UPGRADES
---
CRITICAL PATH
---
TO DO - COMPLETED OR DELETED
Hardwood Trail
Hardwood treads are not installed at this unit
Set basement bathtub
Remove extra steps
Trey ceiling needs to be finished in the master bedroom
Garage window grill inserts Davenport
Missing hardware on drawers to the left and right of the sink Fred
Silver hinges on doors Some. Painters need to uncover tape first before Jill can fix
Replace window and bonus room Sash is on order
Raised dining room chandelier Electrician
Need a lot of lightbulbs
Powder bath fixture needed Electrician
Needs final paint some places Painter
One silver hinge on bonus room door Jill
Three silver hinges on bonus bathroom door Jill
Silver hinges on powder bath door Jill
Paint three still needs to be completed in a few spaces
CODED LOCKBOX 6363
Complete pouring curb so that driveway can be accessible add gravel to make driveway usable
Paint trim around front door Painter
Closet door knobs needed
Lots of extra plumbing fixtures in garage
Home Inspection - Friday 9AM Benjamin Meredith
Scratch on cabinet Jill
Weatherstripping needed on back patio door Jill
Put board into place on back patio Tom
This driveway is not flaky
Light above master shower is a little loose Electrician
Few touchups in stairways and powder bath needed Painter
Paint trim around back exterior doors Painter
Replace damaged weather stripping on rear lower level door Jill
Repair deck railing with loose post cap Premier
Bathroom outlet not working Electrician
Paint edges of interior doors Painter
Seal perimeter of lower level toilet that is shimmed Caulk, Painter - all toilets
Install screen doors Jill
Install screen doors
Install shower rod in master shower Jill. Shower rod is not in master bathroom.
LOTS of paint touch ups throughout home Painters
Clean all receptacle covers throughout home. The painters didn’t remove them, they just painted over the edges Painters
Driveway still needs finished Asphalt filler
Back downspouts need extended Tom will handle this but not til the final grade is finished
1 sconce on the landing is loose and needs tightened up Electrician
Spot on the floor in the little bedroom to right needs removed Jill/kristin
2master bedroom windows need screens Jill
Clean the pvc board around the outside of the garage door Kristin
Raise the downspouts in front of unit (and rest of them on this row) Tom will handle this but not til the final grade is finished
2 holes under kitchen sink needs patched Jill
Remove the coffee maker from the garage?
UPGRADES - COMPLETED
    Oak steps to bedroom level  
    Finished bonus room  
    Finished bonus bath  
    Painted white bathroom cabinetry ( including Bonus Bath +125).  
    Luxury vinyl plank bedroom level, including hallway  
    Luxury vinyl plank in bonus room  
    Expanded driveway  
    Ceiling fans in both small bedrooms  
    Amendment to increase price by $25,130  
CRITICAL PATH - COMPLETED
-- -- Ratified Contract? (0)  08.19.2024    
-- -- $2500 Deposit Received (0)  08.22.2024    
-- -- Association Packet Requested (0)  08.19.2024    
-- -- Association Packet Received (0)  08.24.2024    
-- -- Selections Meeting (0)  08.27.2024    
-- -- Selections Sheet Signed (0)  09.05.2024     8/27: sent to Renee
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  09.07.2024     9/6: sent to Jerry
-- -- Deposit For Upgrades Received (0)  09.06.2024    
-- -- Building Permit (30) *   04.18.2024    
-- -- Order Roof & Floor Trusses (1)  08.22.2024    
-- -- Order Windows & Doors (0)  09.25.2024    
-- -- Stake Out Home (1)  04.18.2024    
-- -- Excavate (2)  04.18.2024    
-- -- Inspection (Footers) (1)  05.13.2024    
-- -- Inspection (Concrete Wall) (1)  05.13.2024    
-- -- Pour Footers (1) *   04.25.2024    
-- -- Set Forms (2)  05.13.2024    
-- -- Pour Foundation Walls (1)  05.13.2024    
-- -- Plumb Slab (2)  05.13.2024    
-- -- Inspection (Plumbing Under Slab) (1)  07.08.2024    
-- -- Inspection (Conduit Under Slab) (1)  07.08.2024    
-- -- Prepare Slab (1)  07.08.2024    
-- -- Inspection (Slab) (1)  07.08.2024    
-- -- Inspection (Drain Tile) (0)  07.08.2024    
-- -- Pour Slab (1) *   07.08.2024    
-- -- Settlement Agent Confirmed (0)  08.22.2024    
-- -- Framing I (9)  08.23.2024    
-- -- Order Steps (0)  09.22.2024    
-- -- Order Tubs / Showers (0)  09.15.2024    
-- -- Framing II (8)  09.12.2024    
-- -- Framing III (8) *   09.19.2024    
-- -- Verify Window & Roof Structure (0)  09.15.2024    
-- -- Install Stairs (0) *   09.25.2024    
-- -- Windows & Doors (0) *   09.25.2024    
-- -- House Number and Status in Window (0)  10.03.2024    
-- -- Roofing (0) *   10.09.2024    
-- -- Order Cabinets (0)  09.27.2024    
-- -- Order Appliances (0)  08.12.2024    
-- -- Deck (0)  11.09.2024    
-- -- Gutters (0)  11.30.2024    
-- -- Driveway (0) *   12.21.2024    
-- -- Patio (0)  12.21.2024    
-- -- Privacy Divider / Fence (0) *   12.18.2024    
-- -- Sod / Seed / Landscaping (0)  03.15.2025    
-- -- HVAC Rough In (4)  10.02.2024    
-- -- Rough In Microwave Vent (0)  10.02.2024    
-- -- Plumbing Rough In (4)  10.19.2024     In process 10/16
-- -- Electric Rough In (4)  10.19.2024    
-- -- Inspection (Rough In HVAC) (1)  10.26.2024    
-- -- Inspection (Rough In Plumbing) (1)  10.26.2024    
-- -- Inspection (Rough In Electric) (1)  10.26.2024    
-- -- Inspection (Framing) (1) *   10.26.2024    
-- -- Inspection (Deck Piers) (0)  11.25.2024    
-- -- Exterior Vinyl (0) *   11.23.2024     in process 11/16
-- -- Exterior Stone (0)  12.18.2024    
-- -- Insulation (2) *   10.26.2024    
-- -- Inspection (Insulation) (1)  10.30.2024    
-- -- Inspection (Electric Service) (0)  11.25.2024    
-- -- Set Electric Meter (0) *   12.12.2024    
-- -- Inspection (Main Sewer Line) (0)  10.14.2024    
-- -- Inspection (Main Water Line) (0)  10.14.2024    
-- -- Order Interior Doors & Trim (0)  10.14.2024    
-- -- Drywall (Hang) (4) *   11.02.2024     In process 10/30
-- -- Loan Approval (0)  11.05.2024     Cash
-- -- Deed Preparation (0)  11.05.2024    
-- -- Drywall (Tape, Block, Skim, Sand) (6) *   11.23.2024     In process 11/16
-- -- Paint 1 (1)  11.23.2024    
-- -- Garage Door (0)  11.25.2024    
-- -- House Numbers (0)  01.11.2025    
-- -- Mailbox (0)  12.19.2024    
-- -- Cabinet Installation (2) *   11.23.2024     11/22
-- -- Granite Installation (1) *   12.04.2024     Wed, Dec 4
-- -- Interior Trim - Install (3) *   12.14.2024     In process 12/4
-- -- Order Plumbing / Lighting Fixtures (0)  12.02.2024    
-- -- Interior Trim - Paint (1)  12.18.2024    
-- -- Luxury Vinyl Plank (3) *   01.05.2025    
-- -- Luxury Vinyl Tile (0)  01.05.2025    
-- -- Paint 2 (3)  01.05.2025    
-- -- Cover Floors (0)  01.05.2025    
-- -- Deliver Plumbing / Lighting Fixtures (0)  11.25.2024    
-- -- Shoe Moulding (0)  01.05.2025    
-- -- Shelving, Door Knobs, Fire Extinguisher (1) *   01.22.2025     In process 1/18
-- -- Install Coded Lockbox (add extra keys) (0)  01.16.2025    
-- -- Pay Water / Sewer Taps (0)  12.30.2024    
-- -- Set Water Meter (1) *   12.30.2024    
-- -- Electric Trim Out (3) *   01.11.2025     In process 1/8
-- -- Ceiling Fans (0)  01.08.2025    
-- -- HVAC Trim Out (1) *   01.05.2025    
-- -- Blower Door Test (1)  01.20.2025    
-- -- Plumbing Trim Out (2) *   01.15.2025     In process 1/11
-- -- Install Appliances (0) *   01.22.2025     fridge, micro, range needed 1/15
-- -- Paint 3 (2) *   01.22.2025     In process 1/18
-- -- Carpet (2)  01.11.2025    
-- -- Appraiser Confirms Construction Completion (0)  01.20.2025    
-- -- Inspection (Final HVAC) (0)  01.22.2025    
-- -- Inspection (Final Plumbing) (0)  01.22.2025    
-- -- Inspection (Final Electric) (0)  01.22.2025    
-- -- Inspection (Final Building) (4) *   01.22.2025     Wed, Jan 22 or Thu, Jan 23
-- -- Pre Walk Through (0)  01.30.2025    
-- -- Stain Hardwood Stairs (1) *   01.25.2025     In process 1/22
-- -- Cleaning (1)  01.30.2025    
-- -- Certificate of Occupancy (1) *   01.25.2025    
-- -- C.O. to Lender (0)  01.25.2025    
-- -- Schedule Closing (0)  01.29.2025    
-- -- Buyer Walk Through (1) *   02.01.2025     Fri, Jan 31 at 1PM
-- -- Payment for Upgrades (0)  01.27.2025    
-- -- Keys to Settlement Agent (0)  01.27.2025    
-- -- Review Settlement Statement (0)  01.29.2025    
-- -- Jerry Signs Closing Documents (0)  01.29.2025    
-- -- Request Trash Tote From POA Manager (0)  01.13.2025    
-- -- Closing (1)  03.03.2025     Brittany @ West View Title
-- -- Remove Coded Lockbox (0)  03.15.2025