000 53 54 55 56 57 49 50 51 52 ADDR
CONGERS-4 - 51  ::  1677 Palomino Trail
[ BUILD: 20261676 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
TO DO
---
UPGRADES
---
    Ratified Contract? (0)      
    $2500 Deposit Received (0)      
    Association Packet Requested (0)      
    Association Packet Received (0)      
    Selections Meeting (0)      
    Selections Sheet Signed (0)      
    Amendment for Upgrades (B,S,L,T,BCP) (0)      
    Deposit For Upgrades Received (0)      
CRITICAL PATH
    Order Roof & Floor Trusses (0)      
    Order Windows & Doors (0)      
Sat    Aug 22      Pour Footers (1) *       
Mon    Aug 24      Set Forms (2)      
Wed    Aug 26      Inspection (Concrete Wall) (1)      
Thu    Aug 27      Pour Foundation Walls (1)      
Fri    Aug 28      Plumb Slab (2)      
Tue    Sep 1      Inspection (Plumbing Under Slab) (1)      
Wed    Sep 2      Inspection (Conduit Under Slab) (1)      
Thu    Sep 3      Prepare Slab (1)      
Fri    Sep 4      Inspection (Slab) (1)      
    Inspection (Drain Tile) (0)      
Mon    Sep 7      Pour Slab (1) *       
    Settlement Agent Confirmed (0)      
Tue    Sep 8      Framing I (9)      
    Order Steps (0)      
    Order Tubs / Showers (0)      
Mon    Sep 21      Framing II (8)      
Thu    Oct 1      Framing III (8) *       
    Verify Window & Roof Structure (0)      
    Install Stairs (0) *       
    Windows & Doors (0) *       
    House Number and Status in Window (0)      
    Roofing (0) *       
    Order Cabinets (0)      
    Order Appliances (0)      
    Deck (0)      
    Gutters (0)      
    Driveway (0) *       
    Patio (0)      
    Privacy Divider / Fence (0) *       
    Sod / Seed / Landscaping (0)      
Tue    Oct 13      HVAC Rough In (4)      
Mon    Oct 19      Plumbing Rough In (4)      
Fri    Oct 23      Electric Rough In (4)      
Thu    Oct 29      Inspection (Rough In HVAC) (1)      
Fri    Oct 30      Inspection (Rough In Plumbing) (1)      
Mon    Nov 2      Inspection (Rough In Electric) (1)      
Tue    Nov 3      Inspection (Framing) (1) *       
    Inspection (Deck Piers) (0)      
    Exterior Vinyl (0) *       
    Exterior Stone (0)      
Wed    Nov 4      Insulation (2) *       
Fri    Nov 6      Inspection (Insulation) (1)      
    Inspection (Electric Service) (0)      
    Set Electric Meter (0) *       
    Inspection (Main Sewer Line) (0)      
    Inspection (Main Water Line) (0)      
    Order Interior Doors & Trim (0)      
Mon    Nov 9      Drywall (Hang) (4) *       
    Loan Approval (0)      
    Deed Preparation (0)      
Fri    Nov 13      Drywall (Tape, Block, Skim, Sand) (6) *       
Mon    Nov 23      Paint 1 (1)      
    Garage Door (0)      
    House Numbers (0)      
    Mailbox (0)      
Tue    Nov 24      Cabinet Installation (2) *       
Thu    Nov 26      Granite Installation (1) *       
Fri    Nov 27      Interior Trim - Install (3) *       
    Order Plumbing / Lighting Fixtures (0)      
Wed    Dec 2      Interior Trim - Paint (1)      
Thu    Dec 3      Luxury Vinyl Plank (3) *       
    Luxury Vinyl Tile (0)      
Tue    Dec 8      Paint 2 (3)      
    Cover Floors (0)      
    Deliver Plumbing / Lighting Fixtures (0)      
    Shoe Moulding (0)      
Fri    Dec 11      Shelving, Door Knobs, Fire Extinguisher (1) *       
    Install Coded Lockbox (add extra keys) (0)      
    Pay Water / Sewer Taps (0)      
Mon    Dec 14      Set Water Meter (1) *       
Tue    Dec 15      Electric Trim Out (3) *       
    Ceiling Fans (0)      
Fri    Dec 18      HVAC Trim Out (1) *       
Mon    Dec 21      Blower Door Test (1)      
Tue    Dec 22      Plumbing Trim Out (2) *       
    Install Appliances (0) *       
Thu    Dec 24      Paint 3 (2) *       
Mon    Dec 28      Carpet (2)      
    Appraiser Confirms Construction Completion (0)      
    Inspection (Final HVAC) (0)      
    Inspection (Final Plumbing) (0)      
    Inspection (Final Electric) (0)      
Wed    Dec 30      Inspection (Final Building) (4) *       
    Pre Walk Through (0)      
Tue    Jan 5      Stain Hardwood Stairs (1) *       
Wed    Jan 6      Cleaning (1)      
Thu    Jan 7      Certificate of Occupancy (1) *       
    C.O. to Lender (0)      
    Schedule Closing (0)      
Fri    Jan 8      Buyer Walk Through (1) *       
    Payment for Upgrades (0)      
    Keys to Settlement Agent (0)      
    Review Settlement Statement (0)      
    Jerry Signs Closing Documents (0)      
    Request Trash Tote From POA Manager (0)      
Mon    Jan 11      Closing (1)      
    Remove Coded Lockbox (0)      
TO DO - COMPLETED OR DELETED
---
UPGRADES - COMPLETED
---
CRITICAL PATH - COMPLETED
-- -- Building Permit (30) *   08.15.2026    
-- -- Stake Out Home (1)  08.19.2026    
-- -- Excavate (2)  08.19.2026    
-- -- Inspection (Footers) (1)  08.19.2026