Thu |
Nov 28 |
Verify Window & Roof Structure (0) |
|
|
Thu |
Nov 28 |
Rough In Microwave Vent (0) |
|
|
Thu |
Nov 28 |
Order Plumbing / Lighting Fixtures (0) |
|
|
Thu |
Nov 28 |
Blower Door Test (1) |
|
|
|
-- |
-- |
Up tub & shower pan needed 5/30 |
Tub is in 6/5 |
|
-- |
-- |
Hole in subfloor near cabinet |
|
|
-- |
-- |
Basement vanity needed |
Tom picking up today- black hardware on order. |
|
-- |
-- |
3 drawer stack not present |
Ordered- will be installed after closing. |
|
-- |
-- |
Bathroom cabinet hardware needed |
|
|
-- |
-- |
Cabinet hardware needed upstairs-both vanities |
Kate has it |
|
-- |
-- |
Drywall repair electrical panel |
|
|
-- |
-- |
Base closet drywall repair |
In process 9/4 |
|
-- |
-- |
Garage trim is a little bent |
|
|
-- |
-- |
White cabinet with BLACK handles in basement |
Jill - handles |
|
-- |
-- |
Lid to water hole needed on side of driveway 9/4 |
|
|
-- |
-- |
Cabinet corner piece |
Trim guy, corner of island |
|
-- |
-- |
Hall shower bottom piece missing |
overflow cover - plumber |
|
-- |
-- |
Attic cover and trim needed |
|
|
-- |
-- |
Attic frame and cover needed |
Painter - paint it |
|
-- |
-- |
Doorstop needed behind basement door |
Joe |
|
-- |
-- |
Install shower rod |
Hall bath, 9/21, Joe |
|
-- |
-- |
|
|
|
-- |
-- |
Fix trim in basement bath |
Trim. Needs caulking 9/24, Painter |
|
-- |
-- |
Light needed in bonus room |
Electrician |
|
-- |
-- |
Weatherstripping on doors |
Painter |
|
-- |
-- |
Front door knobs needed |
|
|
-- |
-- |
Half bath needs mirror |
Joe, 9/27 |
|
-- |
-- |
CODED LOCKBOX 0122 |
|
|
-- |
-- |
Drywall repair living room receptacle |
Just needs painting 9/24, Painter |
|
-- |
-- |
Adjust upstairs closet doors |
Jill |
|
-- |
-- |
Master bath mirror needed |
Joe, 9/27 |
|
-- |
-- |
Cable cover |
Jill |
|
-- |
-- |
nail holes in back and side panels of kitchen island- |
Ordered by Fred 9/29, panels arrive 10/19 |
|
-- |
-- |
Home Inspection, Mon, Oct 3 at 9AM |
|
|
-- |
-- |
pressure wash front & back patio |
has to be sanded (per Tom) by painters |
|
-- |
-- |
finish cleaning out garage |
Jill |
|
-- |
-- |
cable cover in garage needed |
|
|
-- |
-- |
paint touch up |
|
|
-- |
-- |
remove blue tape on transition to utility room |
Cleaner |
|
-- |
-- |
install all mirrors |
|
|
-- |
-- |
push down pins on all doors |
|
|
-- |
-- |
final clean |
|
|
-- |
-- |
cabinet paint touch up pen- white |
Will be brought on Tues/Wed by Fred |
|
-- |
-- |
mop deck |
Jill |
|
-- |
-- |
remove glue from deck divider |
Jill |
|
-- |
-- |
sand white cabinet down |
Jill |
|
-- |
-- |
hook up water to fridge |
|
|
-- |
-- |
caulk sides and back of steps |
Painter |
|
-- |
-- |
black master bath shower drain needed |
Plumber |
|
-- |
-- |
patch sod in yard |
Pettit |
|
-- |
-- |
remove front door plastic on transition strip |
Jill |
|
-- |
-- |
Master bath towel ring correct? |
Joe |
|
-- |
-- |
HVAC filters |
|
|
-- |
-- |
remove nails from deck |
Jill or Tom or Isaac |
|
-- |
-- |
landscaping repairs |
Pettit |
|
-- |
-- |
Basement screen door adjustment |
Tom |
|
-- |
-- |
Basement door does not latch properly |
Jill or Tom or Kenny |
|
-- |
-- |
Garage door button is loose |
Greg will contact Justin |
|
-- |
-- |
paint touch up (blue taped) |
Hopefully 10/18 |
|
-- |
-- |
scratch in master bedroom floor |
Denny will repair it Eric going by Tuesday/Wednesday |
|
-- |
-- |
Sand deck |
Tom |
|
-- |
-- |
Justin Minges, 919-757-8283 |
|
|
-- |
-- |
Ratified Contract? (0) 01.09.2022 |
|
|
-- |
-- |
$2500 Deposit Received (0) 01.10.2022 |
|
|
-- |
-- |
Association Packet Requested (0) 01.09.2022 |
|
|
-- |
-- |
Association Packet Received (0) 01.15.2022 |
1/9/2022: requested |
|
-- |
-- |
Selections Meeting (0) 01.24.2022 |
|
|
-- |
-- |
Selections Sheet Signed (0) 03.19.2022 |
2/2/2022: sent to Courtney for buyer signatures |
|
-- |
-- |
Amendment for Upgrades (B,S,L,T,BCP) (0) 07.28.2022 |
4/1/2022: sent to Jerry for signatures |
|
-- |
-- |
Deposit For Upgrades Received (0) 04.01.2022 |
|
|
-- |
-- |
Building Permit (30) 01.12.2022 |
|
|
-- |
-- |
Order Roof & Floor Trusses (1) 05.02.2022 |
|
|
-- |
-- |
Order Windows & Doors (0) 05.03.2022 |
|
|
-- |
-- |
Stake Out Home (1) 01.27.2022 |
|
|
-- |
-- |
Excavate (2) 01.31.2022 |
|
|
-- |
-- |
Inspection (Footers) (1) 01.31.2022 |
|
|
-- |
-- |
Inspection (Concrete Wall) (1) 09.07.2022 |
|
|
-- |
-- |
Pour Footers (1) 01.31.2022 |
|
|
-- |
-- |
Set Forms (2) 02.10.2022 |
|
|
-- |
-- |
Pour Foundation Walls (1) 02.10.2022 |
|
|
-- |
-- |
Plumb Slab (2) 03.24.2022 |
|
|
-- |
-- |
Inspection (Plumbing Under Slab) (1) 03.31.2022 |
|
|
-- |
-- |
Inspection (Conduit Under Slab) (1) 09.07.2022 |
|
|
-- |
-- |
Prepare Slab (1) 03.31.2022 |
|
|
-- |
-- |
Inspection (Slab) (1) 03.31.2022 |
|
|
-- |
-- |
Inspection (Drain Tile) (0) 09.07.2022 |
|
|
-- |
-- |
Pour Slab (1) * 03.31.2022 |
|
|
-- |
-- |
Settlement Agent Confirmed (0) 04.02.2022 |
|
|
-- |
-- |
Framing I (9) 04.19.2022 |
|
|
-- |
-- |
Order Steps (0) 05.05.2022 |
|
|
-- |
-- |
Order Tubs / Showers (0) 06.20.2022 |
American Standard White Subway Tile |
|
-- |
-- |
Framing II (8) 04.28.2022 |
|
|
-- |
-- |
Framing III (8) * 05.16.2022 |
|
|
-- |
-- |
Install Stairs (0) 05.30.2022 |
|
|
-- |
-- |
Windows & Doors (0) 05.30.2022 |
|
|
-- |
-- |
House Number and Status in Window (0) 06.12.2022 |
|
|
-- |
-- |
Roofing (0) 05.30.2022 |
|
|
-- |
-- |
Order Cabinets (0) 07.07.2022 |
|
|
-- |
-- |
Order Appliances (0) 06.20.2022 |
French Upgrade |
|
-- |
-- |
Deck (0) 05.30.2022 |
Expanded Deck 12 x 12 |
|
-- |
-- |
Gutters (0) 08.03.2022 |
|
|
-- |
-- |
Driveway (0) 08.25.2022 |
Expanded Driveway |
|
-- |
-- |
Patio (0) 10.11.2022 |
|
|
-- |
-- |
Privacy Divider / Fence (0) 09.17.2022 |
|
|
-- |
-- |
Sod / Seed / Landscaping (0) 08.28.2022 |
|
|
-- |
-- |
HVAC Rough In (4) 05.21.2022 |
|
|
-- |
-- |
Inspection (Rough In HVAC) (1) 06.25.2022 |
|
|
-- |
-- |
Plumbing Rough In (4) 06.20.2022 |
In process 6/8 |
|
-- |
-- |
Inspection (Rough In Plumbing) (1) 09.07.2022 |
|
|
-- |
-- |
Electric Rough In (4) 06.25.2022 |
|
|
-- |
-- |
Inspection (Rough In Electric) (1) 09.07.2022 |
|
|
-- |
-- |
Inspection (Deck Piers) (0) 09.07.2022 |
|
|
-- |
-- |
Inspection (Framing) (1) 09.07.2022 |
|
|
-- |
-- |
Exterior Vinyl (0) * 07.11.2022 |
|
|
-- |
-- |
Exterior Stone (0) 04.14.2022 |
|
|
-- |
-- |
Insulation (2) 06.25.2022 |
|
|
-- |
-- |
Inspection (Insulation) (1) 06.30.2022 |
Mon, Jun 27 |
|
-- |
-- |
Inspection (Electric Service) (0) 09.12.2022 |
|
|
-- |
-- |
Set Electric Meter (0) 04.11.2023 |
|
|
-- |
-- |
Inspection (Main Sewer Line) (0) 05.12.2022 |
|
|
-- |
-- |
Inspection (Main Water Line) (0) 09.07.2022 |
|
|
-- |
-- |
Order Interior Doors & Trim (0) 06.27.2022 |
|
|
-- |
-- |
Drywall (Hang) (4) * 07.10.2022 |
In process 7/6 |
|
-- |
-- |
Loan Approval (0) 09.15.2022 |
|
|
-- |
-- |
Deed Preparation (0) 04.27.2022 |
|
|
-- |
-- |
Drywall (Tape, Block, Skim, Sand) (6) * 07.23.2022 |
in process 7/20 |
|
-- |
-- |
Paint 1 (1) 07.23.2022 |
|
|
-- |
-- |
Garage Door (0) 08.10.2022 |
|
|
-- |
-- |
House Numbers (0) 08.20.2022 |
|
|
-- |
-- |
Mailbox (0) 09.15.2022 |
Posts in 9/4 |
|
-- |
-- |
Cabinet Installation (2) * 08.03.2022 |
In process 7/27 |
|
-- |
-- |
Granite Installation (1) * 09.04.2022 |
Week of Aug 29 |
|
-- |
-- |
Interior Trim - Install (3) 08.14.2022 |
Needs painting 8/10 |
|
-- |
-- |
Interior Trim - Paint (1) 10.26.2022 |
|
|
-- |
-- |
Luxury Vinyl Plank (3) * 09.11.2022 |
98% complete 9/7 |
|
-- |
-- |
Luxury Vinyl Tile (0) 08.28.2022 |
|
|
-- |
-- |
Paint 2 (3) 08.28.2022 |
In process 8/24 |
|
-- |
-- |
Cover Floors (1) 09.15.2022 |
|
|
-- |
-- |
Deliver Plumbing / Lighting Fixtures (0) 08.25.2022 |
|
|
-- |
-- |
Shoe Moulding (0) 09.14.2022 |
|
|
-- |
-- |
Shelving, Door Knobs, Fire Extinguisher (0) 09.24.2022 |
Black accessories, . In process 9/21 |
|
-- |
-- |
Install Coded Lockbox (add extra keys) (0) 09.21.2022 |
|
|
-- |
-- |
Pay Water / Sewer Taps (0) 08.25.2022 |
|
|
-- |
-- |
Set Water Meter (0) 09.08.2022 |
|
|
-- |
-- |
Electric Trim Out (3) 09.17.2022 |
Black standard. In process 9/14 almost completed |
|
-- |
-- |
Ceiling Fans (0) 09.14.2022 |
|
|
-- |
-- |
HVAC Trim Out (1) 09.21.2022 |
In process 9/14 |
|
-- |
-- |
Plumbing Trim Out (2) 09.14.2022 |
Black farmhouse upgrade. In process 9/11 |
|
-- |
-- |
Install Appliances (0) * 09.17.2022 |
On site 9/11 |
|
-- |
-- |
Paint 3 (2) * 09.04.2022 |
|
|
-- |
-- |
Carpet (2) 09.07.2022 |
|
|
-- |
-- |
Appraiser Confirms Construction Completion (0) 10.06.2022 |
|
|
-- |
-- |
Inspection (Final HVAC) (1) 09.26.2022 |
|
|
-- |
-- |
Inspection (Final Plumbing) (1) 09.26.2022 |
|
|
-- |
-- |
Inspection (Final Electric) (1) 09.26.2022 |
|
|
-- |
-- |
Inspection (Final Building) (2) * 09.28.2022 |
Mon, Sep 26 |
|
-- |
-- |
Pre Walk Through (0) 09.26.2022 |
|
|
-- |
-- |
Stain Hardwood Stairs (1) 09.21.2022 |
In process 9/17 |
|
-- |
-- |
Cleaning (1) 10.02.2022 |
Sat, Sep 24 |
|
-- |
-- |
Certificate of Occupancy (1) * 09.28.2022 |
|
|
-- |
-- |
C.O. to Lender (0) 09.28.2022 |
|
|
-- |
-- |
Schedule Closing (0) 09.26.2022 |
|
|
-- |
-- |
Buyer Walk Through (1) 10.08.2022 |
Friday, Oct 7 at 11AM |
|
-- |
-- |
Payment for Upgrades (0) 09.29.2022 |
|
|
-- |
-- |
Keys to Settlement Agent (0) 09.26.2022 |
|
|
-- |
-- |
Review Settlement Statement (0) 10.08.2022 |
|
|
-- |
-- |
Jerry Signs Closing Documents (0) 09.28.2022 |
|
|
-- |
-- |
Request Trash Tote From POA Manager (0) 10.03.2022 |
|
|
-- |
-- |
Closing (1) 10.08.2022 |
Brittany @ West View Title, Oct 7 |
|
-- |
-- |
Remove Coded Lockbox (0) 11.14.2022 |
|
|