- |
-- |
House Numbers (0)
09.18.2024 |
|
|
-- |
-- |
Mailbox (0)
09.18.2024 |
|
|
-- |
-- |
Interior Trim - Install (3)
08.03.2024 |
In process 7/24 |
|
-- |
-- |
Order Plumbing / Lighting Fixtures (0)
09.18.2024 |
|
|
-- |
-- |
Interior Trim - Paint (1)
08.03.2024 |
|
|
-- |
-- |
Paint 2 (3)
09.15.2024 |
|
|
-- |
-- |
Pay Water / Sewer Taps (0)
09.12.2024 |
|
|
-- |
-- |
Set Water Meter (0)
09.17.2024 |
|
|
-- |
-- |
HVAC Trim Out (1)
09.18.2024 |
|
|