37 ADDR
CONGERS-2 - 54  ::  1380 Appaloosa Court
[ BUILD: 20231959 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
TO DO
---
UPGRADES
---
CRITICAL PATH
---
TO DO - COMPLETED OR DELETED
Can only be 10x10 deck
Pretty large gap above the patio door, bleeding out the bonus room
Cover carpet
Trim around newly installed cabinets George
More flooring is going to need to be installed in a few of the kitchen cabinets as the trim is not going to cover Eric. I think fixed 9/25
CODED LOCKBOX 5454
Missing smoke detector in hallway Electrician
Powder bath mirror needs installed
Install microwave
Needs trim in garage George
Clean out garage Jill
Finish staining steps Painter - paint risers
Remove mud from sreps
Remove blue tape at stairs
Does front door need to be repainted? Or maybe just cleaned? Jill
Paint garage trim
Install screens
Adjust the door to closet under stairs on the second level
Remove cover on smoke detector living room Jill
Adjust the floor vent in the master bedroom Jason
Remove paint from carpet in master bedroom Jill will check
Paint touchup minor throughout
Pressure wash driveway in front of house Buddy
Attic window. Remove plastic from right hand corner. Tom
Remove glue from transition strips at floor, luxury vinyl plank
Remove glue from transition strips at floor, luxury vinyl plank Jill
UPGRADES - COMPLETED
    White perimeter Kitchen Cabinets  
    Expanded Driveway  
    LVP in upstairs hallway  
    Amendment to increase price by $3,310  
CRITICAL PATH - COMPLETED
-- -- Ratified Contract? (0)  07.19.2024    
-- -- $2500 Deposit Received (0)  07.19.2024    
-- -- Association Packet Requested (0)  07.20.2024    
-- -- Association Packet Received (0)  07.26.2024    
-- -- Selections Meeting (0)  08.15.2024     Mon, Aug 12
-- -- Selections Sheet Signed (0)  08.17.2024     8/14: sent to Mattias for signatures
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  08.20.2024     8/19: sent to Jerry
-- -- Deposit For Upgrades Received (0)  08.17.2024    
-- -- Building Permit (30) *   02.19.2024    
-- -- Order Roof & Floor Trusses (1)  05.23.2024    
-- -- Order Windows & Doors (0)  06.19.2024    
-- -- Stake Out Home (1)  02.19.2024    
-- -- Excavate (2)  02.19.2024    
-- -- Inspection (Footers) (1)  02.19.2024    
-- -- Inspection (Concrete Wall) (1)  02.19.2024    
-- -- Pour Footers (1) *   02.19.2024    
-- -- Set Forms (2)  04.18.2024    
-- -- Pour Foundation Walls (1)  04.18.2024    
-- -- Plumb Slab (2)  04.18.2024    
-- -- Inspection (Plumbing Under Slab) (1)  04.18.2024    
-- -- Inspection (Conduit Under Slab) (1)  04.18.2024    
-- -- Prepare Slab (1)  04.18.2024    
-- -- Inspection (Slab) (1)  04.18.2024    
-- -- Inspection (Drain Tile) (0)  04.18.2024    
-- -- Pour Slab (1) *   04.18.2024    
-- -- Settlement Agent Confirmed (0)  07.19.2024    
-- -- Framing I (9)  04.22.2024    
-- -- Order Steps (0)  05.23.2024    
-- -- Order Tubs / Showers (0)  06.19.2024    
-- -- Framing II (8)  05.13.2024    
-- -- Framing III (8) *   05.23.2024    
-- -- Verify Window & Roof Structure (0)  05.23.2024    
-- -- Install Stairs (0) *   05.23.2024    
-- -- Windows & Doors (0) *   07.15.2024    
-- -- House Number and Status in Window (0)  07.20.2024    
-- -- Roofing (0) *   06.16.2024    
-- -- Order Cabinets (0)  08.16.2024    
-- -- Order Appliances (0)  08.12.2024    
-- -- Deck (0)  07.17.2024    
-- -- Gutters (0)  08.21.2024    
-- -- Driveway (0) *   08.28.2024    
-- -- Patio (0)  08.21.2024    
-- -- Privacy Divider / Fence (0) *   08.18.2024    
-- -- Sod / Seed / Landscaping (0)  10.05.2024    
-- -- HVAC Rough In (4)  06.03.2024    
-- -- Rough In Microwave Vent (0)  06.05.2024    
-- -- Plumbing Rough In (4)  06.26.2024     In process 6/22
-- -- Electric Rough In (4)  06.19.2024    
-- -- Inspection (Rough In HVAC) (1)  07.07.2024    
-- -- Inspection (Rough In Plumbing) (1)  07.07.2024    
-- -- Inspection (Rough In Electric) (1)  07.07.2024    
-- -- Inspection (Framing) (1) *   07.07.2024    
-- -- Inspection (Deck Piers) (0)  09.05.2024    
-- -- Exterior Vinyl (0) *   08.07.2024    
-- -- Exterior Stone (0)  08.07.2024    
-- -- Insulation (2) *   06.30.2024    
-- -- Inspection (Insulation) (1)  07.07.2024    
-- -- Inspection (Electric Service) (0)  09.05.2024    
-- -- Set Electric Meter (0) *   09.17.2024    
-- -- Inspection (Main Sewer Line) (0)  04.04.2024    
-- -- Inspection (Main Water Line) (0)  04.04.2024    
-- -- Order Interior Doors & Trim (0)  08.03.2024    
-- -- Drywall (Hang) (4) *   07.07.2024    
-- -- Loan Approval (0)  08.01.2024    
-- -- Deed Preparation (0)  09.05.2024    
-- -- Drywall (Tape, Block, Skim, Sand) (6) *   07.13.2024     In process 7/6
-- -- Paint 1 (1)  07.13.2024    
-- -- Garage Door (0)  08.14.2024    
-- -- House Numbers (0)  09.18.2024    
-- -- Mailbox (0)  09.15.2024    
-- -- Cabinet Installation (2) *   09.15.2024     Arriving Sept 9, Delivered Sept 11, Install Sept 12
-- -- Granite Installation (1) *   09.25.2024     Sept 23
-- -- Interior Trim - Install (3) *   08.03.2024     In process 8/3
-- -- Order Plumbing / Lighting Fixtures (0)  09.09.2024    
-- -- Interior Trim - Paint (1)  08.10.2024     In process 8/7
-- -- Luxury Vinyl Plank (3) *   08.21.2024    
-- -- Luxury Vinyl Tile (0)  08.21.2024    
-- -- Paint 2 (3)  08.24.2024    
-- -- Cover Floors (0)  08.28.2024    
-- -- Deliver Plumbing / Lighting Fixtures (0)  09.12.2024    
-- -- Shoe Moulding (0)  09.07.2024    
-- -- Shelving, Door Knobs, Fire Extinguisher (1) *   09.25.2024     In process 9/18. Needs mirrors.
-- -- Install Coded Lockbox (add extra keys) (0)  09.19.2024    
-- -- Pay Water / Sewer Taps (0)  09.12.2024    
-- -- Set Water Meter (1) *   09.17.2024    
-- -- Electric Trim Out (3) *   09.21.2024    
-- -- Ceiling Fans (0)  09.21.2024    
-- -- HVAC Trim Out (1) *   09.18.2024    
-- -- Blower Door Test (1)  09.30.2024    
-- -- Plumbing Trim Out (2) *   09.25.2024     In process 9/21.
-- -- Install Appliances (0) *   09.28.2024     Fri, Sep 27
-- -- Paint 3 (2) *   08.24.2024    
-- -- Carpet (2)  08.24.2024     In process 8/21
-- -- Appraiser Confirms Construction Completion (0)  10.03.2024     Mon, Sep 30
-- -- Inspection (Final HVAC) (0)  10.03.2024    
-- -- Inspection (Final Plumbing) (0)  10.03.2024    
-- -- Inspection (Final Electric) (0)  10.03.2024    
-- -- Inspection (Final Building) (4) *   10.04.2024     Thu, Oct 3
-- -- Pre Walk Through (0)  10.05.2024    
-- -- Stain Hardwood Stairs (1) *   10.02.2024    
-- -- Cleaning (1)  10.02.2024     In process 9/28
-- -- Certificate of Occupancy (1) *   10.10.2024    
-- -- C.O. to Lender (0)  10.10.2024    
-- -- Schedule Closing (0)  10.10.2024    
-- -- Buyer Walk Through (1) *   10.11.2024     Thursday, Oct 10 at 11AM
-- -- Payment for Upgrades (0)  10.03.2024    
-- -- Keys to Settlement Agent (0)  10.04.2024    
-- -- Review Settlement Statement (0)  10.10.2024    
-- -- Jerry Signs Closing Documents (0)  09.18.2024    
-- -- Request Trash Tote From POA Manager (0)  10.08.2024    
-- -- Closing (1)  10.11.2024     Brittany @ West View Title
-- -- Remove Coded Lockbox (0)  10.30.2024