37 ADDR
CONGERS-2 - 57  ::  1362 Appaloosa Court
[ BUILD: 20231962 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
TO DO
---
UPGRADES
---
CRITICAL PATH
---
TO DO - COMPLETED OR DELETED
Broken primary bedroom window On order
Deadbolt is missing on back patio door
Driveway is expanded
Does the basement patio deck need railings? yes
Finish back room Drywall stocked 10/23
Adding upgraded refrigerator?
Bonus bathroom needs bathtub
Patch rear concrete square that’s been cut out Tom
Door needed to utility room
Trim out garage. George
This back patio has steps leading off both sides
Driveway has pretty nasty tire tracks running through it pressure wash
Kate, there is a French model fridge in this garage
Finish backroom drywall
Bit of drywall repairs needed to pantry door Drywall
Can we flatten out and re-seed side yard? Pettit
Add trim in now that cabinets have been installed in kitchen and bathrooms George
Possible scuff on one of the cabinets nearest the refrigerator Jill will check it out
Utility room room door needed needs to be installed
Large scratch on master vanity door Jill will look and let Fred know
Pocket door is crooked The door is still crooked, although the frame is repaired. 11/30
Floor needed in back bonus room Carpet
Paint doors and then install flooring and back bonus room and bath
Raised dining room chandelier to appropriate height Electrician
Few lightbulbs needed Jill
Kitchen faucet and bonus bathroom need plumbing installed
Trim out the garage - really
Towel holder rings need installed Joe
Need all mirrors Joe
Need all shelving Joe
Bonus bathroom needs plumbing installed
Remove stuff from driveway
Cover carpet Jill
Trim doors to slide over carpet easily Jorge
Was upgraded pad installed?
Glue needs removed off of bonus bathtub Jill
Few shelves needed Paul
Shoe molding needed in bonus ba5h Jorge
CODED LOCKBOX 5757
Whiteboard needed on back patio Tom
Touchup painting needed throughout Painters
Whiteboard needed on back deck Tom
Screens needed Jill
HVAC is not on 11/30 Tom
Paint concrete below back deck Painters
Vent cover missing on the microwave vent outside Mast & Brunk - Jason
Receptacle cover needed outside of pantry Electrician
Few blemishes on steps - need repainting Johanna
Floor trim missing in small bedroom closet George
Remove black marks in hall bath tub Jill
Remove whiteboard in garage Jill
Broken garage door inside component Davenport
Clean debris off driveway Jill
Separated flooring on back bonus room Denny
Install missing screens - master bedroom Jill has them, needs access
Transition strips - are they the correct color? Denny
Paint touch up Painter
Leave extra paint Painter
Connect garage door to track Davenport
Pressure wash driveway
Missing light bulb
Large crack in steps Joanna going by to take a look 12/23
UPGRADES - COMPLETED
    Finished Bonus Room Behind Garage (carpet, closet, roughed in bathroom)  
    Finished Full Bathroom in Bonus Room (luxury vinyl tile, 24" vanity)  
    Expanded Driveway  
    Luxury Vinyl Plank in Upstairs Hallway and Bedrooms  
    Painted Carpet Grade Stairs to Bedroom Level  
    Upgrades included in contract price  
CRITICAL PATH - COMPLETED
-- -- Ratified Contract? (0)  09.24.2024    
-- -- $2500 Deposit Received (0)  10.03.2024     $5000
-- -- Association Packet Requested (0)  09.24.2024    
-- -- Association Packet Received (0)  10.04.2024    
-- -- Selections Meeting (0)  10.03.2024    
-- -- Selections Sheet Signed (0)  10.03.2024    
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  10.03.2024    
-- -- Deposit For Upgrades Received (0)  10.03.2024    
-- -- Building Permit (30) *   04.18.2024    
-- -- Order Roof & Floor Trusses (1)  07.08.2024    
-- -- Order Windows & Doors (0)  07.20.2024    
-- -- Stake Out Home (1)  04.18.2024    
-- -- Excavate (2)  04.18.2024    
-- -- Inspection (Footers) (1)  04.18.2024    
-- -- Inspection (Concrete Wall) (1)  04.18.2024    
-- -- Pour Footers (1) *   04.18.2024    
-- -- Set Forms (2)  04.18.2024    
-- -- Pour Foundation Walls (1)  04.18.2024    
-- -- Plumb Slab (2)  04.18.2024    
-- -- Inspection (Plumbing Under Slab) (1)  04.25.2024    
-- -- Inspection (Conduit Under Slab) (1)  04.25.2024    
-- -- Prepare Slab (1)  04.25.2024    
-- -- Inspection (Slab) (1)  04.25.2024    
-- -- Inspection (Drain Tile) (0)  04.25.2024    
-- -- Pour Slab (1) *   04.25.2024    
-- -- Settlement Agent Confirmed (0)  10.04.2024    
-- -- Framing I (9)  05.16.2024    
-- -- Order Steps (0)  07.08.2024    
-- -- Order Tubs / Showers (0)  07.08.2024    
-- -- Framing II (8)  07.08.2024    
-- -- Framing III (8) *   07.08.2024    
-- -- Verify Window & Roof Structure (0)  07.08.2024    
-- -- Install Stairs (0) *   07.08.2024    
-- -- Windows & Doors (0) *   08.14.2024    
-- -- House Number and Status in Window (0)  07.20.2024    
-- -- Roofing (0) *   07.15.2024    
-- -- Order Cabinets (0)  10.14.2024    
-- -- Order Appliances (0)  08.12.2024    
-- -- Deck (0)  09.04.2024    
-- -- Gutters (0)  09.04.2024    
-- -- Driveway (0) *   09.11.2024    
-- -- Patio (0)  09.15.2024    
-- -- Privacy Divider / Fence (0) *   09.04.2024    
-- -- Sod / Seed / Landscaping (0)  10.30.2024    
-- -- HVAC Rough In (4)  07.20.2024    
-- -- Rough In Microwave Vent (0)  07.20.2024    
-- -- Plumbing Rough In (4)  07.24.2024     Almost completed. 7/20
-- -- Electric Rough In (4)  08.03.2024     In process 7/24
-- -- Inspection (Rough In HVAC) (1)  08.03.2024    
-- -- Inspection (Rough In Plumbing) (1)  08.03.2024    
-- -- Inspection (Rough In Electric) (1)  08.03.2024     likely Monday 7/29 for inspection
-- -- Inspection (Framing) (1) *   08.03.2024    
-- -- Inspection (Deck Piers) (0)  10.30.2024    
-- -- Exterior Vinyl (0) *   09.04.2024    
-- -- Exterior Stone (0)  09.04.2024    
-- -- Insulation (2) *   08.03.2024    
-- -- Inspection (Insulation) (1)  08.15.2024    
-- -- Inspection (Electric Service) (0)  09.26.2024    
-- -- Set Electric Meter (0) *   10.25.2024    
-- -- Inspection (Main Sewer Line) (0)  04.04.2024    
-- -- Inspection (Main Water Line) (0)  04.04.2024    
-- -- Order Interior Doors & Trim (0)  08.15.2024    
-- -- Drywall (Hang) (4) *   08.18.2024     In process 8/14
-- -- Loan Approval (0)  12.09.2024     USDA
-- -- Deed Preparation (0)  11.04.2024    
-- -- Drywall (Tape, Block, Skim, Sand) (6) *   08.28.2024     In process 8/24
-- -- Paint 1 (1)  08.28.2024    
-- -- Garage Door (0)  10.06.2024    
-- -- House Numbers (0)  10.30.2024    
-- -- Mailbox (0)  11.16.2024    
-- -- Cabinet Installation (2) *   11.02.2024     Install 10/31
-- -- Granite Installation (1) *   11.16.2024     Thu, Nov 14
-- -- Interior Trim - Install (3) *   10.23.2024     In process 10/19
-- -- Order Plumbing / Lighting Fixtures (0)  09.26.2024    
-- -- Interior Trim - Paint (1)  10.30.2024    
-- -- Luxury Vinyl Plank (3) *   10.30.2024    
-- -- Luxury Vinyl Tile (0)  10.30.2024    
-- -- Paint 2 (3)  11.13.2024    
-- -- Cover Floors (0)  11.23.2024    
-- -- Deliver Plumbing / Lighting Fixtures (0)  11.07.2024    
-- -- Shoe Moulding (0)  11.13.2024    
-- -- Shelving, Door Knobs, Fire Extinguisher (1) *   11.30.2024     In process 11/23
-- -- Install Coded Lockbox (add extra keys) (0)  11.24.2024    
-- -- Pay Water / Sewer Taps (0)  09.26.2024    
-- -- Set Water Meter (1) *   09.30.2024    
-- -- Electric Trim Out (3) *   11.23.2024     In process 11/16
-- -- Ceiling Fans (0)  11.16.2024    
-- -- HVAC Trim Out (1) *   11.23.2024    
-- -- Blower Door Test (1)  11.23.2024    
-- -- Plumbing Trim Out (2) *   11.16.2024     In process 11/16
-- -- Install Appliances (0) *   11.23.2024    
-- -- Paint 3 (2) *   11.16.2024     In process 11/13
-- -- Carpet (2)  11.23.2024    
-- -- Appraiser Confirms Construction Completion (0)  12.05.2024     Josh Collins, Tuesday, Dec 3, 9:30 AM
-- -- Inspection (Final HVAC) (0)  11.23.2024    
-- -- Inspection (Final Plumbing) (0)  11.23.2024    
-- -- Inspection (Final Electric) (0)  11.23.2024    
-- -- Inspection (Final Building) (4) *   11.23.2024     Fri, Nov 22
-- -- Pre Walk Through (0)  12.02.2024    
-- -- Stain Hardwood Stairs (1) *   11.23.2024     In process 11/20
-- -- Cleaning (1)  12.07.2024     Almost complete 12/4
-- -- Certificate of Occupancy (1) *   11.27.2024    
-- -- C.O. to Lender (0)  11.27.2024    
-- -- Schedule Closing (0)  12.19.2024    
-- -- Buyer Walk Through (1) *   12.19.2024     Jill to send document to Kate and Scott
-- -- Payment for Upgrades (0)  12.19.2024    
-- -- Keys to Settlement Agent (0)  12.02.2024    
-- -- Review Settlement Statement (0)  12.19.2024    
-- -- Jerry Signs Closing Documents (0)  12.26.2024    
-- -- Request Trash Tote From POA Manager (0)  12.02.2024    
-- -- Closing (1)  12.26.2024     Brittany @ West View Title
-- -- Remove Coded Lockbox (0)  12.21.2024