CONGERS-2 - 23  ::  1416 Palomino Trail
[ BUILD: 20220411 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
TO DO
---
UPGRADES
    Upgraded Carpet Pad in Bonus Room  
CRITICAL PATH
    Verify Window & Roof Structure (0)      
    Rough In Microwave Vent (0)      
    Order Plumbing / Lighting Fixtures (0)      
Tue    Feb 3      Blower Door Test (1)      
TO DO - COMPLETED OR DELETED
Step coverings coming off. Trip hazard
Cultured marble tops needed In living room 11/16
Missing closet door. Up bedroom Needs door knob 1/21 - Jill
Extra cabinet in kitchen-move before flooring Maybe it is gone now - Tom
Cover carpet
Master toilet looks crooked Plumber
Trim garage Edgar or Henry
Cable/electric covers needed
Patch holes base bath Painter
C can’t find keys? 1/7
Put attic cover in place
Finish master bedroom shelving
Drywall repair- hole on stair wall
Pop at top of stairs in nook
Install thermostat
Install cable covers
Install vanity light and upstairs hallway
Install fan in master bathroom
Lightbulbs needed basement Few missing 1/14
Black shower drain needed Plumber
CODED LOCKBOX 2323
Fill in a Little Rock to front left side at ground?
Completely uncalled-for amount of mud in bonus room
Screens
Closet door in bedroom
Dented freezer door
Clean patio and out front Bridges
Paint touch up through our
Paint touch up throughout
Spice rack doesn’t close or open smoothly
Transition strip going into bonus room isn’t secure
Transition strip at the top of the first set of stairs isn’t secure
Remove extra screens under stairs in basement closet
Front door latch needs adjusted so it latches better
Crack in the frame of the LR window
Hole in the back of the coffee bar (on inside of cabinet)
Cabinet to the right of the fridge don’t open all the way and the drawer hits the door when you open it
Key fiasco- two different keys for deadbolt/main door
Key Issue- two different keys/locks Joe
Light bulb powder bath
Scratched cultured marble tops delivered 2/9, installed 2/10
caulk inside master shower and outside trim
fix squeak in master floor
Paint touch up
black drain master
fadd trim under pantry Painter
replace all cultured marble.
sink stain in farm sink?
driveway discoloration Tom
Crack in tub fixing 2/2 and 2/3
Drywall repair above master shower Painter
Dirty base bath fan Jill
Paint smudges MB near light switch Painter
Crack in caulk of countertop Fenco will be scheduling - kitchen
Mark 540-834-7659
Leaking dishwasher Appliance is leaking (CJ) gasket issue (on order)
Cabinet Blemishes Jill to view upon return
Flooring Scratches Jill to view upon return
Grading to fix drainage issue Tom
French drain Tom, Bub
UPGRADES - COMPLETED
    Finished Bonus Room  
    Finished Bonus Bath  
    Level 1 Quartz  
    Farmhouse Sink  
    Three Drawer Stack  
    Pantry Roll out trays  
    Double Waste Basket in Island  
    white subway tile shower walls  
    Shower Door with black trim  
    Expanded Driveway  
    Egress Window in Bonus Room  
    Farmhouse Plumbing Package  
    Garage Keypad  
    French Model Refrigerator  
    Amendment to increase price by $28,240  
CRITICAL PATH - COMPLETED
-- -- Ratified Contract? (0)  02.24.2022    
-- -- $2500 Deposit Received (0)  03.02.2022    
-- -- Association Packet Requested (0)  02.24.2022    
-- -- Association Packet Received (0)  03.04.2022    
-- -- Selections Meeting (0)  03.23.2022    
-- -- Selections Sheet Signed (0)  04.02.2022     3/23/2022: sent to Luke for signatures
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  04.14.2022     4/12/2022: sent to Jerry for signatures
-- -- Deposit For Upgrades Received (0)  04.13.2022    
-- -- Building Permit (30) *   03.06.2022    
-- -- Order Roof & Floor Trusses (1)  08.04.2022    
-- -- Order Windows & Doors (0)  05.03.2022    
-- -- Stake Out Home (1)  03.24.2022    
-- -- Excavate (2)  03.24.2022    
-- -- Inspection (Footers) (1)  03.24.2022    
-- -- Inspection (Concrete Wall) (1)  09.07.2022    
-- -- Pour Footers (1) *   03.24.2022    
-- -- Set Forms (2)  04.07.2022    
-- -- Pour Foundation Walls (1)  04.07.2022    
-- -- Plumb Slab (2)  06.27.2022    
-- -- Inspection (Plumbing Under Slab) (1)  06.27.2022    
-- -- Inspection (Conduit Under Slab) (1)  09.07.2022    
-- -- Prepare Slab (1)  07.25.2022    
-- -- Inspection (Slab) (1)  08.04.2022    
-- -- Inspection (Drain Tile) (0)  09.07.2022    
-- -- Pour Slab (1) *   08.04.2022    
-- -- Settlement Agent Confirmed (0)  02.24.2022    
-- -- Framing I (9)  08.22.2022    
-- -- Order Steps (0)  08.29.2022    
-- -- Order Tubs / Showers (0)  06.20.2022    
-- -- Framing II (8)  09.01.2022    
-- -- Framing III (8) *   09.06.2022    
-- -- Install Stairs (0) *   10.03.2022    
-- -- Windows & Doors (0) *   10.03.2022    
-- -- House Number and Status in Window (0)  10.24.2022    
-- -- Roofing (0) *   10.03.2022    
-- -- Order Cabinets (0)  09.06.2022    
-- -- Order Appliances (0)  08.30.2022     French Upgrade
-- -- Deck (0)  11.02.2022     Standard
-- -- Gutters (0)  12.28.2022    
-- -- Driveway (0) *   11.12.2022     Expanded Driveway
-- -- Patio (0)  10.16.2022    
-- -- Privacy Divider / Fence (0) *   12.17.2022    
-- -- Sod / Seed / Landscaping (0)  12.31.2022    
-- -- HVAC Rough In (4)  09.24.2022    
-- -- Plumbing Rough In (4)  09.24.2022     In process 9/21
-- -- Electric Rough In (4)  10.05.2022     In process10/2
-- -- Inspection (Rough In HVAC) (1)  09.22.2022    
-- -- Inspection (Rough In Plumbing) (1)  10.05.2022    
-- -- Inspection (Rough In Electric) (1)  10.05.2022    
-- -- Inspection (Framing) (1) *   10.05.2022    
-- -- Inspection (Deck Piers) (0)  10.05.2022    
-- -- Exterior Vinyl (0) *   12.10.2022     In process 11/27
-- -- Exterior Stone (0)  12.31.2022     In process 12/28
-- -- Insulation (2) *   10.16.2022    
-- -- Inspection (Insulation) (1)  10.19.2022    
-- -- Inspection (Electric Service) (0)  01.10.2023    
-- -- Set Electric Meter (0) *   04.11.2023    
-- -- Inspection (Main Sewer Line) (0)  12.08.2022    
-- -- Inspection (Main Water Line) (0)  12.08.2022    
-- -- Order Interior Doors & Trim (0)  12.08.2022    
-- -- Drywall (Hang) (4) *   10.16.2022     Finish Bonus Room, Bath
-- -- Loan Approval (0)  03.15.2022    
-- -- Deed Preparation (0)  11.08.2022    
-- -- Drywall (Tape, Block, Skim, Sand) (6) *   11.02.2022     In process 10/29
-- -- Paint 1 (1)  11.05.2022    
-- -- Garage Door (0)  12.31.2022     week of 12/5
-- -- House Numbers (0)  12.27.2022    
-- -- Mailbox (0)  01.07.2023     Post up, needs mailbox
-- -- Cabinet Installation (2) *   11.09.2022     In process 11/5
-- -- Granite Installation (1) *   11.27.2022     Monday 11/23
-- -- Interior Trim - Install (3) *   12.07.2022     In process 12/3
-- -- Interior Trim - Paint (1)  12.10.2022    
-- -- Luxury Vinyl Plank (3) *   12.27.2022     Almost complete 12/17
-- -- Luxury Vinyl Tile (0)  12.27.2022     In process 12/17
-- -- Paint 2 (3)  12.10.2022    
-- -- Cover Floors (0)  12.31.2022    
-- -- Deliver Plumbing / Lighting Fixtures (0)  12.08.2022     Farmhouse Plumbing Black
-- -- Shoe Moulding (0)  12.28.2022    
-- -- Shelving, Door Knobs, Fire Extinguisher (1) *   01.07.2023     shelving needs completed in master closet 1/4
-- -- Install Coded Lockbox (add extra keys) (0)  01.12.2023    
-- -- Pay Water / Sewer Taps (0)  12.12.2022    
-- -- Set Water Meter (1) *   01.05.2023    
-- -- Electric Trim Out (3) *   01.16.2023     Black Lighting. In process 1/11
-- -- Ceiling Fans (0)  01.04.2023    
-- -- HVAC Trim Out (1) *   01.11.2023    
-- -- Plumbing Trim Out (2) *   12.28.2022     Black farmhouse upgrade
-- -- Install Appliances (0) *   01.04.2023     Delivery 10/17, Install 10/27 ( confirm with CJ). On site 12/31
-- -- Paint 3 (2) *   12.14.2022    
-- -- Carpet (2)  12.28.2022    
-- -- Appraiser Confirms Construction Completion (0)  01.16.2023     Robbie Miller, Sun, Jan 15
-- -- Inspection (Final HVAC) (0)  01.16.2023    
-- -- Inspection (Final Plumbing) (0)  01.16.2023    
-- -- Inspection (Final Electric) (0)  01.16.2023    
-- -- Inspection (Final Building) (4) *   01.18.2023     Reinspect, Jan 18
-- -- Pre Walk Through (0)  01.16.2023     Sat/Sun, Jan 14-15
-- -- Stain Hardwood Stairs (1) *   01.07.2023    
-- -- Cleaning (1)  01.18.2023    
-- -- Certificate of Occupancy (1) *   01.20.2023     Final was approved 1/18
-- -- C.O. to Lender (0)  01.20.2023    
-- -- Schedule Closing (0)  01.25.2023    
-- -- Buyer Walk Through (1) *   01.19.2023     Mon, Jan 16
-- -- Payment for Upgrades (0)  01.04.2023    
-- -- Keys to Settlement Agent (0)  01.23.2023    
-- -- Review Settlement Statement (0)  01.26.2023    
-- -- Jerry Signs Closing Documents (0)  12.20.2022    
-- -- Request Trash Tote From POA Manager (0)  01.10.2023    
-- -- Closing (1)  01.26.2023     Brittany @ West View Title
-- -- Remove Coded Lockbox (0)  01.26.2023