| TO DO | ||||
| --- | ||||
| UPGRADES | ||||
| Quartz Countertops Kitchen | ||||
| LVP Upper Level | ||||
| CRITICAL PATH | ||||
| --- | ||||
| TO DO - COMPLETED OR DELETED | ||||
| UPGRADES - COMPLETED | ||||
| White Painted Kitchen Cabinetry | ||||
| Farmhouse Kitchen Sink | ||||
| Three Drawer Stack | ||||
| Double Waste Basket | ||||
| Painted Pine steps | ||||
| White Subway Tile Shower Walls | ||||
| Shower Door with black trim | ||||
| Digital Deadbolt | ||||
| Spice Rack | ||||
| Ship Lap Living Room Wall | ||||
| Amendment to increase price by $13,325 | ||||
| CRITICAL PATH - COMPLETED | ||||
| -- | -- | Inspection (Footers) (1) 03.07.2022 | ||
| -- | -- | Inspection (Concrete Wall) (1) 09.07.2022 | ||
| -- | -- | Inspection (Plumbing Under Slab) (1) 04.21.2022 | ||
| -- | -- | Inspection (Conduit Under Slab) (1) 09.07.2022 | ||
| -- | -- | Inspection (Slab) (1) 05.02.2022 | ||
| -- | -- | Inspection (Drain Tile) (0) 09.07.2022 | ||
| -- | -- | Inspection (Rough In HVAC) (1) 07.27.2022 | ||
| -- | -- | Inspection (Rough In Plumbing) (1) 09.07.2022 | ||
| -- | -- | Inspection (Rough In Electric) (1) 09.07.2022 | ||
| -- | -- | Inspection (Framing) (1) * 09.07.2022 | ||
| -- | -- | Inspection (Deck Piers) (0) 09.07.2022 | ||
| -- | -- | Inspection (Insulation) (1) 08.03.2022 | ||
| -- | -- | Inspection (Electric Service) (0) 10.03.2022 | ||
| -- | -- | Inspection (Main Sewer Line) (0) 05.12.2022 | ||
| -- | -- | Inspection (Main Water Line) (0) 09.08.2022 | ||
| -- | -- | Inspection (Final HVAC) (0) 10.06.2022 | ||
| -- | -- | Inspection (Final Plumbing) (0) 10.06.2022 | ||
| -- | -- | Inspection (Final Electric) (0) 10.06.2022 | ||
| -- | -- | Inspection (Final Building) (4) * 10.10.2022 | Re-inspect, Thursday, Oct 6 | |