1 33 37 89 47 73 67 55 56 59 57 66 65 64 60 61 62 63 ADDR
CONGERS-2 - 57  ::  1362 Appaloosa Court
[ BUILD: 20231962 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS


Saturday (Nov 23)    show all photos
--   --   Bit of drywall repairs needed to pantry door Drywall
--   --   Pocket door is crooked Domingo. Just needs painted
--   --   Need all mirrors Joe
--   --   Cover carpet Jill
--   --   Trim doors to slide over carpet easily Jorge
--   --   Glue needs removed off of bonus bathtub Jill
--   --   Few shelves needed Paul
--   --   Shoe molding needed in bonus ba5h Jorge
--   --   CODED LOCKBOX 5757
Wed    Nov 27      Loan Approval (0)       USDA
Wed    Nov 27      Shelving, Door Knobs, Fire Extinguisher (0)       In process 11/23
Wed    Nov 27      Appraiser Confirms Construction Completion (0)      
Wed    Nov 27      Pre Walk Through (0)      
Wed    Nov 27      Cleaning (1)      
Thu    Nov 28      Schedule Closing (0)      
Thu    Nov 28      Buyer Walk Through (1)      
Fri    Nov 29      Payment for Upgrades (0)      
Fri    Nov 29      Keys to Settlement Agent (0)      
Fri    Nov 29      Review Settlement Statement (0)      
Fri    Nov 29      Jerry Signs Closing Documents (0)      
Fri    Nov 29      Request Trash Tote From POA Manager (0)      
Fri    Nov 29      Closing (1)       Brittany @ West View Title
Mon    Dec 2      Remove Coded Lockbox (0)      
--   --   Broken primary bedroom window On order
--   --   Deadbolt is missing on back patio door
--   --   Driveway is expanded
--   --   Does the basement patio deck need railings? yes
--   --   Finish back room Drywall stocked 10/23
--   --   Adding upgraded refrigerator?
--   --   Bonus bathroom needs bathtub
--   --   Patch rear concrete square that’s been cut out Tom
--   --   Door needed to utility room
--   --   Trim out garage. George
--   --   This back patio has steps leading off both sides
--   --   Driveway has pretty nasty tire tracks running through it pressure wash
--   --   Kate, there is a French model fridge in this garage
--   --   Finish backroom drywall
--   --   Can we flatten out and re-seed side yard? Pettit
--   --   Add trim in now that cabinets have been installed in kitchen and bathrooms George
--   --   Possible scuff on one of the cabinets nearest the refrigerator Jill will check it out
--   --   Utility room room door needed needs to be installed
--   --   Large scratch on master vanity door Jill will look and let Fred know
--   --   Floor needed in back bonus room Carpet
--   --   Paint doors and then install flooring and back bonus room and bath
--   --   Raised dining room chandelier to appropriate height Electrician
--   --   Few lightbulbs needed Jill
--   --   Kitchen faucet and bonus bathroom need plumbing installed
--   --   Trim out the garage - really
--   --   Towel holder rings need installed Joe
--   --   Need all shelving Joe
--   --   Bonus bathroom needs plumbing installed
--   --   Remove stuff from driveway
--   --   Was upgraded pad installed?
-- -- Ratified Contract? (0)  09.24.2024    
-- -- $2500 Deposit Received (0)  10.03.2024     $5000
-- -- Association Packet Requested (0)  09.24.2024    
-- -- Association Packet Received (0)  10.04.2024    
-- -- Selections Meeting (0)  10.03.2024    
-- -- Selections Sheet Signed (0)  10.03.2024    
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  10.03.2024    
-- -- Deposit For Upgrades Received (0)  10.03.2024    
-- -- Building Permit (30)  04.18.2024    
-- -- Order Roof & Floor Trusses (1)  07.08.2024    
-- -- Order Windows & Doors (0)  07.20.2024    
-- -- Stake Out Home (1)  04.18.2024    
-- -- Excavate (2)  04.18.2024    
-- -- Inspection (Footers) (1)  04.18.2024    
-- -- Inspection (Concrete Wall) (1)  04.18.2024    
-- -- Pour Footers (1)  04.18.2024    
-- -- Set Forms (2)  04.18.2024    
-- -- Pour Foundation Walls (1)  04.18.2024    
-- -- Plumb Slab (2)  04.18.2024    
-- -- Inspection (Plumbing Under Slab) (1)  04.25.2024    
-- -- Inspection (Conduit Under Slab) (1)  04.25.2024    
-- -- Prepare Slab (1)  04.25.2024    
-- -- Inspection (Slab) (1)  04.25.2024    
-- -- Inspection (Drain Tile) (0)  04.25.2024    
-- -- Pour Slab (1) *   04.25.2024    
-- -- Settlement Agent Confirmed (0)  10.04.2024    
-- -- Framing I (9)  05.16.2024    
-- -- Order Steps (0)  07.08.2024    
-- -- Order Tubs / Showers (0)  07.08.2024    
-- -- Framing II (8)  07.08.2024    
-- -- Framing III (8) *   07.08.2024    
-- -- Verify Window & Roof Structure (0)  07.08.2024    
-- -- Install Stairs (0)  07.08.2024    
-- -- Windows & Doors (0)  08.14.2024    
-- -- House Number and Status in Window (0)  07.20.2024    
-- -- Roofing (0)  07.15.2024    
-- -- Order Cabinets (0)  10.14.2024    
-- -- Order Appliances (0)  08.12.2024    
-- -- Deck (0)  09.04.2024    
-- -- Gutters (0)  09.04.2024    
-- -- Driveway (0)  09.11.2024    
-- -- Patio (0)  09.15.2024    
-- -- Privacy Divider / Fence (0)  09.04.2024    
-- -- Sod / Seed / Landscaping (0)  10.30.2024    
-- -- HVAC Rough In (4)  07.20.2024    
-- -- Inspection (Rough In HVAC) (1)  08.03.2024    
-- -- Rough In Microwave Vent (0)  07.20.2024    
-- -- Plumbing Rough In (4)  07.24.2024     Almost completed. 7/20
-- -- Inspection (Rough In Plumbing) (1)  08.03.2024    
-- -- Electric Rough In (4)  08.03.2024     In process 7/24
-- -- Inspection (Rough In Electric) (1)  08.03.2024     likely Monday 7/29 for inspection
-- -- Inspection (Deck Piers) (0)  10.30.2024    
-- -- Inspection (Framing) (1)  08.03.2024    
-- -- Exterior Vinyl (0) *   09.04.2024    
-- -- Exterior Stone (0)  09.04.2024    
-- -- Insulation (2)  08.03.2024    
-- -- Inspection (Insulation) (1)  08.15.2024    
-- -- Inspection (Electric Service) (0)  09.26.2024    
-- -- Set Electric Meter (0)  10.25.2024    
-- -- Inspection (Main Sewer Line) (0)  04.04.2024    
-- -- Inspection (Main Water Line) (0)  04.04.2024    
-- -- Order Interior Doors & Trim (0)  08.15.2024    
-- -- Drywall (Hang) (4) *   08.18.2024     In process 8/14
-- -- Deed Preparation (0)  11.04.2024    
-- -- Drywall (Tape, Block, Skim, Sand) (6) *   08.28.2024     In process 8/24
-- -- Paint 1 (1)  08.28.2024    
-- -- Garage Door (0)  10.06.2024    
-- -- House Numbers (0)  10.30.2024    
-- -- Mailbox (0)  11.16.2024    
-- -- Cabinet Installation (2) *   11.02.2024     Install 10/31
-- -- Granite Installation (1) *   11.16.2024     Thu, Nov 14
-- -- Interior Trim - Install (3)  10.23.2024     In process 10/19
-- -- Order Plumbing / Lighting Fixtures (0)  09.26.2024    
-- -- Interior Trim - Paint (1)  10.30.2024    
-- -- Luxury Vinyl Plank (3) *   10.30.2024    
-- -- Luxury Vinyl Tile (0)  10.30.2024    
-- -- Paint 2 (3)  11.13.2024    
-- -- Cover Floors (1)  11.23.2024    
-- -- Deliver Plumbing / Lighting Fixtures (0)  11.07.2024    
-- -- Shoe Moulding (0)  11.13.2024    
-- -- Install Coded Lockbox (add extra keys) (0)  11.24.2024    
-- -- Pay Water / Sewer Taps (0)  09.26.2024    
-- -- Set Water Meter (0)  09.30.2024    
-- -- Electric Trim Out (3)  11.23.2024     In process 11/16
-- -- Ceiling Fans (0)  11.16.2024    
-- -- HVAC Trim Out (1)  11.23.2024    
-- -- Blower Door Test (1)  11.23.2024    
-- -- Plumbing Trim Out (2)  11.16.2024     In process 11/16
-- -- Install Appliances (0) *   11.23.2024    
-- -- Paint 3 (2) *   11.16.2024     In process 11/13
-- -- Carpet (2)  11.23.2024    
-- -- Inspection (Final HVAC) (1)  11.23.2024    
-- -- Inspection (Final Plumbing) (1)  11.23.2024    
-- -- Inspection (Final Electric) (1)  11.23.2024    
-- -- Inspection (Final Building) (2) *   11.23.2024     Fri, Nov 22
-- -- Stain Hardwood Stairs (1)  11.23.2024     In process 11/20
-- -- Certificate of Occupancy (1) *   11.27.2024    
-- -- C.O. to Lender (0)  11.27.2024