1 33 37 89 47 73 67 55 56 59 57 66 65 64 60 61 62 63 ADDR
CONGERS-2 - 65  ::  1373 Appaloosa Court
[ BUILD: 20240008 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS


Saturday (Nov 23)    show all photos
--   --   Stone or paint is needed at the corner front, right Dale
--   --   Large amount of paint overspray on bonus bathroom vanity Painter
--   --   Utility room door hinges are silver instead of black, like the rest of the house Jill
--   --   Fix siding where electrical outlet had to be moved over Davenport
--   --   Deck post appears to be damaged? Or flawed? Brace - Tom
--   --   Few knobs needed in bonus Joe or Paul
--   --   remove paint off rear of the home
--   --   Install dishwasher in kitchen
    Stained hardwood treads to bedroom level  
Wed    Nov 27      Cover Floors (1)      
Thu    Nov 28      Shelving, Door Knobs, Fire Extinguisher (0)       In process 11/23
Thu    Nov 28      Install Coded Lockbox (add extra keys) (0)      
Thu    Nov 28      Electric Trim Out (3)      
Tue    Dec 3      Ceiling Fans (0)      
Tue    Dec 3      HVAC Trim Out (1)      
Wed    Dec 4      Blower Door Test (1)      
Thu    Dec 5      Plumbing Trim Out (2)      
Mon    Dec 9      Appraiser Confirms Construction Completion (0)      
Mon    Dec 9      Inspection (Final HVAC) (1)      
Tue    Dec 10      Inspection (Final Plumbing) (1)      
Wed    Dec 11      Inspection (Final Electric) (1)      
Thu    Dec 12      Inspection (Final Building) (2) *       
Mon    Dec 16      Pre Walk Through (0)      
Mon    Dec 16      Stain Hardwood Stairs (1)      
Tue    Dec 17      Cleaning (1)      
Wed    Dec 18      Certificate of Occupancy (1) *       
Thu    Dec 19      C.O. to Lender (0)      
Thu    Dec 19      Schedule Closing (0)      
Thu    Dec 19      Buyer Walk Through (1)      
Fri    Dec 20      Payment for Upgrades (0)      
Fri    Dec 20      Keys to Settlement Agent (0)      
Fri    Dec 20      Review Settlement Statement (0)      
Fri    Dec 20      Jerry Signs Closing Documents (0)      
Fri    Dec 20      Request Trash Tote From POA Manager (0)      
Fri    Dec 20      Closing (1)       Brittany @ West View Title
Mon    Dec 23      Remove Coded Lockbox (0)      
--   --   12 x 12 deck is planned for this townhouse
--   --   Install back patio door
--   --   A few pieces of insulation missing in garage?
--   --   U/C sticker
--   --   Finish drywall now that stairs are installed
--   --   Bonus room and bonus bathroom are missing drywall
--   --   Bonus bathroom needs a bathtub
--   --   Bonus bath needs toilet Tub
--   --   Bonus bath needs tub Needs installed 9/21
--   --   Pretty large bulge in the driveway on the staircase leading to the main level
--   --   Finish bonus room trim out so drywall can be installed In process 10/16
--   --   Make sure bathroom drywall is completed as that needs a cabinet as well
--   --   Bonus bathroom vanity is in the living room Thurs, Oct 31
--   --   Bonus room needs paint
--   --   There is an upgraded refrigerator in this kitchen
--   --   Install basement bathroom vanity
--   --   Stone needed between driveways
-- -- Ratified Contract? (0)  08.25.2024    
    Stained hardwood treads to bedroom level  
-- -- $2500 Deposit Received (0)  09.06.2024    
-- -- Association Packet Requested (0)  08.25.2024    
-- -- Association Packet Received (0)  08.30.2024    
-- -- Selections Meeting (0)  09.06.2024    
-- -- Selections Sheet Signed (0)  09.17.2024     9/6: sent to Renee
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  09.28.2024     9/26: sent to Jerry
-- -- Deposit For Upgrades Received (0)  09.27.2024    
-- -- Building Permit (30)  04.18.2024    
-- -- Order Roof & Floor Trusses (1)  07.08.2024    
-- -- Order Windows & Doors (0)  08.03.2024    
-- -- Stake Out Home (1)  04.18.2024    
-- -- Excavate (2)  04.18.2024    
-- -- Inspection (Footers) (1)  04.18.2024    
-- -- Inspection (Concrete Wall) (1)  04.18.2024    
-- -- Pour Footers (1)  04.18.2024    
-- -- Set Forms (2)  05.06.2024    
-- -- Pour Foundation Walls (1)  05.06.2024    
-- -- Plumb Slab (2)  05.13.2024    
-- -- Inspection (Plumbing Under Slab) (1)  05.23.2024    
-- -- Inspection (Conduit Under Slab) (1)  05.23.2024    
-- -- Prepare Slab (1)  05.23.2024    
-- -- Inspection (Slab) (1)  05.30.2024    
-- -- Inspection (Drain Tile) (0)  11.18.2024    
-- -- Pour Slab (1) *   05.30.2024    
-- -- Settlement Agent Confirmed (0)  10.03.2024     sent 9/27/2024
-- -- Framing I (9)  07.08.2024    
-- -- Order Steps (0)  08.03.2024    
-- -- Order Tubs / Showers (0)  08.03.2024    
-- -- Framing II (8)  07.08.2024    
-- -- Framing III (8) *   07.08.2024    
-- -- Verify Window & Roof Structure (0)  08.14.2024    
-- -- Install Stairs (0)  08.14.2024    
-- -- Windows & Doors (0)  08.14.2024    
-- -- House Number and Status in Window (0)  08.14.2024    
-- -- Roofing (0)  08.14.2024    
-- -- Order Cabinets (0)  09.08.2024    
-- -- Order Appliances (0)  08.12.2024    
-- -- Deck (0)  10.30.2024    
-- -- Gutters (0)  10.24.2024    
-- -- Driveway (0)  10.19.2024    
-- -- Patio (0)  10.30.2024    
-- -- Privacy Divider / Fence (0)  11.13.2024    
-- -- Sod / Seed / Landscaping (0)  11.18.2024    
-- -- HVAC Rough In (4)  07.20.2024    
-- -- Inspection (Rough In HVAC) (1)  08.24.2024    
-- -- Rough In Microwave Vent (0)  08.03.2024    
-- -- Plumbing Rough In (4)  08.07.2024     In process 8/3
-- -- Inspection (Rough In Plumbing) (1)  08.24.2024    
-- -- Electric Rough In (4)  08.18.2024     In process 8/14
-- -- Inspection (Rough In Electric) (1)  08.24.2024    
-- -- Inspection (Deck Piers) (0)  11.05.2024    
-- -- Inspection (Framing) (1)  08.24.2024    
-- -- Exterior Vinyl (0) *   10.05.2024    
-- -- Exterior Stone (0)  10.05.2024    
-- -- Insulation (2)  08.24.2024    
-- -- Inspection (Insulation) (1)  09.07.2024    
-- -- Inspection (Electric Service) (0)  10.21.2024    
-- -- Set Electric Meter (0)  10.25.2024    
-- -- Inspection (Main Sewer Line) (0)  10.14.2024    
-- -- Inspection (Main Water Line) (0)  10.14.2024    
-- -- Order Interior Doors & Trim (0)  10.14.2024    
-- -- Drywall (Hang) (4) *   09.07.2024     Stocked 9/4
-- -- Loan Approval (0)  11.05.2024     Cash
-- -- Deed Preparation (0)  11.05.2024    
-- -- Drywall (Tape, Block, Skim, Sand) (6) *   10.02.2024     In process 9/28. Needs sanding.
-- -- Paint 1 (1)  10.02.2024    
-- -- Garage Door (0)  10.26.2024    
-- -- House Numbers (0)  11.16.2024    
-- -- Mailbox (0)  11.16.2024    
-- -- Cabinet Installation (2) *   10.09.2024     Install Oct 8
-- -- Granite Installation (1) *   10.12.2024    
-- -- Interior Trim - Install (3)  11.02.2024     In process. Almost complete 10/30
-- -- Order Plumbing / Lighting Fixtures (0)  11.07.2024    
-- -- Interior Trim - Paint (1)  11.06.2024    
-- -- Luxury Vinyl Plank (3) *   11.13.2024     In process 11/9
-- -- Luxury Vinyl Tile (0)  11.13.2024     In process 11/9
-- -- Paint 2 (3)  11.23.2024    
-- -- Deliver Plumbing / Lighting Fixtures (0)  11.07.2024    
-- -- Shoe Moulding (0)  11.16.2024    
-- -- Pay Water / Sewer Taps (0)  11.02.2024    
-- -- Set Water Meter (0)  11.18.2024    
-- -- Install Appliances (0) *   11.23.2024     10/21
-- -- Paint 3 (2) *   11.23.2024    
-- -- Carpet (2)  11.09.2024