CONGERS-2 - 53  ::  1384 Appaloosa Court
[ BUILD: 20231958 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS


Wednesday (Sep 18)    show all photos
--   --   Trim out garage
    Microwave vented to exterior  
    Pine grade painted steps  
    Luxury vinyl tile upgrade to gardenia marble  
Fri    Sep 20      Sod / Seed / Landscaping (0)      
Fri    Sep 20      Loan Approval (0)      
Fri    Sep 20      Deed Preparation (0)      
Fri    Sep 20      Cabinet Installation (2)       Arriving week of Oct 10
Tue    Sep 24      Granite Installation (1)      
Wed    Sep 25      Luxury Vinyl Plank (3)      
Mon    Sep 30      Luxury Vinyl Tile (0)      
Mon    Sep 30      Cover Floors (1)      
Tue    Oct 1      Deliver Plumbing / Lighting Fixtures (0)      
Tue    Oct 1      Shoe Moulding (0)      
Tue    Oct 1      Shelving, Door Knobs, Fire Extinguisher (0)       In process 9/18
Tue    Oct 1      Install Coded Lockbox (add extra keys) (0)      
Tue    Oct 1      Electric Trim Out (3)      
Fri    Oct 4      Ceiling Fans (0)      
Fri    Oct 4      Blower Door Test (1)      
Mon    Oct 7      Plumbing Trim Out (2)      
Wed    Oct 9      Install Appliances (0)      
Wed    Oct 9      Paint 3 (2)      
Fri    Oct 11      Carpet (2)      
Tue    Oct 15      Appraiser Confirms Construction Completion (0)      
Tue    Oct 15      Inspection (Final HVAC) (1)      
Wed    Oct 16      Inspection (Final Plumbing) (1)      
Thu    Oct 17      Inspection (Final Electric) (1)      
Fri    Oct 18      Inspection (Final Building) (2)      
Tue    Oct 22      Pre Walk Through (0)      
Tue    Oct 22      Stain Hardwood Stairs (1)      
Wed    Oct 23      Cleaning (1)      
Thu    Oct 24      Certificate of Occupancy (1)      
Fri    Oct 25      C.O. to Lender (0)      
Fri    Oct 25      Schedule Closing (0)      
Fri    Oct 25      Buyer Walk Through (1)      
Mon    Oct 28      Payment for Upgrades (0)      
Mon    Oct 28      Keys to Settlement Agent (0)      
Mon    Oct 28      Review Settlement Statement (0)      
Mon    Oct 28      Jerry Signs Closing Documents (0)      
Mon    Oct 28      Request Trash Tote From POA Manager (0)      
Mon    Oct 28      Closing (1)       Terry @ Eagle Title
Tue    Oct 29      Remove Coded Lockbox (0)      
--   --   3x6 deck instead of patio - 10x12 deck above. 53-56. 10wx9d below deck as option
--   --   Can only be 10x10 deck
--   --   There’s a few windows missing in each of these units.
--   --   Pretty large gap above the patio door here as well
--   --   Are we building further? If not, can we clean up trash and construction items for showings?
--   --   Things to do for showings: general construction trash, and contractor trash cleanup, install doorknob on back deck door so people can go outside, install handrails
--   --   Expanded driveway installed 8/28
--   --   (need to charge a buyer for driveway upgrade)
-- -- Ratified Contract? (0)  09.08.2024    
    Microwave vented to exterior  
    Pine grade painted steps  
    Luxury vinyl tile upgrade to gardenia marble  
-- -- $2500 Deposit Received (0)  09.12.2024    
-- -- Association Packet Requested (0)  09.08.2024    
-- -- Association Packet Received (0)  09.14.2024    
-- -- Selections Meeting (0)  09.11.2024    
-- -- Selections Sheet Signed (0)  09.12.2024     9/11: sent to Kozhin
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  09.13.2024     9/12: sent to Jerry
-- -- Deposit For Upgrades Received (0)  09.11.2024    
-- -- Building Permit (30)  02.19.2024    
-- -- Order Roof & Floor Trusses (1)  05.23.2024    
-- -- Order Windows & Doors (0)  06.19.2024    
-- -- Stake Out Home (1)  02.19.2024    
-- -- Excavate (2)  02.19.2024    
-- -- Inspection (Footers) (1)  02.19.2024    
-- -- Inspection (Concrete Wall) (1)  02.19.2024    
-- -- Pour Footers (1)  02.19.2024    
-- -- Set Forms (2)  04.18.2024    
-- -- Pour Foundation Walls (1)  04.18.2024    
-- -- Plumb Slab (2)  04.18.2024    
-- -- Inspection (Plumbing Under Slab) (1)  04.18.2024    
-- -- Inspection (Conduit Under Slab) (1)  04.18.2024    
-- -- Prepare Slab (1)  04.18.2024    
-- -- Inspection (Slab) (1)  04.18.2024    
-- -- Inspection (Drain Tile) (0)  04.18.2024    
-- -- Pour Slab (1)  04.18.2024    
-- -- Settlement Agent Confirmed (0)  09.13.2024    
-- -- Framing I (9)  04.22.2024    
-- -- Order Steps (0)  05.23.2024    
-- -- Order Tubs / Showers (0)  06.19.2024    
-- -- Framing II (8)  05.13.2024    
-- -- Framing III (8)  05.23.2024    
-- -- Verify Window & Roof Structure (0)  05.23.2024    
-- -- Install Stairs (0)  05.23.2024    
-- -- Windows & Doors (0)  07.13.2024    
-- -- House Number and Status in Window (0)  07.20.2024    
-- -- Roofing (0)  06.16.2024    
-- -- Order Cabinets (0)  09.11.2024    
-- -- Order Appliances (0)  08.12.2024    
-- -- Deck (0)  07.13.2024    
-- -- Gutters (0)  08.28.2024    
-- -- Driveway (0)  08.28.2024    
-- -- Patio (0)  07.13.2024    
-- -- Privacy Divider / Fence (0)  09.04.2024    
-- -- HVAC Rough In (4)  06.05.2024     in process 6/1
-- -- Inspection (Rough In HVAC) (1)  07.07.2024    
-- -- Rough In Microwave Vent (0)  06.05.2024    
-- -- Plumbing Rough In (4)  06.15.2024     In process 6/5
-- -- Inspection (Rough In Plumbing) (1)  07.07.2024    
-- -- Electric Rough In (4)  06.19.2024     In process 6/15
-- -- Inspection (Rough In Electric) (1)  07.07.2024    
-- -- Inspection (Deck Piers) (0)  09.05.2024    
-- -- Inspection (Framing) (1)  07.07.2024    
-- -- Exterior Vinyl (0)  08.07.2024    
-- -- Exterior Stone (0)  09.04.2024     In process 8/7
-- -- Insulation (2)  06.30.2024    
-- -- Inspection (Insulation) (1)  07.13.2024    
-- -- Inspection (Electric Service) (0)  09.05.2024    
-- -- Set Electric Meter (0)  09.17.2024    
-- -- Inspection (Main Sewer Line) (0)  04.04.2024    
-- -- Inspection (Main Water Line) (0)  04.04.2024    
-- -- Order Interior Doors & Trim (0)  07.20.2024    
-- -- Drywall (Hang) (4)  07.07.2024    
-- -- Drywall (Tape, Block, Skim, Sand) (6)  07.13.2024    
-- -- Paint 1 (1)  07.20.2024     In process 7/17
-- -- Garage Door (0)  08.14.2024    
-- -- House Numbers (0)  09.18.2024    
-- -- Mailbox (0)  09.18.2024    
-- -- Interior Trim - Install (3)  08.03.2024     In process 7/24
-- -- Order Plumbing / Lighting Fixtures (0)  09.18.2024    
-- -- Interior Trim - Paint (1)  08.03.2024    
-- -- Paint 2 (3)  09.15.2024    
-- -- Pay Water / Sewer Taps (0)  09.12.2024    
-- -- Set Water Meter (0)  09.17.2024    
-- -- HVAC Trim Out (1)  09.18.2024