CONGERS-2 - 12  ::  1360 Palomino Trail
[ BUILD: 20220059 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
Fri    Sep 20      Verify Window & Roof Structure (0)      
Fri    Sep 20      Rough In Microwave Vent (0)      
--   --   Home Sale Contingency Settlement Deadline = 4/15/2022
--   --   Hardwood treads to upper level Don’t think needed?
--   --   Move doors for cabinets??? Cabinets in LR 8/24
--   --   Spice rack is difficult to open/close Waiting on cabinet people to come to fix it
--   --   Master bathroom wall/vanity not flush Tom - caulk
--   --   Quartz Vanity Topes
--   --   Quartz Vanity Tops Installed by 9/23. Remove existing countertops.
--   --   Blemish master vanity door?
--   --   Rate Lock Expires Oct 11 !!! Can be extended to Oct 14
--   --   Confirming LVP on 2nd floor-correct?
--   --   Two small areas of drywall damage on the ceiling
--   --   Missing some siding on corner 9/21 Front corner
--   --   Piece of missing siding at dormer
--   --   Bottom portion of vinyl “line”is white Davenport
--   --   Kitchen electrical outlets moved in island
--   --   Coded lockbox 1212
--   --   Outlet cover needed hall bath Electrician
--   --   Paint garage Painter
--   --   Paint garage 10/5 Trim needs completed
--   --   Black shower drain needed Plumber
--   --   Caulk shower panels Painter
--   --   Front stoop siding odd Davenport
--   --   Gap between door and door jamb at french door in kitchen? Weatherstripping
--   --   Paint touch up Painter
--   --   Trim garage 10/8 Edgar
--   --   Clean out bonus room
--   --   Remove dishwasher from dining room Tom
--   --   Needs shelves in master bath 10/10
--   --   White trim below French doors needed Tom
--   --   CODED LOCKBOX 1212
--   --   CODED LOCKBOX 1212
--   --   Three places in upstairs hall bath tub with cracks need to be repaired Oct 21
--   --   Leaking sink in master vanity
--   --   Final Paint Touch Up Painter
--   --   Install Screen Door Done? Tom
--   --   Stain Steps
--   --   Caulk sinks Painter
--   --   Paint show at front door and paint front door
--   --   Clean Back Patio and pressure wash
--   --   Snap light in hallway needs repaired or replaced Electrician
--   --   Drop off extra paint Painter
--   --   Broken part in freezer 10/31 - CJ has the part to install
--   --   Leave extra paint Painter
--   --   Refrigerator drawer difficult to use Jill will coordinate
--   --   Extra paint?
--   --   Street lights out Tom
--   --   Water pooling in backyard Tom - diversion ditch from sediment pond behind trailer
--   --   Sod behind house - does it need to be replaced?
--   --   Does water pool during heavy rains?
--   --   Adjust digital deadbolt for door lock Savannah looking at 10/9
--   --   2 threads going to bedroom level are cracked Tom going to check out 1:45 10/9
--   --   Cover at outside faucet to be fixed. Tom will look at
--   --   Red clay washed into yard Pettit
--   --   Address standing water Pettit
--   --   Back faucet cover Tom
-- -- Ratified Contract? (0)  01.07.2022    
-- -- $2500 Deposit Received (0)  01.11.2022    
-- -- Association Packet Requested (0)  01.07.2022    
-- -- Association Packet Received (0)  01.15.2022     1/7/2022: requested
-- -- Selections Meeting (0)  02.24.2022    
-- -- Selections Sheet Signed (0)  03.04.2022     2/23/2022: sent to Luke for signature
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  03.11.2022     3/11/2022: sent to Jerry for signature
-- -- Deposit For Upgrades Received (0)  03.11.2022    
-- -- Building Permit (30)  01.12.2022    
-- -- Order Roof & Floor Trusses (1)  05.02.2022    
-- -- Order Windows & Doors (0)  05.02.2022    
-- -- Stake Out Home (1)  02.24.2022    
-- -- Excavate (2)  03.07.2022    
-- -- Inspection (Footers) (1)  03.07.2022    
-- -- Inspection (Concrete Wall) (1)  09.07.2022    
-- -- Pour Footers (1)  03.07.2022    
-- -- Set Forms (2)  03.24.2022    
-- -- Pour Foundation Walls (1)  03.28.2022    
-- -- Plumb Slab (2)  04.19.2022    
-- -- Inspection (Plumbing Under Slab) (1)  04.21.2022    
-- -- Inspection (Conduit Under Slab) (1)  09.07.2022    
-- -- Prepare Slab (1)  04.25.2022    
-- -- Inspection (Slab) (1)  05.02.2022    
-- -- Inspection (Drain Tile) (0)  09.07.2022    
-- -- Pour Slab (1)  05.12.2022    
-- -- Settlement Agent Confirmed (0)  04.02.2022    
-- -- Framing I (9)  05.26.2022    
-- -- Order Steps (0)  06.18.2022    
-- -- Order Tubs / Showers (0)  06.20.2022    
-- -- Framing II (8)  06.02.2022    
-- -- Framing III (8)  06.05.2022    
-- -- Install Stairs (0)  06.25.2022    
-- -- Windows & Doors (0)  06.25.2022    
-- -- House Number and Status in Window (0)  07.07.2022    
-- -- Roofing (0)  08.17.2022    
-- -- Order Cabinets (0)  07.11.2022    
-- -- Order Appliances (0)  08.30.2022     Standard SS
-- -- Deck (0)  04.23.2022     n/a
-- -- Gutters (0)  10.05.2022     Greg
-- -- Driveway (0)  10.12.2022     STANDARD - apron in front of sidewalk
-- -- Patio (0)  10.11.2022    
-- -- Privacy Divider / Fence (0)  09.17.2022    
-- -- Sod / Seed / Landscaping (0)  10.20.2022    
-- -- HVAC Rough In (4)  06.25.2022    
-- -- Inspection (Rough In HVAC) (1)  07.27.2022    
-- -- Plumbing Rough In (4)  07.16.2022     In process7/13
-- -- Inspection (Rough In Plumbing) (1)  09.07.2022    
-- -- Electric Rough In (4)  07.24.2022     in process 7/21
-- -- Inspection (Rough In Electric) (1)  09.07.2022    
-- -- Inspection (Deck Piers) (0)  09.07.2022    
-- -- Inspection (Framing) (1)  09.07.2022    
-- -- Exterior Vinyl (0)  09.21.2022     in process 9/17
-- -- Exterior Stone (0)  04.14.2022    
-- -- Insulation (2)  07.27.2022    
-- -- Inspection (Insulation) (1)  08.03.2022    
-- -- Inspection (Electric Service) (0)  10.03.2022    
-- -- Set Electric Meter (0)  04.11.2023    
-- -- Inspection (Main Sewer Line) (0)  05.12.2022    
-- -- Inspection (Main Water Line) (0)  09.08.2022    
-- -- Order Interior Doors & Trim (0)  08.04.2022    
-- -- Drywall (Hang) (4)  08.03.2022     Stocked 7/31
-- -- Loan Approval (0)  09.20.2022    
-- -- Deed Preparation (0)  04.27.2022    
-- -- Drywall (Tape, Block, Skim, Sand) (6)  08.10.2022     In process 8/3
-- -- Paint 1 (1)  08.17.2022    
-- -- Garage Door (0)  09.28.2022    
-- -- House Numbers (0)  10.02.2022    
-- -- Mailbox (0)  09.29.2022    
-- -- Cabinet Installation (2)  08.28.2022     Thu, Aug 25
-- -- Granite Installation (1)  09.24.2022     templated 9/7, by 9/23
-- -- Interior Trim - Install (3)  09.14.2022     Needs painting 9/11
-- -- Order Plumbing / Lighting Fixtures (0)  09.20.2023    
-- -- Interior Trim - Paint (1)  10.26.2022    
-- -- Luxury Vinyl Plank (3)  09.21.2022     main level completed 9/17
-- -- Luxury Vinyl Tile (0)  09.21.2022     In process
-- -- Paint 2 (3)  09.17.2022    
-- -- Cover Floors (1)  09.28.2022    
-- -- Deliver Plumbing / Lighting Fixtures (0)  09.19.2022     Black Plumbing, Black Lighting
-- -- Shoe Moulding (0)  09.24.2022    
-- -- Shelving, Door Knobs, Fire Extinguisher (0)  10.08.2022     Black accessories, shower door black trim. In process 10/5. Interior Handles are completed.
-- -- Install Coded Lockbox (add extra keys) (0)  10.02.2022    
-- -- Pay Water / Sewer Taps (0)  09.19.2022    
-- -- Set Water Meter (0)  09.29.2022    
-- -- Electric Trim Out (3)  10.02.2022     Black Standard. Started 9/28
-- -- Ceiling Fans (0)  10.03.2022    
-- -- HVAC Trim Out (1)  09.28.2022     In process 9/14
-- -- Blower Door Test (1)  10.27.2023    
-- -- Plumbing Trim Out (2)  10.02.2022     Black Standard. In process 9/24. Only hall bath needs completing.
-- -- Install Appliances (0)  10.05.2022    
-- -- Paint 3 (2)  09.17.2022    
-- -- Carpet (2)  09.19.2022    
-- -- Appraiser Confirms Construction Completion (0)  10.11.2022     Jeff Eye, Monday, Oct 10
-- -- Inspection (Final HVAC) (1)  10.06.2022    
-- -- Inspection (Final Plumbing) (1)  10.06.2022    
-- -- Inspection (Final Electric) (1)  10.06.2022    
-- -- Inspection (Final Building) (2)  10.10.2022     Re-inspect, Thursday, Oct 6
-- -- Pre Walk Through (0)  10.10.2022     Thu, Oct 6
-- -- Stain Hardwood Stairs (1)  10.14.2022     Jill will coordinate with painter. In process 10/12
-- -- Cleaning (1)  10.10.2022    
-- -- Certificate of Occupancy (1)  10.11.2022    
-- -- C.O. to Lender (0)  10.11.2022    
-- -- Schedule Closing (0)  10.10.2022     Oct 14?
-- -- Buyer Walk Through (1)  10.11.2022     Monday, Oct 10 at 12PM
-- -- Payment for Upgrades (0)  10.10.2022    
-- -- Keys to Settlement Agent (0)  10.10.2022    
-- -- Review Settlement Statement (0)  10.13.2022    
-- -- Jerry Signs Closing Documents (0)  10.13.2022    
-- -- Request Trash Tote From POA Manager (0)  10.11.2022    
-- -- Closing (1)  10.17.2022     Brittany @ West View Title, Oct 14
-- -- Remove Coded Lockbox (0)  11.10.2022