1 14 73 65 61 62 63 ADDR
CONGERS-2 - 57  ::  1362 Appaloosa Court
[ BUILD: 20231962 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
--   --   Broken primary bedroom window On order
--   --   Deadbolt is missing on back patio door
--   --   Driveway is expanded
--   --   Does the basement patio deck need railings? yes
--   --   Finish back room Drywall stocked 10/23
--   --   Adding upgraded refrigerator?
--   --   Bonus bathroom needs bathtub
--   --   Patch rear concrete square that’s been cut out Tom
--   --   Door needed to utility room
--   --   Trim out garage. George
--   --   This back patio has steps leading off both sides
--   --   Driveway has pretty nasty tire tracks running through it pressure wash
--   --   Kate, there is a French model fridge in this garage
--   --   Finish backroom drywall
--   --   Bit of drywall repairs needed to pantry door Drywall
--   --   Can we flatten out and re-seed side yard? Pettit
--   --   Add trim in now that cabinets have been installed in kitchen and bathrooms George
--   --   Possible scuff on one of the cabinets nearest the refrigerator Jill will check it out
--   --   Utility room room door needed needs to be installed
--   --   Large scratch on master vanity door Jill will look and let Fred know
--   --   Pocket door is crooked The door is still crooked, although the frame is repaired. 11/30
--   --   Floor needed in back bonus room Carpet
--   --   Paint doors and then install flooring and back bonus room and bath
--   --   Raised dining room chandelier to appropriate height Electrician
--   --   Few lightbulbs needed Jill
--   --   Kitchen faucet and bonus bathroom need plumbing installed
--   --   Trim out the garage - really
--   --   Towel holder rings need installed Joe
--   --   Need all mirrors Joe
--   --   Need all shelving Joe
--   --   Bonus bathroom needs plumbing installed
--   --   Remove stuff from driveway
--   --   Cover carpet Jill
--   --   Trim doors to slide over carpet easily Jorge
--   --   Was upgraded pad installed?
--   --   Glue needs removed off of bonus bathtub Jill
--   --   Few shelves needed Paul
--   --   Shoe molding needed in bonus ba5h Jorge
--   --   CODED LOCKBOX 5757
--   --   Whiteboard needed on back patio Tom
--   --   Touchup painting needed throughout Painters
--   --   Whiteboard needed on back deck Tom
--   --   Screens needed Jill
--   --   HVAC is not on 11/30 Tom
--   --   Paint concrete below back deck Painters
--   --   Vent cover missing on the microwave vent outside Mast & Brunk - Jason
--   --   Receptacle cover needed outside of pantry Electrician
--   --   Few blemishes on steps - need repainting Johanna
--   --   Floor trim missing in small bedroom closet George
--   --   Remove black marks in hall bath tub Jill
--   --   Remove whiteboard in garage Jill
--   --   Broken garage door inside component Davenport
--   --   Clean debris off driveway Jill
--   --   Separated flooring on back bonus room Denny
--   --   Install missing screens - master bedroom Jill has them, needs access
--   --   Transition strips - are they the correct color? Denny
--   --   Paint touch up Painter
--   --   Leave extra paint Painter
--   --   Connect garage door to track Davenport
--   --   Pressure wash driveway
--   --   Missing light bulb
--   --   Large crack in steps Joanna going by to take a look 12/23
-- -- Ratified Contract? (0)  09.24.2024    
-- -- $2500 Deposit Received (0)  10.03.2024     $5000
-- -- Association Packet Requested (0)  09.24.2024    
-- -- Association Packet Received (0)  10.04.2024    
-- -- Selections Meeting (0)  10.03.2024    
-- -- Selections Sheet Signed (0)  10.03.2024    
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  10.03.2024    
-- -- Deposit For Upgrades Received (0)  10.03.2024    
-- -- Building Permit (30)  04.18.2024    
-- -- Order Roof & Floor Trusses (1)  07.08.2024    
-- -- Order Windows & Doors (0)  07.20.2024    
-- -- Stake Out Home (1)  04.18.2024    
-- -- Excavate (2)  04.18.2024    
-- -- Inspection (Footers) (1)  04.18.2024    
-- -- Inspection (Concrete Wall) (1)  04.18.2024    
-- -- Pour Footers (1) *   04.18.2024    
-- -- Set Forms (2)  04.18.2024    
-- -- Pour Foundation Walls (1)  04.18.2024    
-- -- Plumb Slab (2)  04.18.2024    
-- -- Inspection (Plumbing Under Slab) (1)  04.25.2024    
-- -- Inspection (Conduit Under Slab) (1)  04.25.2024    
-- -- Prepare Slab (1)  04.25.2024    
-- -- Inspection (Slab) (1)  04.25.2024    
-- -- Inspection (Drain Tile) (0)  04.25.2024    
-- -- Pour Slab (1) *   04.25.2024    
-- -- Settlement Agent Confirmed (0)  10.04.2024    
-- -- Framing I (9)  05.16.2024    
-- -- Order Steps (0)  07.08.2024    
-- -- Order Tubs / Showers (0)  07.08.2024    
-- -- Framing II (8)  07.08.2024    
-- -- Framing III (8) *   07.08.2024    
-- -- Verify Window & Roof Structure (0)  07.08.2024    
-- -- Install Stairs (0)  07.08.2024    
-- -- Windows & Doors (0) *   08.14.2024    
-- -- House Number and Status in Window (0)  07.20.2024    
-- -- Roofing (0) *   07.15.2024    
-- -- Order Cabinets (0)  10.14.2024    
-- -- Order Appliances (0)  08.12.2024    
-- -- Deck (0)  09.04.2024    
-- -- Gutters (0)  09.04.2024    
-- -- Driveway (0) *   09.11.2024    
-- -- Patio (0)  09.15.2024    
-- -- Privacy Divider / Fence (0)  09.04.2024    
-- -- Sod / Seed / Landscaping (0)  10.30.2024    
-- -- HVAC Rough In (4)  07.20.2024    
-- -- Inspection (Rough In HVAC) (1)  08.03.2024    
-- -- Rough In Microwave Vent (0)  07.20.2024    
-- -- Plumbing Rough In (4)  07.24.2024     Almost completed. 7/20
-- -- Inspection (Rough In Plumbing) (1)  08.03.2024    
-- -- Electric Rough In (4)  08.03.2024     In process 7/24
-- -- Inspection (Rough In Electric) (1)  08.03.2024     likely Monday 7/29 for inspection
-- -- Inspection (Deck Piers) (0)  10.30.2024    
-- -- Inspection (Framing) (1) *   08.03.2024    
-- -- Exterior Vinyl (0) *   09.04.2024    
-- -- Exterior Stone (0)  09.04.2024    
-- -- Insulation (2) *   08.03.2024    
-- -- Inspection (Insulation) (1)  08.15.2024    
-- -- Inspection (Electric Service) (0)  09.26.2024    
-- -- Set Electric Meter (0) *   10.25.2024    
-- -- Inspection (Main Sewer Line) (0)  04.04.2024    
-- -- Inspection (Main Water Line) (0)  04.04.2024    
-- -- Order Interior Doors & Trim (0)  08.15.2024    
-- -- Drywall (Hang) (4) *   08.18.2024     In process 8/14
-- -- Loan Approval (0)  12.09.2024     USDA
-- -- Deed Preparation (0)  11.04.2024    
-- -- Drywall (Tape, Block, Skim, Sand) (6) *   08.28.2024     In process 8/24
-- -- Paint 1 (1)  08.28.2024    
-- -- Garage Door (0) *   10.06.2024    
-- -- House Numbers (0)  10.30.2024    
-- -- Mailbox (0)  11.16.2024    
-- -- Cabinet Installation (2) *   11.02.2024     Install 10/31
-- -- Granite Installation (1) *   11.16.2024     Thu, Nov 14
-- -- Interior Trim - Install (3) *   10.23.2024     In process 10/19
-- -- Order Plumbing / Lighting Fixtures (0)  09.26.2024    
-- -- Interior Trim - Paint (1)  10.30.2024    
-- -- Luxury Vinyl Plank (3) *   10.30.2024    
-- -- Luxury Vinyl Tile (0)  10.30.2024    
-- -- Paint 2 (3)  11.13.2024    
-- -- Cover Floors (1)  11.23.2024    
-- -- Deliver Plumbing / Lighting Fixtures (0)  11.07.2024    
-- -- Shoe Moulding (0)  11.13.2024    
-- -- Shelving, Door Knobs, Fire Extinguisher (0) *   11.30.2024     In process 11/23
-- -- Install Coded Lockbox (add extra keys) (0)  11.24.2024    
-- -- Pay Water / Sewer Taps (0)  09.26.2024    
-- -- Set Water Meter (0) *   09.30.2024    
-- -- Electric Trim Out (3)  11.23.2024     In process 11/16
-- -- Ceiling Fans (0)  11.16.2024    
-- -- HVAC Trim Out (1)  11.23.2024    
-- -- Blower Door Test (1)  11.23.2024    
-- -- Plumbing Trim Out (2)  11.16.2024     In process 11/16
-- -- Install Appliances (0) *   11.23.2024    
-- -- Paint 3 (2) *   11.16.2024     In process 11/13
-- -- Carpet (2)  11.23.2024    
-- -- Appraiser Confirms Construction Completion (0)  12.05.2024     Josh Collins, Tuesday, Dec 3, 9:30 AM
-- -- Inspection (Final HVAC) (1)  11.23.2024    
-- -- Inspection (Final Plumbing) (1)  11.23.2024    
-- -- Inspection (Final Electric) (1)  11.23.2024    
-- -- Inspection (Final Building) (2) *   11.23.2024     Fri, Nov 22
-- -- Pre Walk Through (0)  12.02.2024    
-- -- Stain Hardwood Stairs (1)  11.23.2024     In process 11/20
-- -- Cleaning (1)  12.07.2024     Almost complete 12/4
-- -- Certificate of Occupancy (1) *   11.27.2024    
-- -- C.O. to Lender (0)  11.27.2024    
-- -- Schedule Closing (0)  12.19.2024    
-- -- Buyer Walk Through (1)  12.19.2024     Jill to send document to Kate and Scott
-- -- Payment for Upgrades (0)  12.19.2024    
-- -- Keys to Settlement Agent (0)  12.02.2024    
-- -- Review Settlement Statement (0)  12.19.2024    
-- -- Jerry Signs Closing Documents (0)  12.26.2024    
-- -- Request Trash Tote From POA Manager (0)  12.02.2024    
-- -- Closing (1)  12.26.2024     Brittany @ West View Title
-- -- Remove Coded Lockbox (0)  12.21.2024