37 ADDR
CONGERS-2 - 131  ::  1313 Palomino Trail
[ BUILD: 20210001834 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
TO DO
---
UPGRADES
---
CRITICAL PATH
    Verify Window & Roof Structure (0)      
    Rough In Microwave Vent (0)      
    Order Plumbing / Lighting Fixtures (0)      
Tue    Feb 3      Blower Door Test (1)      
TO DO - COMPLETED OR DELETED
Needs tub liners
Paint on cabinets-Jill?
Basement toilet issue? 4/27
Drywall repair in basement shower ceiling 4/27 Drywaller
Crack in Foundation-Tom will seal
Corners for cabinets needed? In box in dining room, waiting on cabinet installer. Installer on site 6/1
Drywall repair basement bath when ceiling is repaired.
Weatherstripping on front window broken 5/15 Tom will swap out the sash
Repair needed to front porch 5/25 Jeremy, Davenport
CODED LOCKBOX 0131
Door weatherstripping needs Jill :)
Very crooked basement toilet 6/1 Plumber
Drywall hole basement bath In process 6/12
Bathroom shelving needs installed 6/12 And closet after carpet
Basement closet drywall patch Painter
Drywall LR ceiling blemish Painter
No electric to kitchen island
Outdoor outlet needed
Outdoor outlet needed
Needs almost all electrical trim out on main level All snap lights needed everywhere
Closet shelving in 2 smaller bedrooms needs fixing
Receptacle near base vanity needs completed And light switch
Finish electric trim out basement bath
Outlet cover basement bath Outlet cover by wall as well
Drywall repair/access panel needed in basement
Closet shelving in master. Carpet is down now. Joe
Weatherstripping needed on front door Jill
Light bulb powder bath Jill
Loose rock Tom will tell rock guys
Larger water line access panel Tom. Looks good - can we paint it?
Paint tops and bottoms of doors
Replace deck board with purple stain?
Few bulbs
Pendant lights- switch out bulb so both lights match- daylight Jill
Plug holes in front and French door Jill
Touch up on cabinet ends of island Jill
Wipe down kitchen cabinet Cleaner
Final paint touch up To be completed Saturday 7/2
Leave gallon of ceiling adn wall paint Painter
Repair hole in master shower Shower repair person - week of July 11
Clean off overspray on banister Painter??? Maybe completed 7/6?
Loose bathroom accessories to be toghtened Joe
Install missing light bulbs Jill. Base bath 7/6
Install base patio screen Jill
Cover for snap light in downstairs stairwell Jill
Insulation on doorbell (indoors) Jill
Fan doesn’t work in powder bath 7/13 Jill & Tom
UPGRADES - COMPLETED
    Expanded Deck 12 x 18  
    Full Basement Family Room  
    Finished Bath  
    Finished Bonus Room  
    Amendment to increase price by $26,800  
CRITICAL PATH - COMPLETED
-- -- Ratified Contract? (0)  11.21.2021    
-- -- $2500 Deposit Received (0)  11.21.2021    
-- -- Association Packet Requested (0)  11.21.2021    
-- -- Association Packet Received (0)  11.21.2021    
-- -- Selections Meeting (0)  12.07.2021    
-- -- Selections Sheet Signed (0)  12.09.2021     12/7/2021: sent to Katherine for buyer signature
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  01.05.2022     1/4/2022: waiting on signature from Jerry
-- -- Deposit For Upgrades Received (0)  01.04.2022     12/14/2021: waiting on upgrade deposit from buyer
-- -- Building Permit (30) *   11.11.2021    
-- -- Order Roof & Floor Trusses (1)  11.11.2021    
-- -- Order Windows & Doors (0)  11.11.2021    
-- -- Stake Out Home (1)  11.08.2021    
-- -- Excavate (2)  11.29.2021    
-- -- Inspection (Footers) (1)  11.29.2021    
-- -- Inspection (Concrete Wall) (1)  02.14.2023    
-- -- Pour Footers (1) *   11.29.2021    
-- -- Set Forms (2)  12.06.2021    
-- -- Pour Foundation Walls (1)  12.09.2021    
-- -- Plumb Slab (2)  12.13.2021    
-- -- Inspection (Plumbing Under Slab) (1)  12.20.2021    
-- -- Inspection (Conduit Under Slab) (1)  02.14.2023    
-- -- Prepare Slab (1)  12.20.2021    
-- -- Inspection (Slab) (1)  12.20.2021    
-- -- Inspection (Drain Tile) (0)  02.14.2023    
-- -- Pour Slab (1) *   12.20.2021    
-- -- Settlement Agent Confirmed (0)  03.30.2022    
-- -- Framing I (9)  01.03.2022    
-- -- Order Steps (0)  12.20.2021    
-- -- Order Tubs / Showers (0)  12.09.2021    
-- -- Framing II (8)  01.17.2022    
-- -- Framing III (8) *   02.03.2022    
-- -- Install Stairs (0) *   02.24.2022    
-- -- Windows & Doors (0) *   04.10.2022    
-- -- House Number and Status in Window (0)  02.28.2022    
-- -- Roofing (0) *   02.17.2022    
-- -- Order Cabinets (0)  01.31.2022    
-- -- Order Appliances (0)  02.24.2022     Standard
-- -- Deck (0)  04.24.2022     Expanded Deck 12 x 18- in process 2/16
-- -- Gutters (0)  05.02.2022    
-- -- Driveway (0) *   06.18.2022     STANDARD - Fri, June 17
-- -- Patio (0)  02.14.2023    
-- -- Privacy Divider / Fence (0) *   04.25.2022    
-- -- Sod / Seed / Landscaping (0)  06.29.2022    
-- -- HVAC Rough In (4)  02.24.2022     in process 2/13
-- -- Plumbing Rough In (4)  03.17.2022     In process 3/12
-- -- Electric Rough In (4)  03.24.2022     In process 3/23
-- -- Inspection (Rough In HVAC) (1)  03.28.2022     3/25
-- -- Inspection (Rough In Plumbing) (1)  02.14.2023    
-- -- Inspection (Rough In Electric) (1)  02.14.2023    
-- -- Inspection (Framing) (1) *   02.14.2023    
-- -- Inspection (Deck Piers) (0)  02.14.2023    
-- -- Exterior Vinyl (0) *   04.18.2022    
-- -- Exterior Stone (0)  04.14.2022    
-- -- Insulation (2) *   03.30.2022     ???
-- -- Inspection (Insulation) (1)  03.31.2022    
-- -- Inspection (Electric Service) (0)  06.02.2022    
-- -- Set Electric Meter (0) *   04.11.2023    
-- -- Inspection (Main Sewer Line) (0)  04.14.2022    
-- -- Inspection (Main Water Line) (0)  02.14.2023    
-- -- Order Interior Doors & Trim (0)  03.10.2022    
-- -- Drywall (Hang) (4) *   04.10.2022    
-- -- Loan Approval (0)  06.13.2022    
-- -- Deed Preparation (0)  04.13.2022    
-- -- Drywall (Tape, Block, Skim, Sand) (6) *   04.18.2022     In process 4/13
-- -- Paint 1 (1)  04.20.2022    
-- -- Garage Door (0)  04.04.2022    
-- -- House Numbers (0)  06.29.2022    
-- -- Mailbox (0)  07.03.2022    
-- -- Cabinet Installation (2) *   04.18.2022     4/14-delivered 4/13
-- -- Granite Installation (1) *   05.07.2022     5/6
-- -- Interior Trim - Install (3) *   05.07.2022     Needs painting 5/4
-- -- Interior Trim - Paint (1)  02.14.2023    
-- -- Luxury Vinyl Plank (3) *   05.21.2022    
-- -- Luxury Vinyl Tile (0)  05.21.2022    
-- -- Paint 2 (3)  05.21.2022    
-- -- Cover Floors (0)  06.30.2022    
-- -- Deliver Plumbing / Lighting Fixtures (0)  06.01.2022     Plumbing on site 5/21
-- -- Shoe Moulding (0)  06.01.2022     On site 5/25
-- -- Shelving, Door Knobs, Fire Extinguisher (1) *   06.12.2022     Black accessories, Bonus bath. In process-90% complete 5/30
-- -- Install Coded Lockbox (add extra keys) (0)  05.25.2022    
-- -- Pay Water / Sewer Taps (0)  05.19.2022    
-- -- Set Water Meter (1) *   06.09.2022    
-- -- Electric Trim Out (3) *   06.25.2022     Quite a bit still needs completed 6/15
-- -- Ceiling Fans (0)  05.16.2022    
-- -- HVAC Trim Out (1) *   06.25.2022     Furnace set 6/1
-- -- Plumbing Trim Out (2) *   05.25.2022     Black Standard
-- -- Install Appliances (0) *   06.08.2022     On site 5/30
-- -- Paint 3 (2) *   06.01.2022    
-- -- Carpet (2)  06.30.2022     In process 6/25
-- -- Appraiser Confirms Construction Completion (0)  07.05.2022    
-- -- Inspection (Final HVAC) (0)  02.14.2023    
-- -- Inspection (Final Plumbing) (0)  02.14.2023    
-- -- Inspection (Final Electric) (0)  02.14.2023    
-- -- Inspection (Final Building) (4) *   06.30.2022     Wed, June 29
-- -- Pre Walk Through (0)  06.27.2022    
-- -- Stain Hardwood Stairs (1) *   06.16.2022    
-- -- Cleaning (1)  07.03.2022    
-- -- Certificate of Occupancy (1) *   06.30.2022    
-- -- C.O. to Lender (0)  06.30.2022    
-- -- Schedule Closing (0)  07.13.2022    
-- -- Buyer Walk Through (1) *   07.05.2022    
-- -- Payment for Upgrades (0)  06.30.2022    
-- -- Keys to Settlement Agent (0)  06.28.2022    
-- -- Review Settlement Statement (0)  07.13.2022    
-- -- Jerry Signs Closing Documents (0)  06.30.2022     Wednesday, June 29, 1:00 PM
-- -- Request Trash Tote From POA Manager (0)  06.28.2022    
-- -- Closing (1)  07.18.2022     Brittany @ West View Title (July 14)
-- -- Remove Coded Lockbox (0)  07.27.2022