000 53 54 55 56 57 49 50 51 52 ADDR
CONGERS-4 - 55  ::  1655 Palomino Trail
[ BUILD: 20261625 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
TO DO
---
UPGRADES
---
    Ratified Contract? (0)      
    $2500 Deposit Received (0)      
    Association Packet Requested (0)      
    Association Packet Received (0)      
    Selections Meeting (0)      
    Selections Sheet Signed (0)      
    Amendment for Upgrades (B,S,L,T,BCP) (0)      
    Deposit For Upgrades Received (0)      
CRITICAL PATH
Sat    Aug 22      Set Forms (2)      
Tue    Aug 25      Inspection (Concrete Wall) (1)      
Wed    Aug 26      Pour Foundation Walls (1)      
Thu    Aug 27      Plumb Slab (2)      
Mon    Aug 31      Inspection (Plumbing Under Slab) (1)      
Tue    Sep 1      Inspection (Conduit Under Slab) (1)      
Wed    Sep 2      Prepare Slab (1)      
Thu    Sep 3      Inspection (Slab) (1)      
    Inspection (Drain Tile) (0)      
Fri    Sep 4      Pour Slab (1) *       
    Settlement Agent Confirmed (0)      
Mon    Sep 7      Framing I (9)      
    Order Steps (0)      
    Order Tubs / Showers (0)      
Fri    Sep 18      Framing II (8)      
Wed    Sep 30      Framing III (8) *       
    Verify Window & Roof Structure (0)      
    Install Stairs (0) *       
    Windows & Doors (0) *       
    House Number and Status in Window (0)      
    Roofing (0) *       
    Order Cabinets (0)      
    Order Appliances (0)      
    Deck (0)      
    Gutters (0)      
    Driveway (0) *       
    Patio (0)      
    Privacy Divider / Fence (0) *       
    Sod / Seed / Landscaping (0)      
Mon    Oct 12      HVAC Rough In (4)      
Fri    Oct 16      Plumbing Rough In (4)      
Thu    Oct 22      Electric Rough In (4)      
Wed    Oct 28      Inspection (Rough In HVAC) (1)      
Thu    Oct 29      Inspection (Rough In Plumbing) (1)      
Fri    Oct 30      Inspection (Rough In Electric) (1)      
Mon    Nov 2      Inspection (Framing) (1) *       
    Inspection (Deck Piers) (0)      
    Exterior Vinyl (0) *       
    Exterior Stone (0)      
Tue    Nov 3      Insulation (2) *       
Thu    Nov 5      Inspection (Insulation) (1)      
    Inspection (Electric Service) (0)      
    Set Electric Meter (0) *       
    Inspection (Main Sewer Line) (0)      
    Inspection (Main Water Line) (0)      
    Order Interior Doors & Trim (0)      
Fri    Nov 6      Drywall (Hang) (4) *       
    Loan Approval (0)      
    Deed Preparation (0)      
Thu    Nov 12      Drywall (Tape, Block, Skim, Sand) (6) *       
Fri    Nov 20      Paint 1 (1)      
    Garage Door (0)      
    House Numbers (0)      
    Mailbox (0)      
Mon    Nov 23      Cabinet Installation (2) *       
Wed    Nov 25      Granite Installation (1) *       
Thu    Nov 26      Interior Trim - Install (3) *       
    Order Plumbing / Lighting Fixtures (0)      
Tue    Dec 1      Interior Trim - Paint (1)      
Wed    Dec 2      Luxury Vinyl Plank (3) *       
    Luxury Vinyl Tile (0)      
Mon    Dec 7      Paint 2 (3)      
    Cover Floors (0)      
    Deliver Plumbing / Lighting Fixtures (0)      
    Shoe Moulding (0)      
Thu    Dec 10      Shelving, Door Knobs, Fire Extinguisher (1) *       
    Install Coded Lockbox (add extra keys) (0)      
    Pay Water / Sewer Taps (0)      
Fri    Dec 11      Set Water Meter (1) *       
Mon    Dec 14      Electric Trim Out (3) *       
    Ceiling Fans (0)      
Thu    Dec 17      HVAC Trim Out (1) *       
Fri    Dec 18      Blower Door Test (1)      
Mon    Dec 21      Plumbing Trim Out (2) *       
    Install Appliances (0) *       
Wed    Dec 23      Paint 3 (2) *       
Fri    Dec 25      Carpet (2)      
    Appraiser Confirms Construction Completion (0)      
    Inspection (Final HVAC) (0)      
    Inspection (Final Plumbing) (0)      
    Inspection (Final Electric) (0)      
Tue    Dec 29      Inspection (Final Building) (4) *       
    Pre Walk Through (0)      
Mon    Jan 4      Stain Hardwood Stairs (1) *       
Tue    Jan 5      Cleaning (1)      
Wed    Jan 6      Certificate of Occupancy (1) *       
    C.O. to Lender (0)      
    Schedule Closing (0)      
Thu    Jan 7      Buyer Walk Through (1) *       
    Payment for Upgrades (0)      
    Keys to Settlement Agent (0)      
    Review Settlement Statement (0)      
    Jerry Signs Closing Documents (0)      
    Request Trash Tote From POA Manager (0)      
Fri    Jan 8      Closing (1)      
    Remove Coded Lockbox (0)      
TO DO - COMPLETED OR DELETED
---
UPGRADES - COMPLETED
---
CRITICAL PATH - COMPLETED
-- -- Building Permit (30) *   08.08.2026    
-- -- Order Roof & Floor Trusses (0)  08.13.2026    
-- -- Order Windows & Doors (0)  08.13.2026    
-- -- Stake Out Home (1)  08.12.2026    
-- -- Excavate (2)  08.12.2026    
-- -- Inspection (Footers) (1)  08.12.2026    
-- -- Pour Footers (1) *   08.13.2026