CONGERS - 5  ::  1314 Caspian Way
[ BUILD: 20210000320 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
TO DO
Install missing screens On order
UPGRADES
---
CRITICAL PATH
Tue    Feb 3      Inspection (Concrete Wall) (1)      
Wed    Feb 4      Inspection (Conduit Under Slab) (1)      
    Inspection (Drain Tile) (0)      
    Verify Window & Roof Structure (0)      
    Patio (0)      
    Rough In Microwave Vent (0)      
Thu    Feb 5      Inspection (Rough In Plumbing) (1)      
Fri    Feb 6      Inspection (Rough In Electric) (1)      
Mon    Feb 9      Inspection (Framing) (1) *       
    Inspection (Deck Piers) (0)      
    Exterior Stone (0)      
    Set Electric Meter (0) *       
    Inspection (Main Water Line) (0)      
    Order Plumbing / Lighting Fixtures (0)      
Tue    Feb 10      Interior Trim - Paint (1)      
    Ceiling Fans (0)      
Wed    Feb 11      Blower Door Test (1)      
    Inspection (Final HVAC) (0)      
    Inspection (Final Plumbing) (0)      
    Inspection (Final Electric) (0)      
Thu    Feb 12      Stain Hardwood Stairs (1) *       
TO DO - COMPLETED OR DELETED
Trim needs painting
Basement bath LVT needed And hall bath
Corner trim kitchen island needed
CODED LOCKBOX 5555
Home Inspection Thursday, 10/28, 2:00 PM
Stain steps In process 10/27
Paint door
Only 1 ceiling fan (that i see) on site
Mirror basement bath
Appliances needed
Black garage hardware to be installed 11/4
address open wire at ceiling from garage light/opener Tom
Paint Touch Up Throughout
Clean various paint spots off carpet Jill will talk to Eric or Isaac
Adjust lock at dining patio door Tom or Jim
Adjust lock at front door
Missing trim at base cabinet next to fridge Quarter round - painter
Repair garbage disposal
Water drains slowly at upstairs hall bathroom sink Tom
Roof sheathing - not enough of a gap at the ridge vent non issue again?
Secure loose powder room sink top and base
Adjust drain pipes at washer pan and water heater pan to drain properly
Seal cracks or gaps at front window and door trim Tom
Secure cabinets to floor at kitchen island where move when weight is applied at the bar area Tom
Install weather stripping at front and rear doors and replace piece on door to garage Tom
Cut off the bottom of doors where they rub the carpet
Dining room door dead bolt does not fully lock
Finish carpet installation at bonus room bathroom and install transition strip
Cut insultation batte at attic access panel down to size of access panel Tom
Heat pump issues4
Extremely hot inside townhouse Tom will contact Ronnie
UPGRADES - COMPLETED
    Expanded Driveway  
    Expanded Patio under deck  
    Digital keypad  
    Painted cabinetry  
    Upgraded 24" vanity over bonus bath pedestal  
    Five Piece Drawer- Kitchen Cabinetry  
    Hardwood treads to bedroom level  
    Upgraded Carpet Pad  
    3 added ceiling fans in bedrooms 2 and 3 and bonus  
    Finished Bonus Room and Full Bathroom  
    Amendment to increase contract price by $16,130  
CRITICAL PATH - COMPLETED
-- -- Ratified Contract? (0)  11.21.2021    
-- -- $2500 Deposit Received (0)  11.21.2021    
-- -- Association Packet Requested (0)  11.21.2021    
-- -- Association Packet Received (0)  11.21.2021    
-- -- Selections Meeting (0)  11.21.2021    
-- -- Selections Sheet Signed (0)  11.21.2021    
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  11.21.2021    
-- -- Deposit For Upgrades Received (0)  11.21.2021    
-- -- Building Permit (30) *       
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1) *       
-- -- Set Forms (2)       in process 3/24
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Settlement Agent Confirmed (0)  11.21.2021    
-- -- Framing I (9)       in process 5/1
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *       
-- -- Install Stairs (0) *       
-- -- Windows & Doors (0) *        in [process 6/6
-- -- House Number and Status in Window (0)      
-- -- Roofing (0) *        in process 6/6
-- -- Order Cabinets (0)      
-- -- Order Appliances (0)  09.07.2021     SS Standard
-- -- Deck (0)  10.06.2021    
-- -- Gutters (0)  10.18.2021    
-- -- Driveway (0) *   09.22.2021    
-- -- Privacy Divider / Fence (0) *   10.18.2021    
-- -- Sod / Seed / Landscaping (0)  10.30.2021    
-- -- HVAC Rough In (4)      
-- -- Plumbing Rough In (4)       In process 6/16
-- -- Electric Rough In (4)       in process 6/19
-- -- Inspection (Rough In HVAC) (1)      
-- -- Exterior Vinyl (0) *   10.13.2021    
-- -- Insulation (2) *       
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)  09.09.2021    
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)       BN Hinges
-- -- Drywall (Hang) (4) *        Stocked 6/30
-- -- Loan Approval (0)  11.21.2021    
-- -- Deed Preparation (0)  11.21.2021    
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        In process 7/18
-- -- Paint 1 (1)      
-- -- Garage Door (0)  09.15.2021    
-- -- House Numbers (0)  10.02.2021    
-- -- Mailbox (0)  11.21.2021    
-- -- Cabinet Installation (2) *   09.01.2021     8/30-on site 8/28
-- -- Granite Installation (1) *   09.22.2021    
-- -- Interior Trim - Install (3) *   09.11.2021     In process 9/8
-- -- Luxury Vinyl Plank (3) *   09.29.2021    
-- -- Luxury Vinyl Tile (0)  10.10.2021     Needs completed in basement bath
-- -- Paint 2 (3)  10.10.2021     In process 10/6
-- -- Cover Floors (0)  11.01.2021    
-- -- Deliver Plumbing / Lighting Fixtures (0)  10.13.2021    
-- -- Shoe Moulding (0)  10.13.2021    
-- -- Shelving, Door Knobs, Fire Extinguisher (1) *   10.30.2021     In process 10/27
-- -- Install Coded Lockbox (add extra keys) (0)  10.21.2021    
-- -- Pay Water / Sewer Taps (0)  10.14.2021    
-- -- Set Water Meter (1) *   10.14.2021    
-- -- Electric Trim Out (3) *   10.30.2021     BN Lighting-in process 10/27
-- -- HVAC Trim Out (1) *   10.30.2021     HVAC set needs thermostat
-- -- Plumbing Trim Out (2) *   10.30.2021     Dishwasher
-- -- Install Appliances (0) *   10.30.2021     SS Standard
-- -- Paint 3 (2) *   10.10.2021    
-- -- Carpet (2)  10.30.2021     In process 10/27
-- -- Appraiser Confirms Construction Completion (0)  11.08.2021    
-- -- Inspection (Final Building) (4) *   10.29.2021     Thu, Oct 28
-- -- Pre Walk Through (0)  10.29.2021    
-- -- Cleaning (1)  11.01.2021     In process 10/30
-- -- Certificate of Occupancy (1) *   10.29.2021    
-- -- C.O. to Lender (0)  10.29.2021    
-- -- Schedule Closing (0)  11.10.2021    
-- -- Buyer Walk Through (1) *   11.03.2021     Mon, 11/1 at 3:00 PM
-- -- Payment for Upgrades (0)  11.04.2021    
-- -- Keys to Settlement Agent (0)  11.02.2021    
-- -- Review Settlement Statement (0)  11.08.2021    
-- -- Jerry Signs Closing Documents (0)  11.11.2021     Nov 10, 10:30 AM
-- -- Request Trash Tote From POA Manager (0)  11.02.2021    
-- -- Closing (1)  11.18.2021     Nov 15, 11:00 AM
-- -- Remove Coded Lockbox (0)  11.17.2021