Thu |
Nov 28 |
Verify Window & Roof Structure (0) |
|
|
Thu |
Nov 28 |
Rough In Microwave Vent (0) |
|
|
Thu |
Nov 28 |
Blower Door Test (1) |
|
|
|
-- |
-- |
Dimmer Switch LR Lights- Because we Love Suzanne Trow!!! |
|
|
-- |
-- |
Home Sale Contingency |
Settlement Deadline = Sept 30 |
|
-- |
-- |
Master bath vanity not installed 12/17 |
|
|
-- |
-- |
Broken master bath vanity 12/28 |
Cultured marble top is broken - Kate will order it again |
|
-- |
-- |
FLOORING AND PAINT COLOR TBD BY BUYER |
|
|
-- |
-- |
broken vanity still on site-as well as a few single cultured marble tops |
in kitchen |
|
-- |
-- |
Extra ceiling fans on site? I don’t see them 2/4 |
Electrician |
|
-- |
-- |
Powder mirror needed |
Joe |
|
-- |
-- |
Black shower drain needed |
Plumber |
|
-- |
-- |
All ceiling fans needed-3 |
Electrician. Living room done |
|
-- |
-- |
All bulbs needed |
Electrician |
|
-- |
-- |
CODED LOCKBOX 0109 |
Attach a vinyl ring to deck post |
|
-- |
-- |
Siding/awning needs attention |
Trim house wrap - Tom. Needs done 3/5 |
|
-- |
-- |
Damaged transition strip |
Landing at 2nd level hallway still needs replacing |
|
-- |
-- |
Why was a shower door installed? |
Please let Scott know |
|
-- |
-- |
Should the floors be covered? |
|
|
-- |
-- |
Weatherstripping needed on exterior doors? |
Courtney - please confirm. All doors need it. |
|
-- |
-- |
Tub repair |
Jill. In process 3/1 |
|
-- |
-- |
Weatherstripping needed front door |
|
|
-- |
-- |
Clean out garage. This one is most packed |
Tom |
|
-- |
-- |
Transition strip needed replaced on upper stairs too |
3/20- looks good to Kate |
|
-- |
-- |
Attic cover needed |
Painter |
|
-- |
-- |
Owners on site mentioning small bedroom fans are reall large |
|
|
-- |
-- |
Touch up spot bath fan |
Painter |
|
-- |
-- |
Flip fans blades living room |
Electrician |
|
-- |
-- |
Flip fans blades living room |
|
|
-- |
-- |
Garage trim needed |
Weatherstripping - Jeff, Davenport |
|
-- |
-- |
Pressure wash all patios |
Bridges |
|
-- |
-- |
Interest Rate Lock expires March 19 |
Can we close before that time? |
|
-- |
-- |
Patio door needs weatherstripping |
Jill |
|
-- |
-- |
Garage door trim |
PVC board, Davenport |
|
-- |
-- |
Remove broken hot water heater |
Tom, Northeastern |
|
-- |
-- |
Ceiling in garage needs patched (near where wire hangs) |
I think this was repaired (see pic) |
|
-- |
-- |
Flooring is chipped near transition strips? |
Jill |
|
-- |
-- |
Spicket casing needs installed (exterior) |
|
|
-- |
-- |
Crack in drywall of master bedroom ceiling |
Painter |
|
-- |
-- |
Screens |
Jill |
|
-- |
-- |
Put patio transition board in place |
Tom |
|
-- |
-- |
Clean off back patio |
Court |
|
-- |
-- |
Several nail holes in shoe to be filled |
In island - Jill |
|
-- |
-- |
Push range in place |
|
|
-- |
-- |
Missing vent cover living room floor |
Jill |
|
-- |
-- |
Is there poly on stairs??? |
Painter |
|
-- |
-- |
Closet doors in upstairs bedrooms to be adjusted |
Jill |
|
-- |
-- |
Drywall glue on master shower wall to be removed |
Court |
|
-- |
-- |
Master bedroom light not coming on |
|
|
-- |
-- |
Clean off deck |
Court |
|
-- |
-- |
Clean out garage |
Court |
|
-- |
-- |
Clean dust off kitchen handles |
Court |
|
-- |
-- |
Remove paint from all hinges handles and brackets |
Painter |
|
-- |
-- |
Sand and repaint the tray ceiling |
Painter |
|
-- |
-- |
Install master shower rod |
Joe- Tuesday morning |
|
-- |
-- |
Adjust water pressure |
Jill |
|
-- |
-- |
Fill nail holes at shoe for master and hall vanities |
Jill |
|
-- |
-- |
Several vinyl issues at bump out window |
Greg |
|
-- |
-- |
Adjust garage door |
Greg |
|
-- |
-- |
Front door 1/4 inch off |
Tom, Domingo |
|
-- |
-- |
Repaint closet under stairs |
Painter |
|
-- |
-- |
Crack on handrail at the top of the steps |
Painter |
|
-- |
-- |
Repaint garage |
Painter |
|
-- |
-- |
Mop out garage floor |
Court |
|
-- |
-- |
Raise pendant lights 8 inches |
Electrician |
|
-- |
-- |
Move electric outlet installed on floor of cabinet to the side of the cabinet under the kitchen sink |
Electrician |
|
-- |
-- |
Replace stair transition going up stairs |
|
|
-- |
-- |
Remove hot water heater |
Tom |
|
-- |
-- |
Attach a vinyl ring to deck post |
|
|
-- |
-- |
Attach a vinyl ring to deck post |
|
|
-- |
-- |
School bus will not come down to Palomino until VDOT signs off on the road |
8/23: RCPS Transportation will call VDOT to ask if the road is approved |
|
-- |
-- |
Grass issue out back, turning black due to no sunlight back there (owner wants stones instead) |
Kate will take a look |
|
-- |
-- |
The placement of her bedroom closet light switch, can we have electricians move it for her? |
Jill will coordinate |
|
-- |
-- |
Board on deck needs replaced |
|
|
-- |
-- |
Move receptacle under kitchen sink |
|
|
-- |
-- |
Adjust the water pressure some more |
|
|
-- |
-- |
PVC on both sides of the garage door is bowing |
|
|
-- |
-- |
Transition strip on first landing needs replaced |
Denny |
|
-- |
-- |
Screen door needs replaced |
|
|
-- |
-- |
Siding on master bump out needs fixed in the corners |
|
|
-- |
-- |
Black aluminum needs replaced at the front door |
Davenport. Repairing 10/18 |
|
-- |
-- |
Front door needs fixed and painted |
|
|
-- |
-- |
Ratified Contract? (0) 07.29.2022 |
|
|
-- |
-- |
$2500 Deposit Received (0) 08.08.2022 |
|
|
-- |
-- |
Association Packet Requested (0) 07.29.2022 |
|
|
-- |
-- |
Association Packet Received (0) 07.30.2022 |
|
|
-- |
-- |
Selections Meeting (0) 08.29.2022 |
|
|
-- |
-- |
Selections Sheet Signed (0) 09.11.2022 |
8/29/2022: sent to Nicole for review |
|
-- |
-- |
Amendment for Upgrades (B,S,L,T,BCP) (0) 10.01.2022 |
9/30/2022: sent to Jerry for signature |
|
-- |
-- |
Deposit For Upgrades Received (0) 09.30.2022 |
|
|
-- |
-- |
Building Permit (30) 07.20.2022 |
|
|
-- |
-- |
Order Roof & Floor Trusses (1) 08.29.2022 |
|
|
-- |
-- |
Order Windows & Doors (0) 09.08.2022 |
|
|
-- |
-- |
Stake Out Home (1) 07.28.2022 |
|
|
-- |
-- |
Excavate (2) 09.01.2022 |
|
|
-- |
-- |
Inspection (Footers) (1) 09.01.2022 |
|
|
-- |
-- |
Inspection (Concrete Wall) (1) 09.07.2022 |
|
|
-- |
-- |
Pour Footers (1) 09.01.2022 |
|
|
-- |
-- |
Set Forms (2) 09.06.2022 |
|
|
-- |
-- |
Pour Foundation Walls (1) 09.06.2022 |
|
|
-- |
-- |
Plumb Slab (2) 09.01.2022 |
|
|
-- |
-- |
Inspection (Plumbing Under Slab) (1) 09.06.2022 |
|
|
-- |
-- |
Inspection (Conduit Under Slab) (1) 09.07.2022 |
|
|
-- |
-- |
Prepare Slab (1) 09.06.2022 |
|
|
-- |
-- |
Inspection (Slab) (1) 09.06.2022 |
|
|
-- |
-- |
Inspection (Drain Tile) (0) 09.08.2022 |
|
|
-- |
-- |
Pour Slab (1) * 09.06.2022 |
|
|
-- |
-- |
Settlement Agent Confirmed (0) 10.08.2022 |
|
|
-- |
-- |
Framing I (9) 09.29.2022 |
|
|
-- |
-- |
Order Steps (0) 10.10.2022 |
|
|
-- |
-- |
Order Tubs / Showers (0) 10.10.2022 |
|
|
-- |
-- |
Framing II (8) 10.09.2022 |
|
|
-- |
-- |
Framing III (8) * 10.20.2022 |
|
|
-- |
-- |
Install Stairs (0) 10.29.2022 |
|
|
-- |
-- |
Windows & Doors (0) 10.29.2022 |
|
|
-- |
-- |
House Number and Status in Window (0) 12.10.2022 |
|
|
-- |
-- |
Roofing (0) 10.29.2022 |
|
|
-- |
-- |
Order Cabinets (0) 10.07.2022 |
|
|
-- |
-- |
Order Appliances (0) 08.30.2022 |
Standard |
|
-- |
-- |
Deck (0) 10.29.2022 |
Expanded 12 x 18 Deck |
|
-- |
-- |
Gutters (0) 02.06.2023 |
|
|
-- |
-- |
Driveway (0) 12.28.2022 |
Expanded Driveway |
|
-- |
-- |
Patio (0) 12.07.2022 |
Expanded 10 x 10 Patio Below Deck |
|
-- |
-- |
Privacy Divider / Fence (0) 02.04.2023 |
privacy panel up-needs deck railings |
|
-- |
-- |
Sod / Seed / Landscaping (0) 03.01.2023 |
|
|
-- |
-- |
HVAC Rough In (4) 10.29.2022 |
In process 10/26 |
|
-- |
-- |
Inspection (Rough In HVAC) (1) 11.07.2022 |
|
|
-- |
-- |
Plumbing Rough In (4) 11.09.2022 |
In process 11/2 |
|
-- |
-- |
Inspection (Rough In Plumbing) (1) 11.10.2022 |
|
|
-- |
-- |
Electric Rough In (4) 11.16.2022 |
In process (almost complete) 11/12 |
|
-- |
-- |
Inspection (Rough In Electric) (1) 11.16.2022 |
|
|
-- |
-- |
Inspection (Deck Piers) (0) 11.10.2022 |
|
|
-- |
-- |
Inspection (Framing) (1) 11.16.2022 |
|
|
-- |
-- |
Exterior Vinyl (0) * 01.28.2023 |
|
|
-- |
-- |
Exterior Stone (0) 04.14.2022 |
|
|
-- |
-- |
Insulation (2) 11.16.2022 |
|
|
-- |
-- |
Inspection (Insulation) (1) 11.21.2022 |
|
|
-- |
-- |
Inspection (Electric Service) (0) 03.08.2023 |
|
|
-- |
-- |
Set Electric Meter (0) 04.06.2023 |
|
|
-- |
-- |
Inspection (Main Sewer Line) (0) 01.23.2023 |
|
|
-- |
-- |
Inspection (Main Water Line) (0) 01.23.2023 |
|
|
-- |
-- |
Order Interior Doors & Trim (0) 12.08.2022 |
|
|
-- |
-- |
Drywall (Hang) (4) * 11.27.2022 |
NONE |
|
-- |
-- |
Loan Approval (0) 02.06.2023 |
|
|
-- |
-- |
Deed Preparation (0) 01.31.2023 |
|
|
-- |
-- |
Drywall (Tape, Block, Skim, Sand) (6) * 12.10.2022 |
In process 12/7 |
|
-- |
-- |
Paint 1 (1) 12.10.2022 |
|
|
-- |
-- |
Garage Door (0) 02.22.2023 |
|
|
-- |
-- |
House Numbers (0) 02.22.2023 |
Missing 1 number |
|
-- |
-- |
Mailbox (0) 02.09.2023 |
|
|
-- |
-- |
Cabinet Installation (2) * 12.17.2022 |
Dec 15. On site 12/14 |
|
-- |
-- |
Granite Installation (1) * 12.27.2022 |
|
|
-- |
-- |
Interior Trim - Install (3) 01.07.2023 |
In process 1/1 |
|
-- |
-- |
Order Plumbing / Lighting Fixtures (0) 08.10.2023 |
|
|
-- |
-- |
Interior Trim - Paint (1) 01.14.2023 |
|
|
-- |
-- |
Luxury Vinyl Plank (3) * 01.28.2023 |
In process 1/25 |
|
-- |
-- |
Luxury Vinyl Tile (0) 01.25.2023 |
|
|
-- |
-- |
Paint 2 (3) 01.28.2023 |
In process 1/11 |
|
-- |
-- |
Cover Floors (1) 02.01.2023 |
|
|
-- |
-- |
Deliver Plumbing / Lighting Fixtures (0) 01.16.2023 |
|
|
-- |
-- |
Shoe Moulding (0) 02.01.2023 |
|
|
-- |
-- |
Shelving, Door Knobs, Fire Extinguisher (0) 02.08.2023 |
Black accessories, Bonus bath. Mirrors are up 2/4 |
|
-- |
-- |
Install Coded Lockbox (add extra keys) (0) 02.15.2023 |
|
|
-- |
-- |
Pay Water / Sewer Taps (0) 01.10.2023 |
|
|
-- |
-- |
Set Water Meter (0) 01.23.2023 |
|
|
-- |
-- |
Electric Trim Out (3) 02.11.2023 |
Black Standard. Just need ceiling fans 2/8 |
|
-- |
-- |
Ceiling Fans (0) 02.04.2023 |
|
|
-- |
-- |
HVAC Trim Out (1) 02.18.2023 |
|
|
-- |
-- |
Plumbing Trim Out (2) 02.04.2023 |
Black Standard. In process 2/1 |
|
-- |
-- |
Install Appliances (0) * 02.04.2023 |
Delivery 10/31- Schedule install with CJ |
|
-- |
-- |
Paint 3 (2) * 01.28.2023 |
|
|
-- |
-- |
Carpet (2) 11.14.2022 |
|
|
-- |
-- |
Appraiser Confirms Construction Completion (0) 03.23.2023 |
Randy, Colonial |
|
-- |
-- |
Inspection (Final HVAC) (1) 03.21.2023 |
|
|
-- |
-- |
Inspection (Final Plumbing) (1) 03.21.2023 |
|
|
-- |
-- |
Inspection (Final Electric) (1) 03.21.2023 |
|
|
-- |
-- |
Inspection (Final Building) (2) * 03.21.2023 |
|
|
-- |
-- |
Pre Walk Through (0) 03.18.2023 |
|
|
-- |
-- |
Stain Hardwood Stairs (1) 02.15.2023 |
|
|
-- |
-- |
Cleaning (1) 03.21.2023 |
|
|
-- |
-- |
Certificate of Occupancy (1) * 03.21.2023 |
|
|
-- |
-- |
C.O. to Lender (0) 03.21.2023 |
|
|
-- |
-- |
Schedule Closing (0) 03.23.2023 |
|
|
-- |
-- |
Buyer Walk Through (1) 03.21.2023 |
|
|
-- |
-- |
Payment for Upgrades (0) 03.05.2023 |
|
|
-- |
-- |
Keys to Settlement Agent (0) 03.05.2023 |
|
|
-- |
-- |
Review Settlement Statement (0) 03.23.2023 |
|
|
-- |
-- |
Jerry Signs Closing Documents (0) 03.10.2023 |
|
|
-- |
-- |
Request Trash Tote From POA Manager (0) 03.18.2023 |
|
|
-- |
-- |
Closing (1) 03.24.2023 |
Brittany @ West View Title |
|
-- |
-- |
Remove Coded Lockbox (0) 03.27.2023 |
|
|