Fri |
Sep 20 |
Verify Window & Roof Structure (0)
|
|
|
Fri |
Sep 20 |
Rough In Microwave Vent (0)
|
|
|
Fri |
Sep 20 |
Blower Door Test (1)
|
|
|
|
-- |
-- |
120 and 119 cabinets are now in drywall way |
|
|
-- |
-- |
Final drywall sanding needed. Cover kitchen cabinets? |
|
|
-- |
-- |
Kitchen hardware needed |
|
|
-- |
-- |
Garage framing trim issue |
Nail trim down9/4 |
|
-- |
-- |
Drywall patch electric panel |
in process 8/31 |
|
-- |
-- |
Side splash needed in hall bath |
Jill will look in model |
|
-- |
-- |
24" bonus vanity on order- to be installed after closing |
delivering 10/3 |
|
-- |
-- |
Gutter repair 8/31 |
|
|
-- |
-- |
Paint small concrete area adjoining 120? |
Below siding, painter |
|
-- |
-- |
Bathroom trim |
Henry |
|
-- |
-- |
Cable outlet covers needed |
Living room |
|
-- |
-- |
Plate cover needed near basement steps |
Electrician |
|
-- |
-- |
CODED LOCKBOX 0119 |
|
|
-- |
-- |
PICTURES OF KITCHEN WHEN COMPLETE |
|
|
-- |
-- |
Adjust closet doors Upstairs bedrooms |
|
|
-- |
-- |
Repair hole in ground level tub/shower |
Oct 21 |
|
-- |
-- |
Ceiling fans in family room, all bedrooms |
Just living room and bonus room, after drywall patch |
|
-- |
-- |
Damaged concrete on left side of driveway |
Tom |
|
-- |
-- |
Tell Scott when kitchen is complete and clean |
|
|
-- |
-- |
Patch holes in white trim board |
Greg, Davenport. Not patched 11/26 |
|
-- |
-- |
Trim in front of tub needed |
|
|
-- |
-- |
Replace door to bedroom that’s peeling |
Edgar. It’s caulked and painted 10/19 |
|
-- |
-- |
Screens |
Jill |
|
-- |
-- |
Power Washing Front/Patio |
Jill |
|
-- |
-- |
nail trim at garage door |
|
|
-- |
-- |
weatherstripping on back basement french door |
Jill |
|
-- |
-- |
remove silicone on basement sink |
Jill |
|
-- |
-- |
paint touch up |
Painter |
|
-- |
-- |
4 ceiling fans need installed |
Electrician |
|
-- |
-- |
remove paint from kitchen french dooe trim |
|
|
-- |
-- |
remove paint from kitchen french door trim |
Bottom of door, Jill? |
|
-- |
-- |
touch up cabinets with paint pen (blue taped) |
Jill |
|
-- |
-- |
replace register cover |
laundry room, Jill |
|
-- |
-- |
replace left bedroom closet door (large hole) |
Jill. It’s caulked and painted 10/19 |
|
-- |
-- |
Replace left side of garage door trim / weatherstripping |
Greg, Davenport |
|
-- |
-- |
Remove extra screens |
|
|
-- |
-- |
Remove gutter splash blocks from driveway |
Tom |
|
-- |
-- |
Gravel between 119 and 120 |
|
|
-- |
-- |
Replace dead and sinking sod behind house |
Pettit- Courtney thinks this is looking much better 11/26 |
|
-- |
-- |
|
|
|
-- |
-- |
Should we clean spill in garage? |
Jill |
|
-- |
-- |
Reclean |
Jill will coordinate |
|
-- |
-- |
Ratified Contract? (0)
01.10.2022 |
|
|
-- |
-- |
$2500 Deposit Received (0)
01.14.2022 |
|
|
-- |
-- |
Association Packet Requested (0)
01.10.2022 |
|
|
-- |
-- |
Association Packet Received (0)
01.15.2022 |
1/9/2022: requested |
|
-- |
-- |
Selections Meeting (0)
02.11.2022 |
|
|
-- |
-- |
Selections Sheet Signed (0)
02.12.2022 |
2/11/2022: sent to buyer for signatures |
|
-- |
-- |
Amendment for Upgrades (B,S,L,T,BCP) (0)
07.11.2022 |
7/8/2022: updating |
|
-- |
-- |
Deposit For Upgrades Received (0)
03.22.2022 |
|
|
-- |
-- |
Building Permit (30)
01.12.2022 |
|
|
-- |
-- |
Order Roof & Floor Trusses (1)
05.02.2022 |
|
|
-- |
-- |
Order Windows & Doors (0)
05.03.2022 |
|
|
-- |
-- |
Stake Out Home (1)
01.27.2022 |
|
|
-- |
-- |
Excavate (2)
01.31.2022 |
|
|
-- |
-- |
Inspection (Footers) (1)
01.31.2022 |
|
|
-- |
-- |
Inspection (Concrete Wall) (1)
09.07.2022 |
|
|
-- |
-- |
Pour Footers (1)
01.31.2022 |
|
|
-- |
-- |
Set Forms (2)
02.10.2022 |
|
|
-- |
-- |
Pour Foundation Walls (1)
02.10.2022 |
|
|
-- |
-- |
Plumb Slab (2)
03.31.2022 |
|
|
-- |
-- |
Inspection (Plumbing Under Slab) (1)
03.31.2022 |
|
|
-- |
-- |
Inspection (Conduit Under Slab) (1)
09.07.2022 |
|
|
-- |
-- |
Prepare Slab (1)
03.31.2022 |
|
|
-- |
-- |
Inspection (Slab) (1)
03.31.2022 |
|
|
-- |
-- |
Inspection (Drain Tile) (0)
09.07.2022 |
|
|
-- |
-- |
Pour Slab (1)
03.31.2022 |
|
|
-- |
-- |
Settlement Agent Confirmed (0)
08.19.2022 |
|
|
-- |
-- |
Framing I (9)
04.19.2022 |
Starting 4/11, Trusses Apr 18 |
|
-- |
-- |
Order Steps (0)
05.05.2022 |
|
|
-- |
-- |
Order Tubs / Showers (0)
05.30.2022 |
|
|
-- |
-- |
Framing II (8)
04.28.2022 |
|
|
-- |
-- |
Framing III (8)
05.16.2022 |
|
|
-- |
-- |
Install Stairs (0)
05.30.2022 |
|
|
-- |
-- |
Windows & Doors (0)
05.30.2022 |
|
|
-- |
-- |
House Number and Status in Window (0)
06.12.2022 |
|
|
-- |
-- |
Roofing (0)
05.30.2022 |
|
|
-- |
-- |
Order Cabinets (0)
07.07.2022 |
|
|
-- |
-- |
Order Appliances (0)
06.20.2022 |
Standard SS |
|
-- |
-- |
Deck (0)
05.30.2022 |
Expanded Deck 12 x 12 |
|
-- |
-- |
Gutters (0)
08.03.2022 |
|
|
-- |
-- |
Driveway (0)
08.25.2022 |
Expanded Driveway, Expanded Patio 10 x 10 |
|
-- |
-- |
Patio (0)
10.11.2022 |
|
|
-- |
-- |
Privacy Divider / Fence (0)
09.17.2022 |
|
|
-- |
-- |
Sod / Seed / Landscaping (0)
08.28.2022 |
|
|
-- |
-- |
HVAC Rough In (4)
05.30.2022 |
In process 5/25 |
|
-- |
-- |
Inspection (Rough In HVAC) (1)
07.06.2022 |
|
|
-- |
-- |
Plumbing Rough In (4)
07.03.2022 |
In process 6/18 |
|
-- |
-- |
Inspection (Rough In Plumbing) (1)
09.07.2022 |
|
|
-- |
-- |
Electric Rough In (4)
07.03.2022 |
In process 6/29 |
|
-- |
-- |
Inspection (Rough In Electric) (1)
09.07.2022 |
|
|
-- |
-- |
Inspection (Deck Piers) (0)
09.07.2022 |
|
|
-- |
-- |
Inspection (Framing) (1)
09.07.2022 |
|
|
-- |
-- |
Exterior Vinyl (0)
08.08.2022 |
|
|
-- |
-- |
Exterior Stone (0)
08.28.2022 |
In process 8/14 |
|
-- |
-- |
Insulation (2)
07.06.2022 |
|
|
-- |
-- |
Inspection (Insulation) (1)
07.10.2022 |
|
|
-- |
-- |
Inspection (Electric Service) (0)
09.12.2022 |
|
|
-- |
-- |
Set Electric Meter (0)
04.11.2023 |
|
|
-- |
-- |
Inspection (Main Sewer Line) (0)
05.12.2022 |
|
|
-- |
-- |
Inspection (Main Water Line) (0)
09.07.2022 |
|
|
-- |
-- |
Order Interior Doors & Trim (0)
06.27.2022 |
|
|
-- |
-- |
Drywall (Hang) (4)
07.10.2022 |
Finish Bonus Room, Bath |
|
-- |
-- |
Loan Approval (0)
09.19.2022 |
|
|
-- |
-- |
Deed Preparation (0)
09.19.2022 |
|
|
-- |
-- |
Drywall (Tape, Block, Skim, Sand) (6)
08.07.2022 |
In process 7/23 |
|
-- |
-- |
Paint 1 (1)
08.10.2022 |
|
|
-- |
-- |
Garage Door (0)
09.04.2022 |
|
|
-- |
-- |
House Numbers (0)
09.29.2022 |
|
|
-- |
-- |
Mailbox (0)
09.15.2022 |
|
|
-- |
-- |
Cabinet Installation (2)
08.10.2022 |
Delivered 7/27 |
|
-- |
-- |
Granite Installation (1)
09.04.2022 |
Week of Aug 29 |
|
-- |
-- |
Interior Trim - Install (3)
09.11.2022 |
Needs painted 9/7 |
|
-- |
-- |
Order Plumbing / Lighting Fixtures (0)
09.21.2023 |
|
|
-- |
-- |
Interior Trim - Paint (1)
10.26.2022 |
|
|
-- |
-- |
Luxury Vinyl Plank (3)
09.24.2022 |
In process 9/21 |
|
-- |
-- |
Luxury Vinyl Tile (0)
09.14.2022 |
|
|
-- |
-- |
Paint 2 (3)
09.14.2022 |
Needs completed so flooring people can arrive asap! |
|
-- |
-- |
Cover Floors (1)
09.28.2022 |
|
|
-- |
-- |
Deliver Plumbing / Lighting Fixtures (0)
08.25.2022 |
|
|
-- |
-- |
Shoe Moulding (0)
09.28.2022 |
In process 9/24 |
|
-- |
-- |
Shelving, Door Knobs, Fire Extinguisher (0)
10.12.2022 |
Black accessories |
|
-- |
-- |
Install Coded Lockbox (add extra keys) (0)
10.10.2022 |
|
|
-- |
-- |
Pay Water / Sewer Taps (0)
08.25.2022 |
|
|
-- |
-- |
Set Water Meter (0)
09.08.2022 |
|
|
-- |
-- |
Electric Trim Out (3)
10.10.2022 |
In process 10/5. Need powder bath light and bulbs. |
|
-- |
-- |
Ceiling Fans (0)
10.05.2022 |
|
|
-- |
-- |
HVAC Trim Out (1)
09.17.2022 |
|
|
-- |
-- |
Plumbing Trim Out (2)
10.05.2022 |
Black Farmhouse upgrade |
|
-- |
-- |
Install Appliances (0)
09.15.2022 |
|
|
-- |
-- |
Paint 3 (2)
09.14.2022 |
|
|
-- |
-- |
Carpet (2)
10.02.2022 |
|
|
-- |
-- |
Appraiser Confirms Construction Completion (0)
10.14.2022 |
Oct 8 or 9 |
|
-- |
-- |
Inspection (Final HVAC) (1)
10.12.2022 |
|
|
-- |
-- |
Inspection (Final Plumbing) (1)
10.14.2022 |
|
|
-- |
-- |
Inspection (Final Electric) (1)
10.14.2022 |
|
|
-- |
-- |
Inspection (Final Building) (2)
10.14.2022 |
Wed, Oct 12 |
|
-- |
-- |
Pre Walk Through (0)
10.10.2022 |
|
|
-- |
-- |
Stain Hardwood Stairs (1)
10.08.2022 |
|
|
-- |
-- |
Cleaning (1)
10.12.2022 |
|
|
-- |
-- |
Certificate of Occupancy (1)
10.14.2022 |
|
|
-- |
-- |
C.O. to Lender (0)
10.14.2022 |
|
|
-- |
-- |
Schedule Closing (0)
10.18.2022 |
|
|
-- |
-- |
Buyer Walk Through (1)
10.15.2022 |
Friday 10/14 |
|
-- |
-- |
Payment for Upgrades (0)
10.20.2022 |
$1,040 for fans |
|
-- |
-- |
Keys to Settlement Agent (0)
10.10.2022 |
|
|
-- |
-- |
Review Settlement Statement (0)
10.20.2022 |
|
|
-- |
-- |
Jerry Signs Closing Documents (0)
09.28.2022 |
|
|
-- |
-- |
Request Trash Tote From POA Manager (0)
10.10.2022 |
|
|
-- |
-- |
Closing (1)
10.20.2022 |
Brittany @ West View Title, Oct 19 at 2PM |
|
-- |
-- |
Remove Coded Lockbox (0)
11.17.2022 |
|
|