Masted bedroom window needed |
|
|
-- |
-- |
Fix hardwood tread cover |
|
|
-- |
-- |
Bottom half of upper steps missing cover |
|
|
-- |
-- |
Large crack in hardwood treads to upper level |
Domingo |
|
-- |
-- |
1031 Exchange - deadline to close is Dec 31 |
|
|
-- |
-- |
Dented garage trim |
|
|
-- |
-- |
Leave extra chain for dining chandelier |
Swap with fixture being delivered this weekend. |
|
-- |
-- |
Microwave in kitchen is scratched/dented |
|
|
-- |
-- |
Needs basement closet door |
Jill installing |
|
-- |
-- |
Maybe ceiling fan globe is broken? Up bedroom. |
Kate trying to order new globe or fan, 12/8 |
|
-- |
-- |
Missing m bedroom handle |
Joe |
|
-- |
-- |
Keys? |
|
|
-- |
-- |
Garage trim |
Trim |
|
-- |
-- |
Cable cover in garage needed |
Jill |
|
-- |
-- |
Clean garage |
Jill |
|
-- |
-- |
Att ic cover needed |
Jill |
|
-- |
-- |
All mirrors needed |
Joe, Monday 12/12 |
|
-- |
-- |
Shower door needed |
Joe, Monday 12/12 |
|
-- |
-- |
touch up paint throughout |
Walls done/trim needs completed |
|
-- |
-- |
paint attic access panel |
|
|
-- |
-- |
handle needed for basement closet door |
Monday 12/12, joe |
|
-- |
-- |
swap torn piece of weather stripping with a new one |
Jill |
|
-- |
-- |
screens need installed |
Jill - all except front three |
|
-- |
-- |
landing ar first set if stairs has a gap between the shoe mold and floor that needs filled in. |
Painter |
|
-- |
-- |
hose under kitchen sink needs tacked up |
Tom |
|
-- |
-- |
cabinet door under sink is loose and needs tightened up. |
Fred |
|
-- |
-- |
line on ceiling above living room window needs fixed |
Painter |
|
-- |
-- |
big hole in closet under stairs on 2nd level |
Painter |
|
-- |
-- |
need another coat of paint on all the walls in the kitchen/dining areas |
|
|
-- |
-- |
repaint all handrails |
Painter |
|
-- |
-- |
caulk along all the seams of the stairs throughout home |
Painter |
|
-- |
-- |
sand all corners of the tray ceiling and psint |
|
|
-- |
-- |
sand all corners of the tray ceiling and repaint |
Painter |
|
-- |
-- |
replace ceiling fan in guest bedroom to the right |
electricians - broken globe - need fan |
|
-- |
-- |
scuff marks on exiting above fan in guest bedroom to right |
painters |
|
-- |
-- |
guest bathroom needs ceiling painted |
painters |
|
-- |
-- |
remove ladder from master closet |
jill |
|
-- |
-- |
can toilet flush any stronger/faster??? |
Tom |
|
-- |
-- |
repaint entire garage |
painters |
|
-- |
-- |
caulk cracks along the patio at the bottom of the house |
Tom |
|
-- |
-- |
put mailbox numbers on the mailbox |
Jill |
|
-- |
-- |
vent on back of home needs tightened to home |
Davenport |
|
-- |
-- |
gap by front window on the outside |
Davenport, where J channel meets trim at living room window |
|
-- |
-- |
CODED LOCKBOX 1919 |
|
|
-- |
-- |
Touch up paint |
Painter |
|
-- |
-- |
Water coming into unfinished basement bonus room |
Tom, Jeremy |
|
-- |
-- |
Screens needed 8/18 |
Jill |
|
-- |
-- |
1. Repair leaking toilet that has already been repaired three times in the half bathroom |
|
|
-- |
-- |
Repair leaking toilet that has already been repaired three times in the half bathroom |
Wes |
|
-- |
-- |
Repair small area of flooring where subfloor is exposed at the top of the stairs coming up from the basement |
Denny, Eric |
|
-- |
-- |
Seal and paint gaps in trim and drywall at the bottom of the stairs coming up from the basement. |
Painter |
|
-- |
-- |
4. Adjust weather stripping at front door to eliminate light/air coming through at hinge side of door |
|
|
-- |
-- |
5. Evaluate master bedroom floor that has some bounce to it and makes noise |
|
|
-- |
-- |
Adjust weather stripping at front door to eliminate light/air coming through at hinge side of door |
Domingo, framer |
|
-- |
-- |
Evaluate master bedroom floor that has some bounce to it and makes noise |
Denny, Eric |
|
-- |
-- |
Call Kris Bowman at 540-578-5922 if Joseph is not available |
|
|
-- |
-- |
Ratified Contract? (0) 02.14.2022 |
|
|
-- |
-- |
$2500 Deposit Received (0) 02.15.2022 |
|
|
-- |
-- |
Association Packet Requested (0) 02.14.2022 |
|
|
-- |
-- |
Association Packet Received (0) 02.18.2022 |
|
|
-- |
-- |
Selections Meeting (0) 03.05.2022 |
|
|
-- |
-- |
Selections Sheet Signed (0) 03.11.2022 |
3/5/2022: sent to Julie for signatures |
|
-- |
-- |
Amendment for Upgrades (B,S,L,T,BCP) (0) 03.23.2022 |
3/22/2022: sent to Jerry for signatures |
|
-- |
-- |
Deposit For Upgrades Received (0) 03.22.2022 |
|
|
-- |
-- |
Building Permit (30) 03.06.2022 |
|
|
-- |
-- |
Order Roof & Floor Trusses (1) 06.20.2022 |
|
|
-- |
-- |
Order Windows & Doors (0) 05.03.2022 |
|
|
-- |
-- |
Stake Out Home (1) 03.24.2022 |
|
|
-- |
-- |
Excavate (2) 03.24.2022 |
|
|
-- |
-- |
Inspection (Footers) (1) 03.24.2022 |
|
|
-- |
-- |
Inspection (Concrete Wall) (1) 09.07.2022 |
|
|
-- |
-- |
Pour Footers (1) 03.24.2022 |
|
|
-- |
-- |
Set Forms (2) 04.04.2022 |
|
|
-- |
-- |
Pour Foundation Walls (1) 04.04.2022 |
|
|
-- |
-- |
Plumb Slab (2) 04.28.2022 |
|
|
-- |
-- |
Inspection (Plumbing Under Slab) (1) 04.28.2022 |
|
|
-- |
-- |
Inspection (Conduit Under Slab) (1) 09.07.2022 |
|
|
-- |
-- |
Prepare Slab (1) 05.12.2022 |
|
|
-- |
-- |
Inspection (Slab) (1) 06.02.2022 |
|
|
-- |
-- |
Inspection (Drain Tile) (0) 09.07.2022 |
|
|
-- |
-- |
Pour Slab (1) * 06.02.2022 |
|
|
-- |
-- |
Settlement Agent Confirmed (0) 08.19.2022 |
|
|
-- |
-- |
Framing I (9) 06.09.2022 |
|
|
-- |
-- |
Order Steps (0) 06.20.2022 |
|
|
-- |
-- |
Order Tubs / Showers (0) 06.20.2022 |
American Standard gray subway tile |
|
-- |
-- |
Framing II (8) 06.27.2022 |
|
|
-- |
-- |
Framing III (8) * 07.05.2022 |
|
|
-- |
-- |
Verify Window & Roof Structure (0) 12.11.2023 |
|
|
-- |
-- |
Install Stairs (0) 07.21.2022 |
|
|
-- |
-- |
Windows & Doors (0) 07.21.2022 |
|
|
-- |
-- |
House Number and Status in Window (0) 08.22.2022 |
|
|
-- |
-- |
Roofing (0) 08.01.2022 |
|
|
-- |
-- |
Order Cabinets (0) 07.19.2022 |
|
|
-- |
-- |
Order Appliances (0) 07.26.2022 |
Standard SS |
|
-- |
-- |
Deck (0) 09.17.2022 |
STANDARD |
|
-- |
-- |
Gutters (0) 10.15.2022 |
|
|
-- |
-- |
Driveway (0) 10.15.2022 |
Expanded Driveway, 10x18 Expanded Patio |
|
-- |
-- |
Patio (0) 10.11.2022 |
|
|
-- |
-- |
Privacy Divider / Fence (0) 10.19.2022 |
|
|
-- |
-- |
Sod / Seed / Landscaping (0) 11.27.2022 |
|
|
-- |
-- |
HVAC Rough In (4) 07.23.2022 |
in process 7/20 |
|
-- |
-- |
Inspection (Rough In HVAC) (1) 08.28.2022 |
|
|
-- |
-- |
Rough In Microwave Vent (0) 12.11.2023 |
|
|
-- |
-- |
Plumbing Rough In (4) 08.20.2022 |
In process 8/17 |
|
-- |
-- |
Inspection (Rough In Plumbing) (1) 09.07.2022 |
|
|
-- |
-- |
Electric Rough In (4) 08.20.2022 |
|
|
-- |
-- |
Inspection (Rough In Electric) (1) 09.07.2022 |
|
|
-- |
-- |
Inspection (Deck Piers) (0) 09.07.2022 |
|
|
-- |
-- |
Inspection (Framing) (1) 09.07.2022 |
|
|
-- |
-- |
Exterior Vinyl (0) * 10.02.2022 |
|
|
-- |
-- |
Exterior Stone (0) 04.14.2022 |
|
|
-- |
-- |
Insulation (2) 08.28.2022 |
|
|
-- |
-- |
Inspection (Insulation) (1) 09.01.2022 |
|
|
-- |
-- |
Inspection (Electric Service) (0) 10.27.2022 |
|
|
-- |
-- |
Set Electric Meter (0) 04.11.2023 |
|
|
-- |
-- |
Inspection (Main Sewer Line) (0) 05.12.2022 |
|
|
-- |
-- |
Inspection (Main Water Line) (0) 09.08.2022 |
|
|
-- |
-- |
Order Interior Doors & Trim (0) 08.29.2022 |
|
|
-- |
-- |
Drywall (Hang) (4) * 09.05.2022 |
NONE |
|
-- |
-- |
Loan Approval (0) 10.31.2022 |
|
|
-- |
-- |
Deed Preparation (0) 10.31.2022 |
|
|
-- |
-- |
Drywall (Tape, Block, Skim, Sand) (6) * 10.02.2022 |
Final sanding 9/28 |
|
-- |
-- |
Paint 1 (1) 10.02.2022 |
|
|
-- |
-- |
Garage Door (0) 10.26.2022 |
|
|
-- |
-- |
House Numbers (0) 10.26.2022 |
|
|
-- |
-- |
Mailbox (0) 11.17.2022 |
|
|
-- |
-- |
Cabinet Installation (2) * 10.07.2022 |
10/4 Install by MidSouth |
|
-- |
-- |
Granite Installation (1) * 10.07.2022 |
Hopefully 10/6 |
|
-- |
-- |
Interior Trim - Install (3) 10.29.2022 |
In process 10/26 |
|
-- |
-- |
Order Plumbing / Lighting Fixtures (0) 08.21.2023 |
|
|
-- |
-- |
Interior Trim - Paint (1) 11.09.2022 |
|
|
-- |
-- |
Luxury Vinyl Plank (3) * 11.05.2022 |
In process 11/2 |
|
-- |
-- |
Luxury Vinyl Tile (0) 11.05.2022 |
In process 11/2 |
|
-- |
-- |
Paint 2 (3) 11.12.2022 |
|
|
-- |
-- |
Cover Floors (1) 11.09.2022 |
|
|
-- |
-- |
Deliver Plumbing / Lighting Fixtures (0) 10.27.2022 |
|
|
-- |
-- |
Shoe Moulding (0) 11.16.2022 |
|
|
-- |
-- |
Shelving, Door Knobs, Fire Extinguisher (0) 12.10.2022 |
Black accessories, shower door black trim. In process 12/3 |
|
-- |
-- |
Install Coded Lockbox (add extra keys) (0) 12.10.2022 |
|
|
-- |
-- |
Pay Water / Sewer Taps (0) 10.18.2022 |
|
|
-- |
-- |
Set Water Meter (0) 11.03.2022 |
|
|
-- |
-- |
Electric Trim Out (3) 11.30.2022 |
Black Standard. In process 11/27 |
|
-- |
-- |
Ceiling Fans (0) 11.27.2022 |
Living Room BR 2/3 |
|
-- |
-- |
HVAC Trim Out (1) 11.27.2022 |
|
|
-- |
-- |
Blower Door Test (1) 12.06.2023 |
|
|
-- |
-- |
Plumbing Trim Out (2) 11.12.2022 |
Black Standard. In process. Main level completed 11/9 |
|
-- |
-- |
Install Appliances (0) * 12.03.2022 |
In dining room. Need to be set in place-kk |
|
-- |
-- |
Paint 3 (2) * 11.16.2022 |
|
|
-- |
-- |
Carpet (2) 11.05.2022 |
|
|
-- |
-- |
Appraiser Confirms Construction Completion (0) 11.28.2022 |
|
|
-- |
-- |
Inspection (Final HVAC) (1) 12.08.2022 |
|
|
-- |
-- |
Inspection (Final Plumbing) (1) 12.08.2022 |
|
|
-- |
-- |
Inspection (Final Electric) (1) 12.08.2022 |
|
|
-- |
-- |
Inspection (Final Building) (2) * 12.08.2022 |
Tues Dec. 6 |
|
-- |
-- |
Pre Walk Through (0) 12.08.2022 |
|
|
-- |
-- |
Stain Hardwood Stairs (1) 11.27.2022 |
|
|
-- |
-- |
Cleaning (1) 12.07.2022 |
Dec. 6 |
|
-- |
-- |
Certificate of Occupancy (1) * 12.08.2022 |
|
|
-- |
-- |
C.O. to Lender (0) 12.08.2022 |
|
|
-- |
-- |
Schedule Closing (0) 12.14.2022 |
|
|
-- |
-- |
Buyer Walk Through (1) 12.10.2022 |
Thursday, 12/8 at 2PM |
|
-- |
-- |
Payment for Upgrades (0) 12.08.2022 |
|
|
-- |
-- |
Keys to Settlement Agent (0) 12.08.2022 |
|
|
-- |
-- |
Review Settlement Statement (0) 12.14.2022 |
|
|
-- |
-- |
Jerry Signs Closing Documents (0) 11.18.2022 |
|
|
-- |
-- |
Request Trash Tote From POA Manager (0) 12.08.2022 |
|
|
-- |
-- |
Closing (1) 12.15.2022 |
Brittany @ West View Title |
|
-- |
-- |
Remove Coded Lockbox (0) 01.02.2023 |
|
|