CONGERS-2 - 55  ::  1376 Appaloosa Court
[ BUILD: 20231960 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS


Wednesday (Sep 18)    show all photos
--   --   Vinyl pieces missing
--   --   Does concrete missing near front metal trim of garage need to be patched?
    Pine painted steps to bedroom level  
    Microwave vented to the exterior  
    Luxury vinyl tile upgrade to gardenia marble  
Fri    Sep 20      Sod / Seed / Landscaping (0)  09.15.2024    
Fri    Sep 20      Loan Approval (0)      
Fri    Sep 20      Deed Preparation (0)      
Fri    Sep 20      Cabinet Installation (2)       Arriving week of Oct 10
Tue    Sep 24      Granite Installation (1)      
Wed    Sep 25      Order Plumbing / Lighting Fixtures (0)      
Wed    Sep 25      Luxury Vinyl Plank (3)      
Mon    Sep 30      Luxury Vinyl Tile (0)      
Mon    Sep 30      Cover Floors (1)      
Tue    Oct 1      Deliver Plumbing / Lighting Fixtures (0)      
Tue    Oct 1      Shoe Moulding (0)      
Tue    Oct 1      Shelving, Door Knobs, Fire Extinguisher (0)      
Tue    Oct 1      Install Coded Lockbox (add extra keys) (0)      
Tue    Oct 1      Electric Trim Out (3)      
Fri    Oct 4      Ceiling Fans (0)      
Fri    Oct 4      HVAC Trim Out (1)      
Mon    Oct 7      Blower Door Test (1)      
Tue    Oct 8      Plumbing Trim Out (2)      
Thu    Oct 10      Install Appliances (0)      
Thu    Oct 10      Paint 3 (2)      
Mon    Oct 14      Carpet (2)      
Wed    Oct 16      Appraiser Confirms Construction Completion (0)      
Wed    Oct 16      Inspection (Final HVAC) (1)      
Thu    Oct 17      Inspection (Final Plumbing) (1)      
Fri    Oct 18      Inspection (Final Electric) (1)      
Mon    Oct 21      Inspection (Final Building) (2)      
Wed    Oct 23      Pre Walk Through (0)      
Wed    Oct 23      Stain Hardwood Stairs (1)      
Thu    Oct 24      Cleaning (1)      
Fri    Oct 25      Certificate of Occupancy (1)      
Mon    Oct 28      C.O. to Lender (0)      
Mon    Oct 28      Schedule Closing (0)      
Mon    Oct 28      Buyer Walk Through (1)      
Tue    Oct 29      Payment for Upgrades (0)      
Tue    Oct 29      Keys to Settlement Agent (0)      
Tue    Oct 29      Review Settlement Statement (0)      
Tue    Oct 29      Jerry Signs Closing Documents (0)      
Tue    Oct 29      Request Trash Tote From POA Manager (0)      
Tue    Oct 29      Closing (1)       Terry @ Eagle Title
Wed    Oct 30      Remove Coded Lockbox (0)      
--   --   Can only be 10x10 deck
--   --   Does concrete near the front garage? Metal piece need to be patched
--   --   Extended driveway framed 8/28
--   --   (need to charge a buyer for driveway upgrade)
-- -- Ratified Contract? (0)  09.08.2024    
    Pine painted steps to bedroom level  
    Microwave vented to the exterior  
    Luxury vinyl tile upgrade to gardenia marble  
-- -- $2500 Deposit Received (0)  09.12.2024    
-- -- Association Packet Requested (0)  09.08.2024    
-- -- Association Packet Received (0)  09.14.2024    
-- -- Selections Meeting (0)  09.11.2024    
-- -- Selections Sheet Signed (0)  09.12.2024     9/11: sent to Kozhin
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  09.13.2024     9/12: sent to Jerry
-- -- Deposit For Upgrades Received (0)  09.11.2024    
-- -- Building Permit (30)  02.19.2024    
-- -- Order Roof & Floor Trusses (1)  05.23.2024    
-- -- Order Windows & Doors (0)  06.19.2024    
-- -- Stake Out Home (1)  02.19.2024    
-- -- Excavate (2)  02.19.2024    
-- -- Inspection (Footers) (1)  02.19.2024    
-- -- Inspection (Concrete Wall) (1)  02.19.2024    
-- -- Pour Footers (1)  02.19.2024    
-- -- Set Forms (2)  04.18.2024    
-- -- Pour Foundation Walls (1)  04.18.2024    
-- -- Plumb Slab (2)  04.18.2024    
-- -- Inspection (Plumbing Under Slab) (1)  04.18.2024    
-- -- Inspection (Conduit Under Slab) (1)  04.18.2024    
-- -- Prepare Slab (1)  04.18.2024    
-- -- Inspection (Slab) (1)  04.18.2024    
-- -- Inspection (Drain Tile) (0)  04.18.2024    
-- -- Pour Slab (1)  04.18.2024    
-- -- Settlement Agent Confirmed (0)  09.13.2024    
-- -- Framing I (9)  04.22.2024    
-- -- Order Steps (0)  05.23.2024    
-- -- Order Tubs / Showers (0)  06.19.2024    
-- -- Framing II (8)  05.13.2024    
-- -- Framing III (8)  05.23.2024    
-- -- Verify Window & Roof Structure (0)  05.23.2024    
-- -- Install Stairs (0)  05.23.2024    
-- -- Windows & Doors (0)  07.15.2024    
-- -- House Number and Status in Window (0)  07.20.2024    
-- -- Roofing (0)  06.16.2024    
-- -- Order Cabinets (0)  09.11.2024    
-- -- Order Appliances (0)  08.12.2024    
-- -- Deck (0)  07.17.2024    
-- -- Gutters (0)  09.15.2024    
-- -- Driveway (0)  09.15.2024    
-- -- Patio (0)  08.03.2024    
-- -- Privacy Divider / Fence (0)  08.14.2024    
-- -- HVAC Rough In (4)  06.03.2024    
-- -- Inspection (Rough In HVAC) (1)  07.10.2024    
-- -- Rough In Microwave Vent (0)  06.05.2024    
-- -- Plumbing Rough In (4)  06.19.2024    
-- -- Inspection (Rough In Plumbing) (1)  07.10.2024    
-- -- Electric Rough In (4)  06.30.2024    
-- -- Inspection (Rough In Electric) (1)  07.10.2024    
-- -- Inspection (Deck Piers) (0)  09.05.2024    
-- -- Inspection (Framing) (1)  07.10.2024    
-- -- Exterior Vinyl (0)  08.07.2024    
-- -- Exterior Stone (0)  08.07.2024    
-- -- Insulation (2)  07.10.2024    
-- -- Inspection (Insulation) (1)  07.17.2024    
-- -- Inspection (Electric Service) (0)  09.05.2024    
-- -- Set Electric Meter (0)  09.17.2024    
-- -- Inspection (Main Sewer Line) (0)  04.04.2024    
-- -- Inspection (Main Water Line) (0)  04.04.2024    
-- -- Order Interior Doors & Trim (0)  08.03.2024    
-- -- Drywall (Hang) (4)  07.17.2024    
-- -- Drywall (Tape, Block, Skim, Sand) (6)  08.03.2024     In process 7/24
-- -- Paint 1 (1)  08.03.2024    
-- -- Garage Door (0)  08.18.2024    
-- -- House Numbers (0)  09.18.2024    
-- -- Mailbox (0)  09.15.2024    
-- -- Interior Trim - Install (3)  08.21.2024     In process 8/18
-- -- Interior Trim - Paint (1)  08.28.2024    
-- -- Paint 2 (3)  09.18.2024    
-- -- Pay Water / Sewer Taps (0)  09.12.2024    
-- -- Set Water Meter (0)  09.17.2024