37 ADDR
CONGERS-2 - 301  ::  1270 Constitution Court #301
[ BUILD: 1805-0147 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
Mon    Dec 15      Ratified Contract? (0)      
Mon    Dec 15      $2500 Deposit Received (0)      
Mon    Dec 15      Association Packet Requested (0)      
Mon    Dec 15      Association Packet Received (0)      
Mon    Dec 15      Selections Meeting (0)      
Mon    Dec 15      Selections Sheet Signed (0)      
Mon    Dec 15      Amendment for Upgrades (B,S,L,T,BCP) (0)      
Mon    Dec 15      Deposit For Upgrades Received (0)      
Mon    Dec 15      Inspection (Concrete Wall) (1)      
Tue    Dec 16      Inspection (Conduit Under Slab) (1)      
Wed    Dec 17      Inspection (Drain Tile) (0)      
Wed    Dec 17      Settlement Agent Confirmed (0)      
Wed    Dec 17      Verify Window & Roof Structure (0)      
Wed    Dec 17      Patio (0)      
Wed    Dec 17      Rough In Microwave Vent (0)      
Wed    Dec 17      Inspection (Rough In Plumbing) (1)      
Thu    Dec 18      Inspection (Rough In Electric) (1)      
Fri    Dec 19      Inspection (Framing) (1) *       
Mon    Dec 22      Inspection (Deck Piers) (0)      
Mon    Dec 22      Exterior Stone (0)      
Mon    Dec 22      Set Electric Meter (0) *       
Mon    Dec 22      Inspection (Main Water Line) (0)      
Mon    Dec 22      Loan Approval (0)      
Mon    Dec 22      Deed Preparation (0)      
Mon    Dec 22      Mailbox (0)      
Mon    Dec 22      Interior Trim - Paint (1)      
Tue    Dec 23      Ceiling Fans (0)      
Tue    Dec 23      Blower Door Test (1)      
Wed    Dec 24      Inspection (Final HVAC) (1)      
Thu    Dec 25      Inspection (Final Plumbing) (1)      
Fri    Dec 26      Inspection (Final Electric) (1)      
Mon    Dec 29      Stain Hardwood Stairs (1) *       
Tue    Dec 30      Request Trash Tote From POA Manager (0)      
--   --   Electric trim out (final) before remaining drywall 8/19
--   --   5 3/4 from vent to bottom of wide molding 21 1/2 width
--   --   Crack in ceiling drywall 10/14
--   --   Ceiling hole? 10/21
--   --   CODED LOCKBOX 0301
--   --   Bathroom floors-first week of January
--   --   Buyer is providing the kitchen sink Should arrive to Tom on 1/5
--   --   Buyer would like to swap granite for CM in bathrooms. Can we reuse CM in 303?
--   --   Move cultured marble bathroom tops to 303 (Kate will confirm)
--   --   Re-paint ceiling Galindez touch up 1/27. GWB Blue taped whole condo as well.
--   --   Electric trim out should be done 1/6 Almost done. Vanity lights after plumbers. 1/13
--   --   Trim in bath needed 1/5 Galindez to finish when they come paint GWB
--   --   Transfer strips at LVT Eric does not stock. Greg will get from lowes 1/21and have Eric install GWB
--   --   sprinkler head needed near front door? 1/13
--   --   Replace siding piece above door where there is no sprinkler
--   --   install microwave 1/16 On site 1/20
--   --   repair hole n siding by front door 1/16
--   --   Kitchen sink faucet is partially in 1/23
--   --   Screens In process 2/3
--   --   Weather stripping at door 1/23
--   --   Cabinet trim 2/3 Needed in bathrooms at vanities. Not done 2/6
--   --   2 more screen doors-at CC? Tom-needs one 2/17
--   --   Shower rod-4 in condo 2/3
--   --   Chunk missing from bottom edge of upper kitchen cabinet Jill will talk to the painter about patching this
--   --   Add bass shoe molding in master bathroom and hall bathroom
--   --   Paint touch ups throughout
--   --   Replace two ripped screens in master bedroom
--   --   Replace return air grill in living room Ronnie, 2/15
--   --   Replace cool light bulb with warm lightbulb in pendant light Jill, 2/15
--   --   Final touch up clean
--   --   Add snap light over shower
--   --   Freezer broken? Leaking water? 2/10 Looks cleaned up-but dripping a little 2/14
--   --   Screws are missing at the low voltage box Tom
--   --   Loose flooring transition strip Tom
--   --   Sand and repaint in living room Isaac
--   --   Clean again after sanding and repainting Kelly
--   --   Caulk at the door frame by low voltage panel Isaac
-- -- Building Permit (30) *       
-- -- Order Roof & Floor Trusses (1)      
-- -- Order Windows & Doors (0)      
-- -- Stake Out Home (1)      
-- -- Excavate (2)      
-- -- Inspection (Footers) (1)      
-- -- Pour Footers (1) *       
-- -- Set Forms (2)      
-- -- Pour Foundation Walls (1)      
-- -- Plumb Slab (2)      
-- -- Inspection (Plumbing Under Slab) (1)      
-- -- Prepare Slab (1)      
-- -- Inspection (Slab) (1)      
-- -- Pour Slab (1) *       
-- -- Framing I (9)      
-- -- Order Steps (0)      
-- -- Order Tubs / Showers (0)      
-- -- Framing II (8)      
-- -- Framing III (8) *       
-- -- Install Stairs (0) *       
-- -- Windows & Doors (0) *       
-- -- House Number and Status in Window (0)      
-- -- Roofing (0) *       
-- -- Order Cabinets (0)      
-- -- Order Appliances (0)      
-- -- Deck (0)      
-- -- Gutters (0)      
-- -- Driveway (0) *       
-- -- Privacy Divider / Fence (0) *       
-- -- Sod / Seed / Landscaping (0)      
-- -- HVAC Rough In (4)       Almost complete 5/25
-- -- Plumbing Rough In (4)      
-- -- Electric Rough In (4)      
-- -- Inspection (Rough In HVAC) (1)      
-- -- Exterior Vinyl (0) *       
-- -- Insulation (2) *       
-- -- Inspection (Insulation) (1)      
-- -- Inspection (Electric Service) (0)      
-- -- Inspection (Main Sewer Line) (0)      
-- -- Order Interior Doors & Trim (0)      
-- -- Drywall (Hang) (4) *        In process 9/2
-- -- Drywall (Tape, Block, Skim, Sand) (6) *        Set to finish 9/22 GWB
-- -- Paint 1 (1)       set to start 10/2 - they are finished 201 then 101 first GWB
-- -- Garage Door (0)      
-- -- House Numbers (0)      
-- -- Cabinet Installation (2) *       
-- -- Granite Installation (1) *        Set to install 1/12 GWB
-- -- Interior Trim - Install (3) *        Almost complete 10/10
-- -- Order Plumbing / Lighting Fixtures (0)      
-- -- Luxury Vinyl Plank (3) *        Set to start Oct. 1 GWB-in process 10/14
-- -- Luxury Vinyl Tile (0)       Installed. Just need transfer strips GWB
-- -- Paint 2 (3)      
-- -- Cover Floors (1)      
-- -- Deliver Plumbing / Lighting Fixtures (0)       Plumbing delivered 10/28
-- -- Shoe Moulding (0)      
-- -- Shelving, Door Knobs, Fire Extinguisher (0) *        In process 10/24
-- -- Install Coded Lockbox (add extra keys) (0)      
-- -- Pay Water / Sewer Taps (0)      
-- -- Set Water Meter (0) *       
-- -- Electric Trim Out (3) *        In process 12/6, 12/28
-- -- HVAC Trim Out (1) *       
-- -- Plumbing Trim Out (2) *        Completed except kitchen sink 1/20 Counter getting fixed 1/21 GWB
-- -- Install Appliances (0) *        Waiting on tops. Appliances stored I n unit 202 GWB
-- -- Paint 3 (2) *        scheduled for later this week 1/21 GWB
-- -- Carpet (2)      
-- -- Appraiser Confirms Construction Completion (0)      
-- -- Inspection (Final Building) (2) *        Waiting on re-inspect
-- -- Pre Walk Through (0)      
-- -- Cleaning (1)       In process 1/27, Kelly
-- -- Certificate of Occupancy (1) *       
-- -- C.O. to Lender (0)      
-- -- Schedule Closing (0)      
-- -- Buyer Walk Through (1) *        Wednesday, 2/10/2021 @ 9:00 AM?
-- -- Payment for Upgrades (0)      
-- -- Keys to Settlement Agent (0)      
-- -- Review Settlement Statement (0)      
-- -- Jerry Signs Closing Documents (0)      
-- -- Closing (1)       Friday, Feb 17 at 10:30 AM at WVT;
-- -- Remove Coded Lockbox (0)       Courtney to remove 2/27