Sat    May 16      Inspection (Concrete Wall) (1)      
Mon    May 18      Inspection (Conduit Under Slab) (1)      
    Inspection (Drain Tile) (0)      
Tue    May 19      Inspection (Rough In Plumbing) (1)      
Wed    May 20      Inspection (Rough In Electric) (1)      
Thu    May 21      Inspection (Framing) (1) *       
    Inspection (Deck Piers) (0)      
    Inspection (Main Water Line) (0)      
    Inspection (Final HVAC) (0)      
    Inspection (Final Plumbing) (0)      
    Inspection (Final Electric) (0)      
TO DO - COMPLETED OR DELETED
UPGRADES - COMPLETED
    Expanded Driveway  
    Expanded Patio under deck  
    Digital keypad  
    Painted cabinetry  
    Upgraded 24" vanity over bonus bath pedestal  
    Five Piece Drawer- Kitchen Cabinetry  
    Hardwood treads to bedroom level  
    Upgraded Carpet Pad  
    3 added ceiling fans in bedrooms 2 and 3 and bonus  
    Finished Bonus Room and Full Bathroom  
    Amendment to increase contract price by $16,130  
CRITICAL PATH - COMPLETED
-- -- Inspection (Footers) (1)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Inspection (Slab) (1)      
-- -- Inspection (Rough In HVAC) (1)      
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)  09.09.2021    
-- -- Inspection (Main Sewer Line) (0)      
-- -- Inspection (Final Building) (4) *   10.29.2021     Thu, Oct 28