CONGERS-2 - 112  ::  1413 Palomino Trail
[ BUILD: 20220414 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
--   --   Leave dining chandelier with extra chain so buyer can swag if need be. Tom will leave extra
--   --   Soggy insulation
--   --  
--   --   Drywall on deck mildews the deck boards
--   --   No shelving in master linen nook Joe
--   --   O washer pan by buyer request
--   --   No washer pan by buyer request Washer pan is in…. 1/11
--   --   Closet door near steps needed 12/28 Needs painted 1/1
--   --   Hoping to close by 1/31 at the latest
--   --   fallen tree Tom
--   --   No towel hanger behind toilet Joe. It’s installed 1/11
--   --   Must close by 1/31 at the latest! 1/27 at 10:00 AM
--   --   Paint closet door under steps Painter
--   --   Oven may not fit?
--   --   Needs mirrors All baths
--   --   Lightbulbs needed basement
--   --   Hole needs patching powder bath Painter
--   --   Missing light in living room Electrician
--   --   Pressure wash patio Bridges
--   --   Missing snap lights upstairs hallway Electrician
--   --   Trim needs patching outside of upstairs bedroom closest to banister Painter
--   --   Handle into garage isn’t functional Joe
--   --   Powder bath receptacle missing Electrician
--   --   CODED LOCKBOX 0112
--   --   Door plugs Jill
--   --   Screens Jill
--   --   Paint front door Painter
--   --   Few damaged doors 9blue tape) Painter
--   --   Few cabinet blemishes (blue tape) Jill - touch up pen
--   --   Paint on kitchen ceiling Painter
--   --   Towel Bar to be secured in Bonus Bath Joe
--   --   Paint Garage Painter
--   --   HVAC closet- drywall hole Drywall
--   --   Missing drywall Up Hallway Drywall. In process 1/28
--   --   Finish Final Clean Courtney
--   --   Paint Touch Up Throughout Painter
--   --   Paint bubble front door Painter
--   --   Bonus window screen doesn’t fit Jill
--   --   Clean all floors before Tuesday move-in Courtney
--   --   Tenant: Devin, 540-233-7777
--   --   Leak above kitchen light
--   --   Basement: Pop nail above the double door Several pop nails on the ceiling. Painter
--   --   Basement:Dark line from around 4 feet of the ceiling light plus seam around 1.5 feet from this light. These are on the side further from the door. Painter
--   --   n the hallway coming from the basement steps near the light switch is an odd spot in the drywall. Painter
--   --   iving room: As you get to the top of the basement steps near the doorbell on the ceiling it needs to be sanded and painted. Someone painted a good size area but did not sand first. Painter
--   --   Living Room:By the smoke detector at steps there is a seam showing. Painter
--   --   Living Room: By the recessed light by the window there is a half dollar bad spot. Painter
--   --   Living Room: At the steps there is a bad spot by the ceiling but on the wall. Painter
--   --   Living Room:Recessed wall near window on the right looks black. Is this construction dirt or is it burning plastic? Painter
--   --   Living Rom:Around 2 feet from the smoke detector there is a bad spot in drywall Painter
--   --   Half Bath: Faucet is dripping and there is a pop nail behind the faucet. Painter, Plumber
--   --   Kitchen lights – center recessed and pendant light on ceiling needs to be sanded and painted. Painter
--   --   Trim leading in to half bath on outside has a nail coming through on right side. Painter
--   --   Steps to top floor: Pop nail at base of steps on the ceiling Painter
--   --   Bedroom 1 (Left): Walk across the floor and it creaks. Denny, Eric, Eagle
--   --   Bedroom 1 left:Pop nail by light Painter
--   --   Bedroom 1 left:Ceiling above window small crack and couple nail and bad spots Painter
--   --   Bedroom 2: Floor is separating and has caused another bad spot in the board where it is sticking up. Denny
--   --   Bedroom 2:Several popped nails in the ceiling Painter
--   --   Bath 1 – Hallway Crack in ceiling above the vanity Painter
--   --   Hall Bath-Spots of running paint above tub on wall and ceiling Painter
--   --   Master Bedroom: Remote on wall fell out off. Can we use a better anchor or something to hold this on? Tenant has remote. Jill/Tom
--   --   3rd floor f
--   --   3rd floor has some squeaks in smaller rooms and master bedrooms Denny
-- -- Ratified Contract? (0)  03.09.2022    
-- -- $2500 Deposit Received (0)  03.11.2022    
-- -- Association Packet Requested (0)  03.09.2022    
-- -- Association Packet Received (0)  03.11.2022    
-- -- Selections Meeting (0)  04.05.2022    
-- -- Selections Sheet Signed (0)  04.09.2022     4/8/2022: sent to Julie for signatures
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  04.21.2022     4/20/2022: sent to Jerry for signatures
-- -- Deposit For Upgrades Received (0)  04.20.2022    
-- -- Building Permit (30)  07.05.2022    
-- -- Order Roof & Floor Trusses (1)  08.04.2022    
-- -- Order Windows & Doors (0)  05.03.2022    
-- -- Stake Out Home (1)  03.24.2022    
-- -- Excavate (2)  04.19.2022    
-- -- Inspection (Footers) (1)  04.19.2022    
-- -- Inspection (Concrete Wall) (1)  09.07.2022    
-- -- Pour Footers (1)  04.19.2022    
-- -- Set Forms (2)  04.19.2022    
-- -- Pour Foundation Walls (1)  04.21.2022    
-- -- Plumb Slab (2)  08.08.2022    
-- -- Inspection (Plumbing Under Slab) (1)  08.08.2022    
-- -- Inspection (Conduit Under Slab) (1)  09.07.2022    
-- -- Prepare Slab (1)  08.22.2022    
-- -- Inspection (Slab) (1)  08.22.2022    
-- -- Inspection (Drain Tile) (0)  09.08.2022    
-- -- Pour Slab (1)  08.22.2022    
-- -- Settlement Agent Confirmed (0)  10.08.2022    
-- -- Framing I (9)  08.22.2022    
-- -- Order Steps (0)  09.01.2022    
-- -- Order Tubs / Showers (0)  06.20.2022    
-- -- Framing II (8)  09.06.2022    
-- -- Framing III (8)  09.29.2022    
-- -- Verify Window & Roof Structure (0)  01.11.2024    
-- -- Install Stairs (0)  10.03.2022    
-- -- Windows & Doors (0)  10.03.2022    
-- -- House Number and Status in Window (0)  10.24.2022    
-- -- Roofing (0)  10.02.2022    
-- -- Order Cabinets (0)  09.09.2022    
-- -- Order Appliances (0)  08.30.2022     Standard
-- -- Deck (0)  10.29.2022     Expanded 12 x 18 Deck
-- -- Gutters (0)  01.21.2023    
-- -- Driveway (0)  12.07.2022     Expanded Driveway
-- -- Patio (0)  10.29.2022     Expanded 10 x 10 Patio Below Deck
-- -- Privacy Divider / Fence (0)  01.07.2023    
-- -- Sod / Seed / Landscaping (0)  01.11.2023    
-- -- HVAC Rough In (4)  10.02.2022    
-- -- Inspection (Rough In HVAC) (1)  10.17.2022    
-- -- Rough In Microwave Vent (0)  01.11.2024    
-- -- Plumbing Rough In (4)  10.16.2022     In process 10/5
-- -- Inspection (Rough In Plumbing) (1)  10.17.2022    
-- -- Electric Rough In (4)  10.19.2022    
-- -- Inspection (Rough In Electric) (1)  10.26.2022    
-- -- Inspection (Deck Piers) (0)  11.10.2022    
-- -- Inspection (Framing) (1)  10.29.2022    
-- -- Exterior Vinyl (0)  01.01.2023    
-- -- Exterior Stone (0)  01.19.2023     Almost completed 11/18
-- -- Insulation (2)  10.26.2022    
-- -- Inspection (Insulation) (1)  11.03.2022    
-- -- Inspection (Electric Service) (0)  01.10.2023    
-- -- Set Electric Meter (0)  04.11.2023    
-- -- Inspection (Main Sewer Line) (0)  12.19.2022    
-- -- Inspection (Main Water Line) (0)  12.19.2022    
-- -- Order Interior Doors & Trim (0)  12.08.2022    
-- -- Drywall (Hang) (4)  11.05.2022     Finish Bonus Room, Bath
-- -- Loan Approval (0)  01.04.2023    
-- -- Deed Preparation (0)  01.04.2023    
-- -- Drywall (Tape, Block, Skim, Sand) (6)  11.27.2022     In process11/19. Needs final sanding
-- -- Paint 1 (1)  11.27.2022    
-- -- Garage Door (0)  01.07.2023    
-- -- House Numbers (0)  01.07.2023    
-- -- Mailbox (0)  01.16.2023    
-- -- Cabinet Installation (2)  11.30.2022     11/28
-- -- Granite Installation (1)  11.30.2022     11/29?
-- -- Interior Trim - Install (3)  12.17.2022     In process 12/14
-- -- Order Plumbing / Lighting Fixtures (0)  11.06.2023    
-- -- Interior Trim - Paint (1)  01.01.2023    
-- -- Luxury Vinyl Plank (3)  01.11.2023    
-- -- Luxury Vinyl Tile (0)  01.11.2023     In process. Base bath needs installed 1/7
-- -- Paint 2 (3)  01.01.2023    
-- -- Cover Floors (1)  01.13.2023    
-- -- Deliver Plumbing / Lighting Fixtures (0)  12.29.2022    
-- -- Shoe Moulding (0)  01.14.2023     In process 1/11
-- -- Shelving, Door Knobs, Fire Extinguisher (0)  01.18.2023     Black accessories, Bonus bath In process 1/11
-- -- Install Coded Lockbox (add extra keys) (0)  01.18.2023    
-- -- Pay Water / Sewer Taps (0)  12.29.2022    
-- -- Set Water Meter (0)  01.16.2023    
-- -- Electric Trim Out (3)  01.18.2023     Black lighting. In process 1/14
-- -- Ceiling Fans (0)  01.18.2023    
-- -- HVAC Trim Out (1)  01.14.2023    
-- -- Blower Door Test (1)  11.06.2023    
-- -- Plumbing Trim Out (2)  01.14.2023     Black standard plumbing. In process 1/11
-- -- Install Appliances (0)  01.14.2023     Delivery 10/24, Install 11/1 ( confirm with CJ)
-- -- Paint 3 (2)  01.01.2023    
-- -- Carpet (2)  10.26.2022    
-- -- Appraiser Confirms Construction Completion (0)  01.26.2023    
-- -- Inspection (Final HVAC) (1)  01.23.2023    
-- -- Inspection (Final Plumbing) (1)  01.23.2023    
-- -- Inspection (Final Electric) (1)  01.23.2023    
-- -- Inspection (Final Building) (2)  01.26.2023     Mon, Jan 23
-- -- Pre Walk Through (0)  01.25.2023    
-- -- Stain Hardwood Stairs (1)  01.23.2023     In process 1/21
-- -- Cleaning (1)  01.26.2023    
-- -- Certificate of Occupancy (1)  01.26.2023    
-- -- C.O. to Lender (0)  01.26.2023    
-- -- Schedule Closing (0)  01.26.2023    
-- -- Buyer Walk Through (1)  01.26.2023    
-- -- Payment for Upgrades (0)  01.26.2023    
-- -- Keys to Settlement Agent (0)  01.23.2023    
-- -- Review Settlement Statement (0)  01.26.2023    
-- -- Jerry Signs Closing Documents (0)  01.26.2023    
-- -- Request Trash Tote From POA Manager (0)  01.24.2023    
-- -- Closing (1)  01.28.2023     Brittany @ West View Title
-- -- Remove Coded Lockbox (0)  02.06.2023