Vent micro!!! |
|
|
-- |
-- |
Patch garage concrete 11/30 |
|
|
-- |
-- |
paint 1 in process 12/14 |
|
|
-- |
-- |
Shower framing issue? Upstairs bath |
In process of repair 1/7-needs painted (maybe just paint 2) |
|
-- |
-- |
FLOORING AND PAINT COLOR TBD BY BUYER |
|
|
-- |
-- |
Should we sweep well? Dust countertops? |
|
|
-- |
-- |
Cover steps |
Jill |
|
-- |
-- |
Missing closet door |
Edgar |
|
-- |
-- |
Flooing- riverside main level |
Ordered by Eric 2/8 |
|
-- |
-- |
Paint- Chantily Baths, Stonington rest of house |
Communicated to Joanna 2/8 |
|
-- |
-- |
Light fixtures up but they haven’t painted. I guess painters will paint around? |
|
|
-- |
-- |
Need master ceiling fan |
Electrician |
|
-- |
-- |
One snap light missing in kitchen |
Electrician |
|
-- |
-- |
Drywall repair near garage door |
In process 3/1 |
|
-- |
-- |
Few outlet covers needed foyer |
Electrician |
|
-- |
-- |
Expanded Driveway |
mother of buyer is sending payment (wait to pour) |
|
-- |
-- |
Would like to upgrade to a digital deadbolt if possible |
|
|
-- |
-- |
Cover carpets |
|
|
-- |
-- |
Electric cover needed near garage 3/5 |
electricians |
|
-- |
-- |
White plugs on side of island-better color option? |
Need gray |
|
-- |
-- |
Install patio door screens |
Tom guys |
|
-- |
-- |
Push oven against wall |
Needs a cord-who does this? |
|
-- |
-- |
Needs mirrors and towel bar in master bath |
Joe |
|
-- |
-- |
Outlet needed near garage |
Electrician - cover |
|
-- |
-- |
CODED LOCKBOX 0108 |
|
|
-- |
-- |
Install board under patio door |
Tom |
|
-- |
-- |
Powder bath mirror needs installed |
All mirrors need installed |
|
-- |
-- |
Clean out garage |
|
|
-- |
-- |
Remove the board between decks |
Tom |
|
-- |
-- |
Sand and repaint spot near master bathroom vanity |
Painter |
|
-- |
-- |
Need black master shower drain |
Plumber |
|
-- |
-- |
Attic cover |
Jill |
|
-- |
-- |
Unsure if microwave vent is working |
Tom will talk to Jeremy who was going to check it |
|
-- |
-- |
Repair, landscaping near driveway and on side of house |
Pettit |
|
-- |
-- |
String hanging from front doorbell |
Jill |
|
-- |
-- |
Clean out garage before walk through today. |
Jill |
|
-- |
-- |
Nail holes to be filled in nosing right before first landing on first set of steps |
And second nosing coming into hallway (Painter) |
|
-- |
-- |
Upstairs closet doors to be adjusted |
Jill |
|
-- |
-- |
Chirping battery in master bedroom |
Jill |
|
-- |
-- |
Clean off back deck |
Court |
|
-- |
-- |
Squeaky floor in between bedrooms two and three |
Denny is going to look at it today (3/27) |
|
-- |
-- |
Final cleaning to include kitchen cabinets |
Jill/Lynn |
|
-- |
-- |
Install window screens |
Jill |
|
-- |
-- |
Scratch on toilet seat upstairs bathroom |
Jill |
|
-- |
-- |
Missing globe on light fixture above powder bath mirror |
Jill |
|
-- |
-- |
Missing globe on light fixture above powder bath mirror |
|
|
-- |
-- |
Weatherstripping, torn on the bottom of the patio door |
Tom |
|
-- |
-- |
Put electrical covers back on and hall bath |
|
|
-- |
-- |
Mud on carpet |
Jill |
|
-- |
-- |
Smooth concrete in corner of garage |
Tom |
|
-- |
-- |
Broken garage door-bent |
Davenport - waiting on parts as of 4/3 |
|
-- |
-- |
Smooth concrete in corner of garage |
|
|
-- |
-- |
The floor creaks in the guest bedroom |
Denny, Eric |
|
-- |
-- |
Guest shower head is loose where it meets the wall |
Mazur |
|
-- |
-- |
Ratified Contract? (0) 01.31.2023 |
For Sale Again on 11/30/2022; |
|
-- |
-- |
$2500 Deposit Received (0) 02.03.2023 |
|
|
-- |
-- |
Association Packet Requested (0) 01.31.2023 |
|
|
-- |
-- |
Association Packet Received (0) 01.31.2023 |
|
|
-- |
-- |
Selections Meeting (0) 02.09.2023 |
|
|
-- |
-- |
Selections Sheet Signed (0) 02.12.2023 |
Sent to Jayme on 2/9/2023 |
|
-- |
-- |
Amendment for Upgrades (B,S,L,T,BCP) (0) 02.22.2023 |
2/21: sent to Jerry for signatures |
|
-- |
-- |
Deposit For Upgrades Received (0) 02.12.2023 |
|
|
-- |
-- |
Building Permit (30) 07.20.2022 |
|
|
-- |
-- |
Order Roof & Floor Trusses (1) 08.29.2022 |
|
|
-- |
-- |
Order Windows & Doors (0) 09.08.2022 |
|
|
-- |
-- |
Stake Out Home (1) 07.28.2022 |
|
|
-- |
-- |
Excavate (2) 09.01.2022 |
|
|
-- |
-- |
Inspection (Footers) (1) 09.06.2022 |
|
|
-- |
-- |
Inspection (Concrete Wall) (1) 09.07.2022 |
|
|
-- |
-- |
Pour Footers (1) 09.06.2022 |
|
|
-- |
-- |
Set Forms (2) 09.06.2022 |
|
|
-- |
-- |
Pour Foundation Walls (1) 09.06.2022 |
|
|
-- |
-- |
Plumb Slab (2) 09.06.2022 |
|
|
-- |
-- |
Inspection (Plumbing Under Slab) (1) 09.06.2022 |
|
|
-- |
-- |
Inspection (Conduit Under Slab) (1) 09.07.2022 |
|
|
-- |
-- |
Prepare Slab (1) 09.06.2022 |
|
|
-- |
-- |
Inspection (Slab) (1) 09.06.2022 |
|
|
-- |
-- |
Inspection (Drain Tile) (0) 09.08.2022 |
|
|
-- |
-- |
Pour Slab (1) * 09.06.2022 |
|
|
-- |
-- |
Settlement Agent Confirmed (0) 09.16.2022 |
|
|
-- |
-- |
Framing I (9) 09.29.2022 |
|
|
-- |
-- |
Order Steps (0) 10.10.2022 |
|
|
-- |
-- |
Order Tubs / Showers (0) 10.10.2022 |
|
|
-- |
-- |
Framing II (8) 10.09.2022 |
|
|
-- |
-- |
Framing III (8) * 10.20.2022 |
|
|
-- |
-- |
Verify Window & Roof Structure (0) 03.07.2024 |
|
|
-- |
-- |
Install Stairs (0) 10.29.2022 |
|
|
-- |
-- |
Windows & Doors (0) 10.29.2022 |
|
|
-- |
-- |
House Number and Status in Window (0) 12.10.2022 |
|
|
-- |
-- |
Roofing (0) 10.29.2022 |
|
|
-- |
-- |
Order Cabinets (0) 10.07.2022 |
|
|
-- |
-- |
Order Appliances (0) 08.30.2022 |
French Model Upgrade |
|
-- |
-- |
Deck (0) 10.29.2022 |
Expanded 12 x 12 Deck |
|
-- |
-- |
Gutters (0) 02.08.2023 |
|
|
-- |
-- |
Driveway (0) 02.08.2023 |
|
|
-- |
-- |
Patio (0) 02.08.2023 |
Standard |
|
-- |
-- |
Privacy Divider / Fence (0) 02.08.2023 |
|
|
-- |
-- |
Sod / Seed / Landscaping (0) 03.01.2023 |
|
|
-- |
-- |
HVAC Rough In (4) 11.02.2022 |
In process 10/29 |
|
-- |
-- |
Inspection (Rough In HVAC) (1) 11.07.2022 |
|
|
-- |
-- |
Rough In Microwave Vent (0) 03.07.2024 |
|
|
-- |
-- |
Plumbing Rough In (4) 11.09.2022 |
In process 11/5 |
|
-- |
-- |
Inspection (Rough In Plumbing) (1) 11.10.2022 |
|
|
-- |
-- |
Electric Rough In (4) 11.16.2022 |
In process11/12 |
|
-- |
-- |
Inspection (Rough In Electric) (1) 11.16.2022 |
|
|
-- |
-- |
Inspection (Deck Piers) (0) 02.13.2023 |
|
|
-- |
-- |
Inspection (Framing) (1) 11.21.2022 |
|
|
-- |
-- |
Exterior Vinyl (0) * 02.08.2023 |
almost completed 2/1 |
|
-- |
-- |
Exterior Stone (0) 02.15.2023 |
in process 2/11 |
|
-- |
-- |
Insulation (2) 11.16.2022 |
|
|
-- |
-- |
Inspection (Insulation) (1) 11.21.2022 |
|
|
-- |
-- |
Inspection (Electric Service) (0) 03.08.2023 |
|
|
-- |
-- |
Set Electric Meter (0) 04.06.2023 |
|
|
-- |
-- |
Inspection (Main Sewer Line) (0) 01.23.2023 |
|
|
-- |
-- |
Inspection (Main Water Line) (0) 01.23.2023 |
|
|
-- |
-- |
Order Interior Doors & Trim (0) 12.08.2022 |
|
|
-- |
-- |
Drywall (Hang) (4) * 11.27.2022 |
NONE |
|
-- |
-- |
Loan Approval (0) 03.06.2023 |
|
|
-- |
-- |
Deed Preparation (0) 01.31.2023 |
|
|
-- |
-- |
Drywall (Tape, Block, Skim, Sand) (6) * 12.14.2022 |
In process 12/10 |
|
-- |
-- |
Paint 1 (1) 12.14.2022 |
|
|
-- |
-- |
Garage Door (0) 01.26.2023 |
|
|
-- |
-- |
House Numbers (0) 02.23.2023 |
|
|
-- |
-- |
Mailbox (0) 02.09.2023 |
|
|
-- |
-- |
Cabinet Installation (2) * 12.17.2022 |
Dec 15 |
|
-- |
-- |
Granite Installation (1) * 12.27.2022 |
|
|
-- |
-- |
Interior Trim - Install (3) 01.14.2023 |
Almost completed 1/11 |
|
-- |
-- |
Order Plumbing / Lighting Fixtures (0) 03.07.2024 |
|
|
-- |
-- |
Interior Trim - Paint (1) 01.14.2023 |
|
|
-- |
-- |
Luxury Vinyl Plank (3) * 02.25.2023 |
In process 2/22 |
|
-- |
-- |
Luxury Vinyl Tile (0) 02.25.2023 |
|
|
-- |
-- |
Paint 2 (3) 02.15.2023 |
|
|
-- |
-- |
Cover Floors (1) 03.01.2023 |
|
|
-- |
-- |
Deliver Plumbing / Lighting Fixtures (0) 01.16.2023 |
ORDERED- DO NOT INSTALL YET |
|
-- |
-- |
Shoe Moulding (0) 03.01.2023 |
In process 2/25 |
|
-- |
-- |
Shelving, Door Knobs, Fire Extinguisher (0) 03.08.2023 |
Black accessories |
|
-- |
-- |
Install Coded Lockbox (add extra keys) (0) 03.10.2023 |
|
|
-- |
-- |
Pay Water / Sewer Taps (0) 01.10.2023 |
|
|
-- |
-- |
Set Water Meter (0) 01.23.2023 |
|
|
-- |
-- |
Electric Trim Out (3) 02.11.2023 |
Black Standard. Started 2/8 |
|
-- |
-- |
Ceiling Fans (0) 02.25.2023 |
|
|
-- |
-- |
HVAC Trim Out (1) 03.01.2023 |
|
|
-- |
-- |
Blower Door Test (1) 03.07.2024 |
|
|
-- |
-- |
Plumbing Trim Out (2) 03.05.2023 |
Black Standard - done? |
|
-- |
-- |
Install Appliances (0) * 03.05.2023 |
FRENCH Upgrade |
|
-- |
-- |
Paint 3 (2) * 02.15.2023 |
|
|
-- |
-- |
Carpet (2) 03.01.2023 |
|
|
-- |
-- |
Appraiser Confirms Construction Completion (0) 03.23.2023 |
Sandy Davis - tell her when |
|
-- |
-- |
Inspection (Final HVAC) (1) 03.21.2023 |
|
|
-- |
-- |
Inspection (Final Plumbing) (1) 03.21.2023 |
|
|
-- |
-- |
Inspection (Final Electric) (1) 03.21.2023 |
|
|
-- |
-- |
Inspection (Final Building) (2) * 03.21.2023 |
|
|
-- |
-- |
Pre Walk Through (0) 03.18.2023 |
|
|
-- |
-- |
Stain Hardwood Stairs (1) 03.05.2023 |
|
|
-- |
-- |
Cleaning (1) 03.21.2023 |
|
|
-- |
-- |
Certificate of Occupancy (1) * 03.21.2023 |
|
|
-- |
-- |
C.O. to Lender (0) 03.21.2023 |
|
|
-- |
-- |
Schedule Closing (0) 03.23.2023 |
|
|
-- |
-- |
Buyer Walk Through (1) 03.21.2023 |
|
|
-- |
-- |
Payment for Upgrades (0) 03.05.2023 |
|
|
-- |
-- |
Keys to Settlement Agent (0) 03.21.2023 |
|
|
-- |
-- |
Review Settlement Statement (0) 03.23.2023 |
|
|
-- |
-- |
Jerry Signs Closing Documents (0) 03.10.2023 |
|
|
-- |
-- |
Request Trash Tote From POA Manager (0) 03.18.2023 |
|
|
-- |
-- |
Closing (1) 03.24.2023 |
Brittany @ West View Title |
|
-- |
-- |
Remove Coded Lockbox (0) 03.27.2023 |
|
|