Thu |
Nov 28 |
Verify Window & Roof Structure (0) |
|
|
Thu |
Nov 28 |
Rough In Microwave Vent (0) |
|
|
Thu |
Nov 28 |
Order Plumbing / Lighting Fixtures (0) |
|
|
Thu |
Nov 28 |
Blower Door Test (1) |
|
|
|
-- |
-- |
Window Layout? |
Rendering = Separate, Floor Plans = Together |
|
-- |
-- |
Need rendering showing triple window with awning |
|
|
-- |
-- |
deck stairs? |
|
|
-- |
-- |
Micro needs vented 4/27 |
|
|
-- |
-- |
Jill-insulation in 127-please toss in all tubs |
|
|
-- |
-- |
retaining wall between 128-129? |
|
|
-- |
-- |
Basement vanity missing |
Setting Thu, Aug 4 |
|
-- |
-- |
No roll out rays |
|
|
-- |
-- |
No trash can |
|
|
-- |
-- |
No spice rack |
|
|
-- |
-- |
No cabinet crown molding |
|
|
-- |
-- |
Rate Lock Expires July 20 |
|
|
-- |
-- |
Paint garage |
Painter |
|
-- |
-- |
|
|
|
-- |
-- |
Shoe molding needed basement bath |
after vanity is installed? |
|
-- |
-- |
Mailboxes |
Tom |
|
-- |
-- |
Paint front doors |
Painter |
|
-- |
-- |
Splash blocks needed (all units) |
Tom |
|
-- |
-- |
|
|
|
-- |
-- |
Drywall patch needed behind oven |
|
|
-- |
-- |
Home Inspection Monday, August 9th at 5:30pm |
|
|
-- |
-- |
Movers arrive 1pm on August 11 |
|
|
-- |
-- |
Touch up garage trim |
Painter |
|
-- |
-- |
Cable cover |
Jill |
|
-- |
-- |
Paint trim in base bath |
Painter |
|
-- |
-- |
Privacy panel |
Jill will follow up |
|
-- |
-- |
Gap in cabinet trim and paint |
Painter |
|
-- |
-- |
Wrong front panel on waste basket |
Courtney - please clarify |
|
-- |
-- |
Spice rack door correct? Or should handle be at top |
Handle should be at top so drawer pulls out correctly. |
|
-- |
-- |
Caulk side splashes on vanities |
Painter |
|
-- |
-- |
Cover on master bath light switch |
Painter |
|
-- |
-- |
Push attic cover into place |
Painter |
|
-- |
-- |
CODED LOCKBOX 0128 |
|
|
-- |
-- |
Touch Faucet not available-install after closing |
On order, Northeastern |
|
-- |
-- |
Apply finish coat of paint to exterior trim below back door/above deck |
Add PVC board |
|
-- |
-- |
Complete final grading of property |
|
|
-- |
-- |
Threshold from deck to patio door does not have adequate support |
|
|
-- |
-- |
Secure gasket to oven door housing. |
Tom will look at it, or CJ |
|
-- |
-- |
Microwave does not exhaust to exterior correctly. |
CJ |
|
-- |
-- |
Cover exposed wall framing in garage |
|
|
-- |
-- |
Make repairs to closet door so it closes properly. |
Jill |
|
-- |
-- |
Fix deadbolt in bonus room and kitchen door so it locks properly. |
|
|
-- |
-- |
Replace HVAC filter |
Jill |
|
-- |
-- |
Install smoke detector in bonus room? |
|
|
-- |
-- |
Secure power bath toilet to floor |
Plumber |
|
-- |
-- |
Truss in attic is cracked/split. Provide copy of repair report, or repair as appropriate. |
Tom will coordinate |
|
-- |
-- |
Deck attack (attach) bracket needs to be properly installed. |
|
|
-- |
-- |
Adjust door to bonus room closet |
Jill will ask Edgar the trim guy to look at it |
|
-- |
-- |
Caulk end panel of shower just past shower door next to toilet |
|
|
-- |
-- |
Hall Bath- paint vertical strip between bath and wall |
|
|
-- |
-- |
caulk behind toilets where trim meets cabient |
|
|
-- |
-- |
Raise pendant lights I foot |
Electrician |
|
-- |
-- |
New door front for trash can and spice rack |
On order |
|
-- |
-- |
|
|
|
-- |
-- |
|
|
|
-- |
-- |
|
|
|
-- |
-- |
Richard Ortega 571-934-6152 |
|
|
-- |
-- |
PVC board off deck |
|
|
-- |
-- |
Pre |
|
|
-- |
-- |
Shower caddy |
|
|
-- |
-- |
Ratified Contract? (0) 11.21.2021 |
|
|
-- |
-- |
$2500 Deposit Received (0) 11.21.2021 |
|
|
-- |
-- |
Association Packet Requested (0) 11.21.2021 |
|
|
-- |
-- |
Association Packet Received (0) 11.21.2021 |
|
|
-- |
-- |
Selections Meeting (0) 01.17.2022 |
|
|
-- |
-- |
Selections Sheet Signed (0) 01.20.2022 |
1/18/2022: sent to Courtney for buyer signatures |
|
-- |
-- |
Amendment for Upgrades (B,S,L,T,BCP) (0) 01.28.2022 |
1/28/2022: sent to Jerry for signature |
|
-- |
-- |
Deposit For Upgrades Received (0) 01.28.2022 |
|
|
-- |
-- |
Building Permit (30) 01.10.2022 |
|
|
-- |
-- |
Order Roof & Floor Trusses (1) 03.31.2022 |
|
|
-- |
-- |
Order Windows & Doors (0) 03.31.2022 |
|
|
-- |
-- |
Stake Out Home (1) 12.14.2021 |
|
|
-- |
-- |
Excavate (2) 01.17.2022 |
|
|
-- |
-- |
Inspection (Footers) (1) 01.17.2022 |
|
|
-- |
-- |
Inspection (Concrete Wall) (1) 09.07.2022 |
|
|
-- |
-- |
Pour Footers (1) 01.17.2022 |
|
|
-- |
-- |
Set Forms (2) 02.10.2022 |
|
|
-- |
-- |
Pour Foundation Walls (1) 02.10.2022 |
|
|
-- |
-- |
Plumb Slab (2) 02.24.2022 |
|
|
-- |
-- |
Inspection (Plumbing Under Slab) (1) 03.13.2022 |
|
|
-- |
-- |
Inspection (Conduit Under Slab) (1) 09.07.2022 |
|
|
-- |
-- |
Prepare Slab (1) 03.13.2022 |
|
|
-- |
-- |
Inspection (Slab) (1) 03.13.2022 |
|
|
-- |
-- |
Inspection (Drain Tile) (0) 09.07.2022 |
|
|
-- |
-- |
Pour Slab (1) * 03.13.2022 |
|
|
-- |
-- |
Settlement Agent Confirmed (0) 01.11.2022 |
|
|
-- |
-- |
Framing I (9) 03.24.2022 |
|
|
-- |
-- |
Order Steps (0) 04.11.2022 |
|
|
-- |
-- |
Order Tubs / Showers (0) 04.28.2022 |
|
|
-- |
-- |
Framing II (8) 03.31.2022 |
|
|
-- |
-- |
Framing III (8) * 04.04.2022 |
|
|
-- |
-- |
Install Stairs (0) 04.11.2022 |
|
|
-- |
-- |
Windows & Doors (0) 05.19.2022 |
|
|
-- |
-- |
House Number and Status in Window (0) 05.30.2022 |
|
|
-- |
-- |
Roofing (0) 05.02.2022 |
|
|
-- |
-- |
Order Cabinets (0) 01.31.2022 |
|
|
-- |
-- |
Order Appliances (0) 05.16.2022 |
Standard SS |
|
-- |
-- |
Deck (0) 05.30.2022 |
Needs railings EXPANDED |
|
-- |
-- |
Gutters (0) 06.29.2022 |
|
|
-- |
-- |
Driveway (0) 07.20.2022 |
Expanded Driveway, Expanded Patio 10 x 10. Week of july 18 |
|
-- |
-- |
Patio (0) 01.05.2023 |
|
|
-- |
-- |
Privacy Divider / Fence (0) 08.15.2022 |
Patio privacy divider? |
|
-- |
-- |
Sod / Seed / Landscaping (0) 08.29.2022 |
after closing |
|
-- |
-- |
HVAC Rough In (4) 05.05.2022 |
In process 4/18 |
|
-- |
-- |
Inspection (Rough In HVAC) (1) 05.12.2022 |
5/9 |
|
-- |
-- |
Plumbing Rough In (4) 05.08.2022 |
In process 5/4 |
|
-- |
-- |
Inspection (Rough In Plumbing) (1) 09.07.2022 |
|
|
-- |
-- |
Electric Rough In (4) 05.11.2022 |
In process 5/8 |
|
-- |
-- |
Inspection (Rough In Electric) (1) 09.07.2022 |
|
|
-- |
-- |
Inspection (Deck Piers) (0) 09.07.2022 |
|
|
-- |
-- |
Inspection (Framing) (1) 09.07.2022 |
|
|
-- |
-- |
Exterior Vinyl (0) * 06.25.2022 |
|
|
-- |
-- |
Exterior Stone (0) 06.25.2022 |
|
|
-- |
-- |
Insulation (2) 05.15.2022 |
|
|
-- |
-- |
Inspection (Insulation) (1) 05.16.2022 |
|
|
-- |
-- |
Inspection (Electric Service) (0) 07.25.2022 |
|
|
-- |
-- |
Set Electric Meter (0) 04.11.2023 |
|
|
-- |
-- |
Inspection (Main Sewer Line) (0) 03.13.2022 |
|
|
-- |
-- |
Inspection (Main Water Line) (0) 09.07.2022 |
|
|
-- |
-- |
Order Interior Doors & Trim (0) 05.16.2022 |
|
|
-- |
-- |
Drywall (Hang) (4) * 05.23.2022 |
Finish Bonus Room bath. In process 5/18 |
|
-- |
-- |
Loan Approval (0) 07.07.2022 |
|
|
-- |
-- |
Deed Preparation (0) 04.27.2022 |
|
|
-- |
-- |
Drywall (Tape, Block, Skim, Sand) (6) * 05.30.2022 |
in process 5/25 |
|
-- |
-- |
Paint 1 (1) 06.08.2022 |
|
|
-- |
-- |
Garage Door (0) 07.03.2022 |
|
|
-- |
-- |
House Numbers (0) 07.16.2022 |
|
|
-- |
-- |
Mailbox (0) 08.10.2022 |
|
|
-- |
-- |
Cabinet Installation (2) * 06.15.2022 |
June 12. On site 6/12 |
|
-- |
-- |
Granite Installation (1) * 08.03.2022 |
Tue, Jul 26. Partially complete 7/27 |
|
-- |
-- |
Interior Trim - Install (3) 06.29.2022 |
Needs painting 6/25 |
|
-- |
-- |
Interior Trim - Paint (1) 01.05.2023 |
|
|
-- |
-- |
Luxury Vinyl Plank (3) * 07.11.2022 |
In process 7/6 |
|
-- |
-- |
Luxury Vinyl Tile (0) 07.11.2022 |
In process 7/6 |
|
-- |
-- |
Paint 2 (3) 07.27.2022 |
|
|
-- |
-- |
Cover Floors (1) 07.11.2022 |
|
|
-- |
-- |
Deliver Plumbing / Lighting Fixtures (0) 07.14.2022 |
Upgrade Farmhouse, Touch 20 |
|
-- |
-- |
Shoe Moulding (0) 07.20.2022 |
Almost completed 7/16 |
|
-- |
-- |
Shelving, Door Knobs, Fire Extinguisher (0) 08.07.2022 |
Almost complete 8/3 |
|
-- |
-- |
Install Coded Lockbox (add extra keys) (0) 08.07.2022 |
|
|
-- |
-- |
Pay Water / Sewer Taps (0) 07.28.2022 |
|
|
-- |
-- |
Set Water Meter (0) 08.04.2022 |
|
|
-- |
-- |
Electric Trim Out (3) 08.07.2022 |
Brushed Nickel. In process |
|
-- |
-- |
Ceiling Fans (0) 07.07.2022 |
|
|
-- |
-- |
HVAC Trim Out (1) 07.27.2022 |
Almost completed 7/16 |
|
-- |
-- |
Plumbing Trim Out (2) 08.03.2022 |
Farmhouse Plumbing, Brushed Nickel- Touch 20. In process 7/27 |
|
-- |
-- |
Install Appliances (0) * 08.07.2022 |
|
|
-- |
-- |
Paint 3 (2) * 07.31.2022 |
|
|
-- |
-- |
Carpet (2) 07.03.2022 |
|
|
-- |
-- |
Appraiser Confirms Construction Completion (0) 08.10.2022 |
Johnny Hensley, Aug 8 |
|
-- |
-- |
Inspection (Final HVAC) (1) 09.07.2022 |
|
|
-- |
-- |
Inspection (Final Plumbing) (1) 09.07.2022 |
|
|
-- |
-- |
Inspection (Final Electric) (1) 09.07.2022 |
|
|
-- |
-- |
Inspection (Final Building) (2) * 08.07.2022 |
|
|
-- |
-- |
Pre Walk Through (0) 08.08.2022 |
|
|
-- |
-- |
Stain Hardwood Stairs (1) 08.11.2022 |
One coat of poly left 8/10-likely after closing. |
|
-- |
-- |
Cleaning (1) 08.08.2022 |
|
|
-- |
-- |
Certificate of Occupancy (1) * 08.09.2022 |
|
|
-- |
-- |
C.O. to Lender (0) 08.09.2022 |
|
|
-- |
-- |
Schedule Closing (0) 08.10.2022 |
|
|
-- |
-- |
Buyer Walk Through (1) 08.10.2022 |
|
|
-- |
-- |
Payment for Upgrades (0) 08.11.2022 |
|
|
-- |
-- |
Keys to Settlement Agent (0) 08.08.2022 |
|
|
-- |
-- |
Review Settlement Statement (0) 08.11.2022 |
|
|
-- |
-- |
Jerry Signs Closing Documents (0) 07.26.2022 |
|
|
-- |
-- |
Request Trash Tote From POA Manager (0) 08.11.2022 |
|
|
-- |
-- |
Closing (1) 08.11.2022 |
Brittany @ West View Title 8/10 at 1pm |
|
-- |
-- |
Remove Coded Lockbox (0) 08.29.2022 |
|
|