1 87 73 ADDR
CONGERS-2 - 55  ::  1376 Appaloosa Court
[ BUILD: 20231960 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
--   --   Can only be 10x10 deck
--   --   Vinyl pieces missing
--   --   Does concrete near the front garage? Metal piece need to be patched
--   --   Does concrete missing near front metal trim of garage need to be patched? Tom
--   --   Extended driveway framed 8/28
--   --   (need to charge a buyer for driveway upgrade)
--   --   Air vent above how closet is badly bent Hall - return vent, Jason
--   --   Few drywall holes need patched in kitchen Painter
--   --   Panel will need to be cut and repaired in places. Electrical outlets were not installed on the exterior. Vinyl, Davenport - ASAP
--   --   Install luxury panel in master bathroom vinyl
--   --   Needs powder mat mirror and fennel shelving installed after carpet is in
--   --   Garage is completely full of appliances
--   --   Repaint front door Painter
--   --   All transition strips need installed Denny
--   --   Add trim work cabinets are now installed
--   --   I need the keys to install a lock box at this home Pantry
--   --   Lock to the garage door does not function properly Paul. Not fixed 10/23
--   --   Needs powder bath mirror and final shelving installed after carpet is in Paul
--   --   Pantry is missing a support on the shelf Paul
--   --   CODED LOCKBOX 5555
--   --   Can we get white electrical covers for the brown kitchen island? Jill
--   --   Powder bath light needed Electricians
--   --   Few large scratches on stained staircase
--   --   Powder bath light needed
--   --   Two towel rings needed in master bath Tom has them
--   --   Microwave vent doesn’t work CJ
--   --   Can we get brown electrical covers for the brown kitchen island? Jill
--   --   Handrail needs installed and vinyl needs repaired before final inspection
--   --   Repair wrap at right side of garage door Davenport
--   --   Install handrails George - ASAP
--   --   Paint front door Painter
--   --   Finish touchup painting Painter
--   --   Gap on wall electrical switch plate Painter
--   --   Install shower bar Paul
--   --   Remove extra pieces of bathroom flooring Jill
--   --   Screens needed Jill
--   --   Clean out bonus room
--   --   Install window screens
--   --   Caulk in wood gaps at the top of the stair transition
--   --   Install shower rod, master bathroom, and towel hooks
--   --   Remove ladder from garage
--   --   Master bathroom needs towel rings
--   --   Kozhin, 540-282-2788, kahmad@harmanrealty.com Contact for tenants
--   --   Repair aluminum wrap at base of both sides of garage door Davenport
--   --   toilet paper holders need installed Joe
--   --   Lowes is replacing refrigerator Tenants are not providing access
-- -- Ratified Contract? (0)  09.08.2024    
    First $2500 of upgrades are free  
    Expanded driveway  
    Pine painted steps to bedroom level  
    Microwave vented to the exterior  
    Luxury vinyl tile upgrade to gardenia marble  
    Upgraded luxury vinyl plank in upstairs  
    Amendment to increase price by $2005  
-- -- $2500 Deposit Received (0)  09.12.2024    
-- -- Association Packet Requested (0)  09.08.2024    
-- -- Association Packet Received (0)  09.14.2024    
-- -- Selections Meeting (0)  09.11.2024    
-- -- Selections Sheet Signed (0)  09.12.2024     9/11: sent to Kozhin
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  09.13.2024     9/12: sent to Jerry
-- -- Deposit For Upgrades Received (0)  09.11.2024    
-- -- Building Permit (30)  02.19.2024    
-- -- Order Roof & Floor Trusses (1)  05.23.2024    
-- -- Order Windows & Doors (0)  06.19.2024    
-- -- Stake Out Home (1)  02.19.2024    
-- -- Excavate (2)  02.19.2024    
-- -- Inspection (Footers) (1)  02.19.2024    
-- -- Inspection (Concrete Wall) (1)  02.19.2024    
-- -- Pour Footers (1) *   02.19.2024    
-- -- Set Forms (2)  04.18.2024    
-- -- Pour Foundation Walls (1)  04.18.2024    
-- -- Plumb Slab (2)  04.18.2024    
-- -- Inspection (Plumbing Under Slab) (1)  04.18.2024    
-- -- Inspection (Conduit Under Slab) (1)  04.18.2024    
-- -- Prepare Slab (1)  04.18.2024    
-- -- Inspection (Slab) (1)  04.18.2024    
-- -- Inspection (Drain Tile) (0)  04.18.2024    
-- -- Pour Slab (1) *   04.18.2024    
-- -- Settlement Agent Confirmed (0)  09.13.2024    
-- -- Framing I (9)  04.22.2024    
-- -- Order Steps (0)  05.23.2024    
-- -- Order Tubs / Showers (0)  06.19.2024    
-- -- Framing II (8)  05.13.2024    
-- -- Framing III (8) *   05.23.2024    
-- -- Verify Window & Roof Structure (0)  05.23.2024    
-- -- Install Stairs (0)  05.23.2024    
-- -- Windows & Doors (0) *   07.15.2024    
-- -- House Number and Status in Window (0)  07.20.2024    
-- -- Roofing (0) *   06.16.2024    
-- -- Order Cabinets (0)  09.11.2024    
-- -- Order Appliances (0)  08.12.2024    
-- -- Deck (0)  07.17.2024    
-- -- Gutters (0)  09.15.2024    
-- -- Driveway (0) *   09.15.2024    
-- -- Patio (0)  08.03.2024    
-- -- Privacy Divider / Fence (0)  08.14.2024    
-- -- Sod / Seed / Landscaping (0)  10.05.2024    
-- -- HVAC Rough In (4)  06.03.2024    
-- -- Inspection (Rough In HVAC) (1)  07.10.2024    
-- -- Rough In Microwave Vent (0)  06.05.2024    
-- -- Plumbing Rough In (4)  06.19.2024    
-- -- Inspection (Rough In Plumbing) (1)  07.10.2024    
-- -- Electric Rough In (4)  06.30.2024    
-- -- Inspection (Rough In Electric) (1)  07.10.2024    
-- -- Inspection (Deck Piers) (0)  09.05.2024    
-- -- Inspection (Framing) (1) *   07.10.2024    
-- -- Exterior Vinyl (0) *   08.07.2024    
-- -- Exterior Stone (0)  08.07.2024    
-- -- Insulation (2) *   07.10.2024    
-- -- Inspection (Insulation) (1)  07.17.2024    
-- -- Inspection (Electric Service) (0)  09.05.2024    
-- -- Set Electric Meter (0) *   09.17.2024    
-- -- Inspection (Main Sewer Line) (0)  04.04.2024    
-- -- Inspection (Main Water Line) (0)  04.04.2024    
-- -- Order Interior Doors & Trim (0)  08.03.2024    
-- -- Drywall (Hang) (4) *   07.17.2024    
-- -- Loan Approval (0)  10.12.2024    
-- -- Deed Preparation (0)  10.12.2024    
-- -- Drywall (Tape, Block, Skim, Sand) (6) *   08.03.2024     In process 7/24
-- -- Paint 1 (1)  08.03.2024    
-- -- Garage Door (0) *   08.18.2024    
-- -- House Numbers (0)  09.18.2024    
-- -- Mailbox (0)  09.15.2024    
-- -- Cabinet Installation (2) *   10.09.2024     Install Oct 8
-- -- Granite Installation (1) *   10.17.2024    
-- -- Interior Trim - Install (3) *   08.21.2024     In process 8/18
-- -- Order Plumbing / Lighting Fixtures (0)  09.23.2024    
-- -- Interior Trim - Paint (1)  08.28.2024    
-- -- Luxury Vinyl Plank (3) *   10.05.2024     In process 10/2
-- -- Luxury Vinyl Tile (0)  10.09.2024    
-- -- Paint 2 (3)  09.18.2024    
-- -- Cover Floors (1)  10.17.2024    
-- -- Deliver Plumbing / Lighting Fixtures (0)  09.25.2024    
-- -- Shoe Moulding (0)  10.12.2024    
-- -- Shelving, Door Knobs, Fire Extinguisher (0) *   10.02.2024     In process 9/28. Needs mirrors once cabinets are installed.
-- -- Install Coded Lockbox (add extra keys) (0)  10.17.2024    
-- -- Pay Water / Sewer Taps (0)  09.12.2024    
-- -- Set Water Meter (0) *   09.17.2024    
-- -- Electric Trim Out (3)  10.19.2024     In process 10/16
-- -- Ceiling Fans (0)  10.12.2024    
-- -- HVAC Trim Out (1)  10.12.2024    
-- -- Blower Door Test (1)  10.28.2024    
-- -- Plumbing Trim Out (2)  10.26.2024     In process 10/23
-- -- Install Appliances (0) *   10.23.2024    
-- -- Paint 3 (2) *   10.16.2024    
-- -- Carpet (2)  10.05.2024    
-- -- Appraiser Confirms Construction Completion (0)  10.24.2024    
-- -- Inspection (Final HVAC) (1)  11.04.2024    
-- -- Inspection (Final Plumbing) (1)  11.04.2024    
-- -- Inspection (Final Electric) (1)  11.04.2024    
-- -- Inspection (Final Building) (2) *   11.02.2024     Tue, Oct 29
-- -- Pre Walk Through (0)  11.02.2024     10/25
-- -- Stain Hardwood Stairs (1)  10.19.2024    
-- -- Cleaning (1)  11.02.2024    
-- -- Certificate of Occupancy (1) *   11.05.2024    
-- -- C.O. to Lender (0)  11.05.2024    
-- -- Schedule Closing (0)  10.31.2024    
-- -- Buyer Walk Through (1)  10.24.2024    
-- -- Payment for Upgrades (0)  10.24.2024    
-- -- Keys to Settlement Agent (0)  11.02.2024    
-- -- Review Settlement Statement (0)  10.24.2024    
-- -- Jerry Signs Closing Documents (0)  10.25.2024    
-- -- Request Trash Tote From POA Manager (0)  10.31.2024    
-- -- Closing (1)  11.01.2024     Terry @ Eagle Title
-- -- Remove Coded Lockbox (0)  11.07.2024