Handle missing on upper cabinetry in kitchen |
Fred |
|
-- |
-- |
Garage door needs window grills |
Davenport |
|
|
|
Vinyl Plank in Upstairs Hallway and Bedroom ($2,900 cost included in contract price)
|
|
|
|
Stained Hardwood Treads to Bedroom Level ($1,890 cost included in contract price)
|
|
|
|
Expanded Driveway ($1,260 cost included in contract price)
|
|
|
|
Eggshell Finish Paint ($1,050 cost included in contract price)
|
|
|
|
Upgraded LVT upstairs Bathrooms
|
|
|
|
Level III Granite Salinas White in Kitchen
|
|
|
|
Level III Granite Salinas White in Up Baths
|
|
Wed |
Nov 27 |
Gutters (0) |
|
|
Wed |
Nov 27 |
Driveway (0) |
|
|
Wed |
Nov 27 |
Patio (0) |
|
|
Wed |
Nov 27 |
Privacy Divider / Fence (0) |
|
|
Wed |
Nov 27 |
Sod / Seed / Landscaping (0) |
|
|
Wed |
Nov 27 |
Set Electric Meter (0) |
|
|
Wed |
Nov 27 |
House Numbers (0) |
|
|
Wed |
Nov 27 |
Mailbox (0) |
|
|
Wed |
Nov 27 |
Granite Installation (1) * |
Wed, Dec 4 |
|
Thu |
Nov 28 |
Interior Trim - Install (3) |
|
|
Tue |
Dec 3 |
Order Plumbing / Lighting Fixtures (0) |
|
|
Tue |
Dec 3 |
Interior Trim - Paint (1) |
|
|
Wed |
Dec 4 |
Luxury Vinyl Plank (3) * |
|
|
Mon |
Dec 9 |
Luxury Vinyl Tile (0) |
|
|
Mon |
Dec 9 |
Paint 2 (3) |
|
|
Thu |
Dec 12 |
Cover Floors (1) |
|
|
Fri |
Dec 13 |
Shoe Moulding (0) |
|
|
Fri |
Dec 13 |
Shelving, Door Knobs, Fire Extinguisher (0) |
|
|
Fri |
Dec 13 |
Install Coded Lockbox (add extra keys) (0) |
|
|
Fri |
Dec 13 |
Pay Water / Sewer Taps (0) |
|
|
Fri |
Dec 13 |
Set Water Meter (0) |
|
|
Fri |
Dec 13 |
Electric Trim Out (3) |
|
|
Wed |
Dec 18 |
Ceiling Fans (0) |
|
|
Wed |
Dec 18 |
HVAC Trim Out (1) |
|
|
Thu |
Dec 19 |
Blower Door Test (1) |
|
|
Fri |
Dec 20 |
Plumbing Trim Out (2) |
|
|
Tue |
Dec 24 |
Install Appliances (0) * |
11/18 |
|
Tue |
Dec 24 |
Paint 3 (2) * |
|
|
Thu |
Dec 26 |
Carpet (2) |
|
|
Mon |
Dec 30 |
Appraiser Confirms Construction Completion (0) |
|
|
Mon |
Dec 30 |
Inspection (Final HVAC) (1) |
|
|
Tue |
Dec 31 |
Inspection (Final Plumbing) (1) |
|
|
Wed |
Jan 1 |
Inspection (Final Electric) (1) |
|
|
Thu |
Jan 2 |
Inspection (Final Building) (2) * |
|
|
Mon |
Jan 6 |
Pre Walk Through (0) |
|
|
Mon |
Jan 6 |
Stain Hardwood Stairs (1) |
|
|
Tue |
Jan 7 |
Cleaning (1) |
|
|
Wed |
Jan 8 |
Certificate of Occupancy (1) * |
|
|
Thu |
Jan 9 |
C.O. to Lender (0) |
|
|
Thu |
Jan 9 |
Schedule Closing (0) |
|
|
Thu |
Jan 9 |
Buyer Walk Through (1) |
|
|
Fri |
Jan 10 |
Payment for Upgrades (0) |
|
|
Fri |
Jan 10 |
Keys to Settlement Agent (0) |
|
|
Fri |
Jan 10 |
Review Settlement Statement (0) |
|
|
Fri |
Jan 10 |
Jerry Signs Closing Documents (0) |
|
|
Fri |
Jan 10 |
Request Trash Tote From POA Manager (0) |
|
|
Fri |
Jan 10 |
Closing (1) |
Brittany @ West View Title |
|
Mon |
Jan 13 |
Remove Coded Lockbox (0) |
|
|
|
-- |
-- |
Ratified Contract? (0) 06.17.2024 |
|
|
|
|
Vinyl Plank in Upstairs Hallway and Bedroom ($2,900 cost included in contract price)
|
|
|
|
Stained Hardwood Treads to Bedroom Level ($1,890 cost included in contract price)
|
|
|
|
Expanded Driveway ($1,260 cost included in contract price)
|
|
|
|
Eggshell Finish Paint ($1,050 cost included in contract price)
|
|
|
|
Upgraded LVT upstairs Bathrooms
|
|
|
|
Level III Granite Salinas White in Kitchen
|
|
|
|
Level III Granite Salinas White in Up Baths
|
|
-- |
-- |
$2500 Deposit Received (0) 06.19.2024 |
|
|
-- |
-- |
Association Packet Requested (0) 06.17.2024 |
|
|
-- |
-- |
Association Packet Received (0) 06.21.2024 |
|
|
-- |
-- |
Selections Meeting (0) 07.10.2024 |
|
|
-- |
-- |
Selections Sheet Signed (0) 07.20.2024 |
7/10: sent to Brandon for signatures |
|
-- |
-- |
Amendment for Upgrades (B,S,L,T,BCP) (0) 08.18.2024 |
7/28: sending new copy to Jerry |
|
-- |
-- |
Deposit For Upgrades Received (0) 07.25.2024 |
|
|
-- |
-- |
Building Permit (30) 04.18.2024 |
|
|
-- |
-- |
Order Roof & Floor Trusses (1) 08.22.2024 |
|
|
-- |
-- |
Order Windows & Doors (0) 09.22.2024 |
|
|
-- |
-- |
Stake Out Home (1) 04.18.2024 |
|
|
-- |
-- |
Excavate (2) 04.18.2024 |
|
|
-- |
-- |
Inspection (Footers) (1) 05.13.2024 |
|
|
-- |
-- |
Inspection (Concrete Wall) (1) 05.13.2024 |
|
|
-- |
-- |
Pour Footers (1) 04.25.2024 |
|
|
-- |
-- |
Set Forms (2) 05.13.2024 |
|
|
-- |
-- |
Pour Foundation Walls (1) 05.13.2024 |
|
|
-- |
-- |
Plumb Slab (2) 05.13.2024 |
|
|
-- |
-- |
Inspection (Plumbing Under Slab) (1) 07.08.2024 |
|
|
-- |
-- |
Inspection (Conduit Under Slab) (1) 07.08.2024 |
|
|
-- |
-- |
Prepare Slab (1) 07.08.2024 |
|
|
-- |
-- |
Inspection (Slab) (1) 07.08.2024 |
|
|
-- |
-- |
Inspection (Drain Tile) (0) 07.08.2024 |
|
|
-- |
-- |
Pour Slab (1) * 07.08.2024 |
|
|
-- |
-- |
Settlement Agent Confirmed (0) 07.28.2024 |
Sent 7/25/2024 |
|
-- |
-- |
Framing I (9) 08.22.2024 |
|
|
-- |
-- |
Order Steps (0) 09.15.2024 |
|
|
-- |
-- |
Order Tubs / Showers (0) 09.15.2024 |
|
|
-- |
-- |
Framing II (8) 09.12.2024 |
|
|
-- |
-- |
Framing III (8) * 09.12.2024 |
|
|
-- |
-- |
Verify Window & Roof Structure (0) 09.15.2024 |
|
|
-- |
-- |
Install Stairs (0) 09.15.2024 |
|
|
-- |
-- |
Windows & Doors (0) 10.02.2024 |
|
|
-- |
-- |
House Number and Status in Window (0) 10.03.2024 |
|
|
-- |
-- |
Roofing (0) 10.09.2024 |
|
|
-- |
-- |
Order Cabinets (0) 09.08.2024 |
|
|
-- |
-- |
Order Appliances (0) 08.12.2024 |
|
|
-- |
-- |
Deck (0) 11.13.2024 |
|
|
-- |
-- |
HVAC Rough In (4) 10.02.2024 |
|
|
-- |
-- |
Inspection (Rough In HVAC) (1) 10.23.2024 |
|
|
-- |
-- |
Rough In Microwave Vent (0) 10.02.2024 |
|
|
-- |
-- |
Plumbing Rough In (4) 10.12.2024 |
In process 10/9 |
|
-- |
-- |
Inspection (Rough In Plumbing) (1) 10.26.2024 |
|
|
-- |
-- |
Electric Rough In (4) 10.23.2024 |
|
|
-- |
-- |
Inspection (Rough In Electric) (1) 10.26.2024 |
|
|
-- |
-- |
Inspection (Deck Piers) (0) 11.25.2024 |
|
|
-- |
-- |
Inspection (Framing) (1) 10.26.2024 |
|
|
-- |
-- |
Exterior Vinyl (0) * 11.23.2024 |
in process 11/16 |
|
-- |
-- |
Exterior Stone (0) 11.23.2024 |
|
|
-- |
-- |
Insulation (2) 10.30.2024 |
|
|
-- |
-- |
Inspection (Insulation) (1) 11.02.2024 |
|
|
-- |
-- |
Inspection (Electric Service) (0) 11.25.2024 |
|
|
-- |
-- |
Inspection (Main Sewer Line) (0) 10.14.2024 |
|
|
-- |
-- |
Inspection (Main Water Line) (0) 10.14.2024 |
|
|
-- |
-- |
Order Interior Doors & Trim (0) 10.14.2024 |
|
|
-- |
-- |
Drywall (Hang) (4) * 11.02.2024 |
|
|
-- |
-- |
Loan Approval (0) 11.05.2024 |
Cash, 1031 Exchange |
|
-- |
-- |
Deed Preparation (0) 11.05.2024 |
|
|
-- |
-- |
Drywall (Tape, Block, Skim, Sand) (6) * 11.16.2024 |
In process 11/13 |
|
-- |
-- |
Paint 1 (1) 11.16.2024 |
|
|
-- |
-- |
Garage Door (0) 11.25.2024 |
|
|
-- |
-- |
Cabinet Installation (2) * 11.25.2024 |
11/22 |
|
-- |
-- |
Deliver Plumbing / Lighting Fixtures (0) 11.25.2024 |
|
|