37 ADDR
CONGERS-2 - 132  ::  1309 Palomino Trail
[ BUILD: 20210001835 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
TO DO
---
UPGRADES
---
CRITICAL PATH
---
TO DO - COMPLETED OR DELETED
UPGRADES - COMPLETED
    Finish Bonus Room  
    Finished Family Room  
    Finish Bonus Bath  
    Level Three Quartz  
    Farmhouse sink  
    Painted White Cabinetry Kitchen  
    Painted Bath Cabinetry  
    Oak Treads  
    Luxury Vinyl Plank- Upper Level  
    Expanded Deck 12x12  
    Expanded Patio 10x10  
    Sub way Tile Master Shower walls  
    Heavy Glass Shower Door For Master  
    Pull Out Waste Basket  
    Three Drawer Stack  
    Roll Out Trays in 33  
    Roll Out Trays in 18  
    French Style Refrigerator  
    Oak Stairs to Basement Level  
    LVP Bonus Room  
    LVP Family Room  
    Ship Lap Living Room Wall  
    Farmhouse Plumbing Package  
    Amendment to increase price by $49,075  
CRITICAL PATH - COMPLETED
-- -- Inspection (Footers) (1)  11.29.2021    
-- -- Inspection (Concrete Wall) (1)  02.14.2023    
-- -- Inspection (Plumbing Under Slab) (1)  12.20.2021    
-- -- Inspection (Conduit Under Slab) (1)  02.14.2023    
-- -- Inspection (Slab) (1)  12.20.2021    
-- -- Inspection (Drain Tile) (0)  02.14.2023    
-- -- Inspection (Rough In HVAC) (1)  03.21.2022    
-- -- Inspection (Rough In Plumbing) (1)  02.14.2023    
-- -- Inspection (Rough In Electric) (1)  02.14.2023    
-- -- Inspection (Framing) (1) *   02.14.2023    
-- -- Inspection (Deck Piers) (0)  02.14.2023    
-- -- Inspection (Insulation) (1)  03.24.2022    
-- -- Inspection (Electric Service) (0)  06.02.2022    
-- -- Inspection (Main Sewer Line) (0)  04.14.2022    
-- -- Inspection (Main Water Line) (0)  02.14.2023    
-- -- Inspection (Final HVAC) (0)  02.14.2023    
-- -- Inspection (Final Plumbing) (0)  02.14.2023    
-- -- Inspection (Final Electric) (0)  02.14.2023    
-- -- Inspection (Final Building) (4) *   06.24.2022     Tuesday, June 21