CONGERS - 5  ::  1314 Caspian Way
[ BUILD: 20210000320 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
TO DO
UPGRADES
---
CRITICAL PATH
Wed    Mar 25      Inspection (Concrete Wall) (1)      
Thu    Mar 26      Inspection (Conduit Under Slab) (1)      
    Inspection (Drain Tile) (0)      
Fri    Mar 27      Inspection (Rough In Plumbing) (1)      
Mon    Mar 30      Inspection (Rough In Electric) (1)      
Tue    Mar 31      Inspection (Framing) (1) *       
    Inspection (Deck Piers) (0)      
    Inspection (Main Water Line) (0)      
    Inspection (Final HVAC) (0)      
    Inspection (Final Plumbing) (0)      
    Inspection (Final Electric) (0)      
TO DO - COMPLETED OR DELETED
UPGRADES - COMPLETED
    Expanded Driveway  
    Expanded Patio under deck  
    Digital keypad  
    Painted cabinetry  
    Upgraded 24" vanity over bonus bath pedestal  
    Five Piece Drawer- Kitchen Cabinetry  
    Hardwood treads to bedroom level  
    Upgraded Carpet Pad  
    3 added ceiling fans in bedrooms 2 and 3 and bonus  
    Finished Bonus Room and Full Bathroom  
    Amendment to increase contract price by $16,130  
CRITICAL PATH - COMPLETED
-- -- Inspection (Footers) (1)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Inspection (Slab) (1)      
-- -- Inspection (Rough In HVAC) (1)      
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)  09.09.2021    
-- -- Inspection (Main Sewer Line) (0)      
-- -- Inspection (Final Building) (4) *   10.29.2021     Thu, Oct 28