| TO DO | ||||
| --- | ||||
| UPGRADES | ||||
| --- | ||||
| CRITICAL PATH | ||||
| --- | ||||
| TO DO - COMPLETED OR DELETED | ||||
| UPGRADES - COMPLETED | ||||
| Add window to Bonus Room | ||||
| 12 X 12 Deck | ||||
| White/Gray Painted Kitchen Cabinetry | ||||
| Vent Microwave to Exterior | ||||
| Upgrades Built Into Updated List Price | ||||
| French Model Refrigerator | ||||
| Expanded driveway | ||||
| Digital deadbolt | ||||
| Grace keypad | ||||
| Amendment to increase price by $950 | ||||
| Payment from buyer for digital deadbolt, keypad | ||||
| Payment from mom for expanded driveway | ||||
| CRITICAL PATH - COMPLETED | ||||
| -- | -- | Inspection (Footers) (1) 09.06.2022 | ||
| -- | -- | Inspection (Concrete Wall) (1) 09.07.2022 | ||
| -- | -- | Inspection (Plumbing Under Slab) (1) 09.06.2022 | ||
| -- | -- | Inspection (Conduit Under Slab) (1) 09.07.2022 | ||
| -- | -- | Inspection (Slab) (1) 09.06.2022 | ||
| -- | -- | Inspection (Drain Tile) (0) 09.08.2022 | ||
| -- | -- | Inspection (Rough In HVAC) (1) 11.07.2022 | ||
| -- | -- | Inspection (Rough In Plumbing) (1) 11.10.2022 | ||
| -- | -- | Inspection (Rough In Electric) (1) 11.16.2022 | ||
| -- | -- | Inspection (Framing) (1) * 11.21.2022 | ||
| -- | -- | Inspection (Deck Piers) (0) 02.13.2023 | ||
| -- | -- | Inspection (Insulation) (1) 11.21.2022 | ||
| -- | -- | Inspection (Electric Service) (0) 03.08.2023 | ||
| -- | -- | Inspection (Main Sewer Line) (0) 01.23.2023 | ||
| -- | -- | Inspection (Main Water Line) (0) 01.23.2023 | ||
| -- | -- | Inspection (Final HVAC) (0) 03.21.2023 | ||
| -- | -- | Inspection (Final Plumbing) (0) 03.21.2023 | ||
| -- | -- | Inspection (Final Electric) (0) 03.21.2023 | ||
| -- | -- | Inspection (Final Building) (4) * 03.21.2023 | ||