CONGERS-2 - 65  ::  1373 Appaloosa Court
[ BUILD: 20240008 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS


Wednesday (Apr 23)    show all photos
--   --   Stone or paint is needed at the corner front, right Dale
--   --   12 x 12 deck is planned for this townhouse
--   --   Install back patio door
--   --   A few pieces of insulation missing in garage?
--   --   U/C sticker
--   --   Finish drywall now that stairs are installed
--   --   Bonus room and bonus bathroom are missing drywall
--   --   Bonus bathroom needs a bathtub
--   --   Bonus bath needs toilet Tub
--   --   Bonus bath needs tub Needs installed 9/21
--   --   Pretty large bulge in the driveway on the staircase leading to the main level
--   --   Finish bonus room trim out so drywall can be installed In process 10/16
--   --   Make sure bathroom drywall is completed as that needs a cabinet as well
--   --   Bonus bathroom vanity is in the living room Thurs, Oct 31
--   --   Bonus room needs paint
--   --   There is an upgraded refrigerator in this kitchen
--   --   Install basement bathroom vanity
--   --   Large amount of paint overspray on bonus bathroom vanity Painter
--   --   Utility room door hinges are silver instead of black, like the rest of the house Jill
--   --   Fix siding where electrical outlet had to be moved over Davenport
--   --   Deck post appears to be damaged? Or flawed? Brace - Tom
--   --   Stone needed between driveways
--   --   Few knobs needed in bonus Joe or Paul
--   --   remove paint off rear of the home Jill
--   --   Install dishwasher in kitchen
--   --   Small ding in refrigerator door Kate is communicating with Maya. There is no ding in fridge here...is there?
--   --   Pool on the stairwell going to second level needs patched
--   --   Fill in gap in drywall next to stairs going up to main level Drywaller
--   --   Second coat of paint needed on front door. Painter
--   --   CODED LOCKBOX 6565
--   --   Home Inspection - Thursday, Dec 19 at 1PM Benjamin Meredith
--   --   Bit of glue needs removed in bonus bath tub Jill
--   --   Paint front and rear door trims Joanna
--   --   Adjust deck door deadbolt Paul
--   --   Adjust weatherstripping on front door Jeremiah
--   --   Install additional fasteners to deck joist Tom
--   --   Garage drywall hole near opener Joanna
--   --   Adjust hot water heater Tom
--   --   Adjust powder bath door so it’s quiet Jill
--   --   Gap at bonus room window Joanna
--   --   Tighten bath faucet in basement Munzur
--   --   Install overflow on hall bath Munzur
--   --   Small chip in hall bath Jill- Kevin is coming n the morning of Monday the 30th
--   --   Install screens Jill - waiting on last few to arrive. Master bedroom needed.
--   --   Paint tops and bottoms of doors Joanna
--   --   Adjust rear gutter Tom
--   --   Secure grounding in front of the house Electrician
--   --   Closing Thursday, January 2
--   --   Garage needs painted when it’s cleaned all the way out Painting
--   --   Repair drywall at washing machine
--   --   Mark in ceiling of kitchen from water
--   --   Water marks above toilet in powder room
--   --   Do we know when tenants are moving in? Floors could use a good cleaning after repairs
-- -- Ratified Contract? (0)  08.25.2024    
-- -- $2500 Deposit Received (0)  09.06.2024    
-- -- Association Packet Requested (0)  08.25.2024    
-- -- Association Packet Received (0)  08.30.2024    
-- -- Selections Meeting (0)  09.06.2024    
-- -- Selections Sheet Signed (0)  09.17.2024     9/6: sent to Renee
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  09.28.2024     9/26: sent to Jerry
-- -- Deposit For Upgrades Received (0)  09.27.2024    
-- -- Building Permit (30)  04.18.2024    
-- -- Order Roof & Floor Trusses (1)  07.08.2024    
-- -- Order Windows & Doors (0)  08.03.2024    
-- -- Stake Out Home (1)  04.18.2024    
-- -- Excavate (2)  04.18.2024    
-- -- Inspection (Footers) (1)  04.18.2024    
-- -- Inspection (Concrete Wall) (1)  04.18.2024    
-- -- Pour Footers (1) *   04.18.2024    
-- -- Set Forms (2)  05.06.2024    
-- -- Pour Foundation Walls (1)  05.06.2024    
-- -- Plumb Slab (2)  05.13.2024    
-- -- Inspection (Plumbing Under Slab) (1)  05.23.2024    
-- -- Inspection (Conduit Under Slab) (1)  05.23.2024    
-- -- Prepare Slab (1)  05.23.2024    
-- -- Inspection (Slab) (1)  05.30.2024    
-- -- Inspection (Drain Tile) (0)  11.18.2024    
-- -- Pour Slab (1) *   05.30.2024    
-- -- Settlement Agent Confirmed (0)  10.03.2024     sent 9/27/2024
-- -- Framing I (9)  07.08.2024    
-- -- Order Steps (0)  08.03.2024    
-- -- Order Tubs / Showers (0)  08.03.2024    
-- -- Framing II (8)  07.08.2024    
-- -- Framing III (8) *   07.08.2024    
-- -- Verify Window & Roof Structure (0)  08.14.2024    
-- -- Install Stairs (0)  08.14.2024    
-- -- Windows & Doors (0) *   08.14.2024    
-- -- House Number and Status in Window (0)  08.14.2024    
-- -- Roofing (0) *   08.14.2024    
-- -- Order Cabinets (0)  09.08.2024    
-- -- Order Appliances (0)  08.12.2024    
-- -- Deck (0)  10.30.2024    
-- -- Gutters (0)  10.24.2024    
-- -- Driveway (0) *   10.19.2024    
-- -- Patio (0)  10.30.2024    
-- -- Privacy Divider / Fence (0)  11.13.2024    
-- -- Sod / Seed / Landscaping (0)  11.18.2024    
-- -- HVAC Rough In (4)  07.20.2024    
-- -- Inspection (Rough In HVAC) (1)  08.24.2024    
-- -- Rough In Microwave Vent (0)  08.03.2024    
-- -- Plumbing Rough In (4)  08.07.2024     In process 8/3
-- -- Inspection (Rough In Plumbing) (1)  08.24.2024    
-- -- Electric Rough In (4)  08.18.2024     In process 8/14
-- -- Inspection (Rough In Electric) (1)  08.24.2024    
-- -- Inspection (Deck Piers) (0)  11.05.2024    
-- -- Inspection (Framing) (1) *   08.24.2024    
-- -- Exterior Vinyl (0) *   10.05.2024    
-- -- Exterior Stone (0)  10.05.2024    
-- -- Insulation (2) *   08.24.2024    
-- -- Inspection (Insulation) (1)  09.07.2024    
-- -- Inspection (Electric Service) (0)  10.21.2024    
-- -- Set Electric Meter (0) *   10.25.2024    
-- -- Inspection (Main Sewer Line) (0)  10.14.2024    
-- -- Inspection (Main Water Line) (0)  10.14.2024    
-- -- Order Interior Doors & Trim (0)  10.14.2024    
-- -- Drywall (Hang) (4) *   09.07.2024     Stocked 9/4
-- -- Loan Approval (0)  11.05.2024     Cash
-- -- Deed Preparation (0)  11.05.2024    
-- -- Drywall (Tape, Block, Skim, Sand) (6) *   10.02.2024     In process 9/28. Needs sanding.
-- -- Paint 1 (1)  10.02.2024    
-- -- Garage Door (0) *   10.26.2024    
-- -- House Numbers (0)  11.16.2024    
-- -- Mailbox (0)  11.16.2024    
-- -- Cabinet Installation (2) *   10.09.2024     Install Oct 8
-- -- Granite Installation (1) *   10.12.2024    
-- -- Interior Trim - Install (3) *   11.02.2024     In process. Almost complete 10/30
-- -- Order Plumbing / Lighting Fixtures (0)  11.07.2024    
-- -- Interior Trim - Paint (1)  11.06.2024    
-- -- Luxury Vinyl Plank (3) *   11.13.2024     In process 11/9
-- -- Luxury Vinyl Tile (0)  11.13.2024     In process 11/9
-- -- Paint 2 (3)  11.23.2024    
-- -- Cover Floors (1)  11.30.2024    
-- -- Deliver Plumbing / Lighting Fixtures (0)  11.07.2024    
-- -- Shoe Moulding (0)  11.16.2024    
-- -- Shelving, Door Knobs, Fire Extinguisher (0) *   12.04.2024     In process 12/4
-- -- Install Coded Lockbox (add extra keys) (0)  12.14.2024    
-- -- Pay Water / Sewer Taps (0)  11.02.2024    
-- -- Set Water Meter (0) *   11.18.2024    
-- -- Electric Trim Out (3)  12.14.2024     In process 12/7
-- -- Ceiling Fans (0)  12.07.2024    
-- -- HVAC Trim Out (1)  12.14.2024    
-- -- Blower Door Test (1)  12.14.2024    
-- -- Plumbing Trim Out (2)  11.30.2024    
-- -- Install Appliances (0) *   11.23.2024     10/21
-- -- Paint 3 (2) *   11.23.2024    
-- -- Carpet (2)  11.09.2024    
-- -- Appraiser Confirms Construction Completion (0)  12.26.2024    
-- -- Inspection (Final HVAC) (1)  12.14.2024    
-- -- Inspection (Final Plumbing) (1)  12.14.2024    
-- -- Inspection (Final Electric) (1)  12.14.2024    
-- -- Inspection (Final Building) (2) *   12.14.2024    
-- -- Pre Walk Through (0)  12.23.2024    
-- -- Stain Hardwood Stairs (1)  12.21.2024     In process 12/18
-- -- Cleaning (1)  12.23.2024     In process 12/21
-- -- Certificate of Occupancy (1) *   12.20.2024    
-- -- C.O. to Lender (0)  12.26.2024    
-- -- Schedule Closing (0)  12.26.2024    
-- -- Buyer Walk Through (1)  01.02.2025     Mon, Dec 30 at 3:30 PM
-- -- Payment for Upgrades (0)  12.20.2024    
-- -- Keys to Settlement Agent (0)  12.20.2024    
-- -- Review Settlement Statement (0)  12.26.2024    
-- -- Jerry Signs Closing Documents (0)  12.30.2024    
-- -- Request Trash Tote From POA Manager (0)  12.26.2024    
-- -- Closing (1)  01.09.2025     Brittany @ West View Title
-- -- Remove Coded Lockbox (0)  01.06.2025