CONGERS-2 - 58  ::  1358 Appaloosa Court
[ BUILD: 20231963 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
TO DO
---
UPGRADES
---
CRITICAL PATH
---
TO DO - COMPLETED OR DELETED
12 x 18 deck is here
Make sure deck is really 12 x 18
Missing deck board
Few blemishes on cabinet fronts. Mainly drawer and left cabinet front. Jill has patched them 9/15
Tell buyer when to schedule an inspection
Cover carpet
Doors are going to need to be trimmed down to slide over carpet easily George
Missing one master towel bar
Trim garage
Oven needs to be pushed into place after plug is installed Tom
Pretty large drywall hole and stairwell
Door needed to utility room
Trim out garage
Install master bedroom closet door George
Needs front door locks and back patio door lock installed Paul
Hallway lights are upside down Electrician
Mirrors needed Paul
Need a few light bulbs Jill
Light needed in powder bathroom after silly sink without cabinet
Doorbell needs installed electrician
Need brown electrical covers and outlets for kitchen island Jill
Install attic cover
CODED LOCKBOX 5858
Home Inspection - Mon, Nov 11 at 9AM
Radon test Friday 12PM until Monday
Do you want to patch the holes in the basement concrete?
Is there a missing piece of insulation in the roughed-in bathroom in the basement?
Install screens Jill
Missing a few lightbulbs Jill
Hook up heat pump
Caulk side splashes Painter
Small hole needs trim outside of master bedroom Painter or George
Outlet too close to master mirror Electrician
Trim needed in front of bathtub and shower George
Few vents are not set correctly in flooring
Quarter round needed in closet George
Home Inspection Monday, Nov 11 at 9AM
Cable cover needed Tom (garage)
Final few paint touchups needed before final walk-through Painters
Needs patio door screen
Clean spots off granite Jill
fill holes bonus room floor Tom
cut hole for future tub in bonus bath concrete Cut concrete
fix floor register in laundry room Tom
secure fan remote to wall in mastr need better anchors
address garage door hinges- see report the door does not close
Cover cable box Jill
UPGRADES - COMPLETED
    Expanded Driveway  
    12 x 18 deck  
    Living Room ceiling fan  
    Amendment to increase price by $4,420  
CRITICAL PATH - COMPLETED
-- -- Ratified Contract? (0)  05.16.2024    
-- -- $2500 Deposit Received (0)  05.23.2024    
-- -- Association Packet Requested (0)  05.16.2024    
-- -- Association Packet Received (0)  05.18.2024    
-- -- Selections Meeting (0)  06.05.2024    
-- -- Selections Sheet Signed (0)  06.07.2024     6/5: sent to buyers
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  06.08.2024     6/8: sent to Jerry
-- -- Deposit For Upgrades Received (0)  06.08.2024    
-- -- Building Permit (30) *   04.18.2024    
-- -- Order Roof & Floor Trusses (1)  07.08.2024    
-- -- Order Windows & Doors (0)  07.20.2024    
-- -- Stake Out Home (1)  04.18.2024    
-- -- Excavate (2)  04.18.2024    
-- -- Inspection (Footers) (1)  04.18.2024    
-- -- Inspection (Concrete Wall) (1)  04.18.2024    
-- -- Pour Footers (1) *   04.18.2024    
-- -- Set Forms (2)  04.18.2024    
-- -- Pour Foundation Walls (1)  04.18.2024    
-- -- Plumb Slab (2)  04.18.2024    
-- -- Inspection (Plumbing Under Slab) (1)  04.25.2024    
-- -- Inspection (Conduit Under Slab) (1)  04.25.2024    
-- -- Prepare Slab (1)  04.25.2024    
-- -- Inspection (Slab) (1)  04.25.2024    
-- -- Inspection (Drain Tile) (0)  04.25.2024    
-- -- Pour Slab (1) *   04.25.2024    
-- -- Settlement Agent Confirmed (0)  07.24.2024     sent
-- -- Framing I (9)  05.16.2024    
-- -- Order Steps (0)  07.08.2024    
-- -- Order Tubs / Showers (0)  07.08.2024    
-- -- Framing II (8)  07.08.2024    
-- -- Framing III (8) *   07.08.2024    
-- -- Verify Window & Roof Structure (0)  07.08.2024    
-- -- Install Stairs (0) *   07.08.2024    
-- -- Windows & Doors (0) *   07.20.2024    
-- -- House Number and Status in Window (0)  07.20.2024    
-- -- Roofing (0) *   07.15.2024    
-- -- Order Cabinets (0)  08.06.2024    
-- -- Order Appliances (0)  08.12.2024    
-- -- Deck (0)  08.18.2024    
-- -- Gutters (0)  09.04.2024    
-- -- Driveway (0) *   09.15.2024    
-- -- Patio (0)  09.04.2024    
-- -- Privacy Divider / Fence (0) *   09.15.2024    
-- -- Sod / Seed / Landscaping (0)  10.23.2024    
-- -- HVAC Rough In (4)  07.20.2024    
-- -- Rough In Microwave Vent (0)  09.11.2024    
-- -- Plumbing Rough In (4)  07.24.2024     In process 7/20
-- -- Electric Rough In (4)  08.03.2024     In process 7/24
-- -- Inspection (Rough In HVAC) (1)  08.03.2024    
-- -- Inspection (Rough In Plumbing) (1)  08.03.2024    
-- -- Inspection (Rough In Electric) (1)  08.03.2024    
-- -- Inspection (Framing) (1) *   08.03.2024    
-- -- Inspection (Deck Piers) (0)  09.11.2024    
-- -- Exterior Vinyl (0) *   09.04.2024    
-- -- Exterior Stone (0)  09.04.2024    
-- -- Insulation (2) *   08.03.2024    
-- -- Inspection (Insulation) (1)  08.14.2024    
-- -- Inspection (Electric Service) (0)  09.26.2024    
-- -- Set Electric Meter (0) *   10.25.2024    
-- -- Inspection (Main Sewer Line) (0)  04.04.2024    
-- -- Inspection (Main Water Line) (0)  04.04.2024    
-- -- Order Interior Doors & Trim (0)  08.15.2024    
-- -- Drywall (Hang) (4) *   08.14.2024     In process 8/10
-- -- Loan Approval (0)  09.26.2024     Ryan Charles, Alcova Mortgage (96.5% FHA)
-- -- Deed Preparation (0)  09.26.2024    
-- -- Drywall (Tape, Block, Skim, Sand) (6) *   08.28.2024     In process 8/24
-- -- Paint 1 (1)  08.28.2024    
-- -- Garage Door (0)  10.06.2024    
-- -- House Numbers (0)  10.30.2024    
-- -- Mailbox (0)  11.16.2024     Install
-- -- Cabinet Installation (2) *   09.04.2024     Delivered 8/28, Installed 8/29
-- -- Granite Installation (1) *   09.11.2024    
-- -- Interior Trim - Install (3) *   09.21.2024     In process 9/18
-- -- Order Plumbing / Lighting Fixtures (0)  09.26.2024    
-- -- Interior Trim - Paint (1)  09.21.2024    
-- -- Luxury Vinyl Plank (3) *   09.25.2024    
-- -- Luxury Vinyl Tile (0)  09.21.2024    
-- -- Paint 2 (3)  09.04.2024    
-- -- Cover Floors (0)  09.28.2024    
-- -- Deliver Plumbing / Lighting Fixtures (0)  09.26.2024    
-- -- Shoe Moulding (0)  10.05.2024     In process 10/2
-- -- Shelving, Door Knobs, Fire Extinguisher (1) *   10.16.2024     In process 10/9. Needs front door knobs, and shelving installed.
-- -- Install Coded Lockbox (add extra keys) (0)  10.31.2024    
-- -- Pay Water / Sewer Taps (0)  09.26.2024    
-- -- Set Water Meter (1) *   09.30.2024    
-- -- Electric Trim Out (3) *   10.23.2024    
-- -- Ceiling Fans (0)  10.23.2024    
-- -- HVAC Trim Out (1) *   10.16.2024    
-- -- Blower Door Test (1)  11.07.2024    
-- -- Plumbing Trim Out (2) *   11.06.2024     In process 10/30
-- -- Install Appliances (0) *   10.05.2024     Current Delivery/Install Date 9/20
-- -- Paint 3 (2) *   10.12.2024    
-- -- Carpet (2)  09.25.2024    
-- -- Appraiser Confirms Construction Completion (0)  11.13.2024    
-- -- Inspection (Final HVAC) (0)  11.09.2024    
-- -- Inspection (Final Plumbing) (0)  11.09.2024    
-- -- Inspection (Final Electric) (0)  11.09.2024    
-- -- Inspection (Final Building) (4) *   11.09.2024     Thurs, Nov 7
-- -- Pre Walk Through (0)  11.13.2024    
-- -- Stain Hardwood Stairs (1) *   11.06.2024     In process 11/2
-- -- Cleaning (1)  11.13.2024     will be done 11/11
-- -- Certificate of Occupancy (1) *   11.14.2024    
-- -- C.O. to Lender (0)  11.14.2024    
-- -- Schedule Closing (0)  11.13.2024    
-- -- Buyer Walk Through (1) *   11.13.2024     kate setting up
-- -- Payment for Upgrades (0)  11.11.2024    
-- -- Keys to Settlement Agent (0)  11.13.2024    
-- -- Review Settlement Statement (0)  11.13.2024    
-- -- Jerry Signs Closing Documents (0)  09.18.2024    
-- -- Request Trash Tote From POA Manager (0)  11.13.2024    
-- -- Closing (1)  11.21.2024     Brittany @ West View Title
-- -- Remove Coded Lockbox (0)  11.21.2024