Thu |
Nov 28 |
Verify Window & Roof Structure (0) |
|
|
Thu |
Nov 28 |
Rough In Microwave Vent (0) |
|
|
Thu |
Nov 28 |
Order Plumbing / Lighting Fixtures (0) |
|
|
Thu |
Nov 28 |
Blower Door Test (1) |
|
|
|
-- |
-- |
Paint 1 i process 12/7 |
|
|
-- |
-- |
Patch concrete hole in base bath |
|
|
-- |
-- |
Waiting on farmhouse sink |
Fred. In kitchen floor |
|
-- |
-- |
Awning looks slightly bent? |
Tom, Jeremy, Davenport |
|
-- |
-- |
Patch holes in all garage trim |
PVC Board, Davenport |
|
-- |
-- |
Garage keypad |
Davenport-after garage trim is repaired |
|
-- |
-- |
Cover carpet |
Need to cover carpet |
|
-- |
-- |
CODED LOCKBOX 0110 |
|
|
-- |
-- |
Push oven in place |
Tom |
|
-- |
-- |
Dent in Refrigerator |
Kate has alerted Leisa |
|
-- |
-- |
Replace deadbolt as paint has been rubbed off? |
Joe |
|
-- |
-- |
Bonus bath light fixture needed |
Electrician |
|
-- |
-- |
Receptacles needed in island |
Electrician |
|
-- |
-- |
Needs all lightbulbs |
Electrician |
|
-- |
-- |
Drywall repair in bonus bath |
Drywall. Needs painting 2/22 |
|
-- |
-- |
Receptacles not centered |
|
|
-- |
-- |
Powder bath receptacle needed |
Electrician |
|
-- |
-- |
Small holes to patch powder bath |
Painter |
|
-- |
-- |
Wall touch up paint needed |
Painter |
|
-- |
-- |
Cable box covers needed in all units |
Low voltage panels in garage - Tom |
|
-- |
-- |
Fill screw holes at French door |
Jill |
|
-- |
-- |
Pantry support missing on support rod |
Joe |
|
-- |
-- |
|
|
|
-- |
-- |
Upstairs closet doors to be adjusted |
Jill |
|
-- |
-- |
Floor squeak at the top of first set of steps in hallway between kitchen and living room |
Denny |
|
-- |
-- |
Fill screw holes at front door |
Jill |
|
-- |
-- |
Remove construction debris off bonus room door |
Jill |
|
-- |
-- |
Range in garage unprotected??? Yikes |
Kate will talk to CJ |
|
-- |
-- |
Range in garage unprotected??? Yikes |
|
|
-- |
-- |
Weatherstripping back patio |
Jill |
|
-- |
-- |
Electric cover needed in garage |
Jill |
|
-- |
-- |
Weatherstripping back door |
Jill |
|
-- |
-- |
Cabinet chip back of cabinet next to microwave |
Tom? Fred? |
|
-- |
-- |
Trim on either side of farm sink |
Tom? |
|
-- |
-- |
Clea paint off handles, knobs, etc. |
|
|
-- |
-- |
Clean paint off handles, knobs, etc |
Painter |
|
-- |
-- |
Hall bath fan to be fixed to ceiling with paint touch up |
Electrician |
|
-- |
-- |
nick in master shower |
Jill. Likely fixed 3/22 |
|
-- |
-- |
Bonus Bath- clean paint off kicjkplate |
|
|
-- |
-- |
Bonus Bath- clean paint off kickplate |
Painter |
|
-- |
-- |
Paint Touch Up Throughout |
Painter. In process 3/22 |
|
-- |
-- |
Repaint garage |
Painter |
|
-- |
-- |
Several outlets to be straigtened- marked wiht blue tape |
Electrician |
|
-- |
-- |
Moulding on both sides of farm sink |
Fred is aware and has the owners contact info |
|
-- |
-- |
Drywall patch and paint |
3/30 - waiting to get in, coordinating with owner |
|
-- |
-- |
Ratified Contract? (0) 03.27.2022 |
|
|
-- |
-- |
$2500 Deposit Received (0) 03.30.2022 |
|
|
-- |
-- |
Association Packet Requested (0) 03.27.2022 |
|
|
-- |
-- |
Association Packet Received (0) 04.02.2022 |
|
|
-- |
-- |
Selections Meeting (0) 04.05.2022 |
|
|
-- |
-- |
Selections Sheet Signed (0) 04.29.2022 |
|
|
-- |
-- |
Amendment for Upgrades (B,S,L,T,BCP) (0) 06.07.2022 |
6/7/2022: sent to Jerry for signatures |
|
-- |
-- |
Deposit For Upgrades Received (0) 06.07.2022 |
|
|
-- |
-- |
Building Permit (30) 07.20.2022 |
|
|
-- |
-- |
Order Roof & Floor Trusses (1) 08.29.2022 |
|
|
-- |
-- |
Order Windows & Doors (0) 09.08.2022 |
|
|
-- |
-- |
Stake Out Home (1) 07.28.2022 |
|
|
-- |
-- |
Excavate (2) 09.01.2022 |
|
|
-- |
-- |
Inspection (Footers) (1) 09.01.2022 |
|
|
-- |
-- |
Inspection (Concrete Wall) (1) 09.07.2022 |
|
|
-- |
-- |
Pour Footers (1) 09.01.2022 |
|
|
-- |
-- |
Set Forms (2) 09.06.2022 |
|
|
-- |
-- |
Pour Foundation Walls (1) 09.06.2022 |
|
|
-- |
-- |
Plumb Slab (2) 09.01.2022 |
|
|
-- |
-- |
Inspection (Plumbing Under Slab) (1) 09.06.2022 |
|
|
-- |
-- |
Inspection (Conduit Under Slab) (1) 09.07.2022 |
|
|
-- |
-- |
Prepare Slab (1) 09.06.2022 |
|
|
-- |
-- |
Inspection (Slab) (1) 09.06.2022 |
|
|
-- |
-- |
Inspection (Drain Tile) (0) 09.08.2022 |
|
|
-- |
-- |
Pour Slab (1) * 09.06.2022 |
|
|
-- |
-- |
Settlement Agent Confirmed (0) 04.02.2022 |
|
|
-- |
-- |
Framing I (9) 09.29.2022 |
|
|
-- |
-- |
Order Steps (0) 10.10.2022 |
|
|
-- |
-- |
Order Tubs / Showers (0) 10.10.2022 |
|
|
-- |
-- |
Framing II (8) 10.09.2022 |
|
|
-- |
-- |
Framing III (8) * 10.20.2022 |
|
|
-- |
-- |
Install Stairs (0) 10.29.2022 |
|
|
-- |
-- |
Windows & Doors (0) 10.29.2022 |
|
|
-- |
-- |
House Number and Status in Window (0) 12.10.2022 |
|
|
-- |
-- |
Roofing (0) 10.29.2022 |
|
|
-- |
-- |
Order Cabinets (0) 10.11.2022 |
|
|
-- |
-- |
Order Appliances (0) 08.30.2022 |
Standard |
|
-- |
-- |
Deck (0) 10.29.2022 |
Expanded 12 x 18 Deck |
|
-- |
-- |
Gutters (0) 02.06.2023 |
|
|
-- |
-- |
Driveway (0) 12.28.2022 |
Expanded Driveway |
|
-- |
-- |
Patio (0) 12.07.2022 |
Standard |
|
-- |
-- |
Privacy Divider / Fence (0) 02.04.2023 |
privacy panel up-needs deck railings |
|
-- |
-- |
Sod / Seed / Landscaping (0) 03.01.2023 |
|
|
-- |
-- |
HVAC Rough In (4) 11.02.2022 |
In process10/29 |
|
-- |
-- |
Inspection (Rough In HVAC) (1) 11.07.2022 |
|
|
-- |
-- |
Plumbing Rough In (4) 11.02.2022 |
|
|
-- |
-- |
Inspection (Rough In Plumbing) (1) 11.10.2022 |
|
|
-- |
-- |
Electric Rough In (4) 11.09.2022 |
In process 11/5 |
|
-- |
-- |
Inspection (Rough In Electric) (1) 11.10.2022 |
|
|
-- |
-- |
Inspection (Deck Piers) (0) 11.10.2022 |
|
|
-- |
-- |
Inspection (Framing) (1) 11.10.2022 |
|
|
-- |
-- |
Exterior Vinyl (0) * 01.28.2023 |
|
|
-- |
-- |
Exterior Stone (0) 04.14.2022 |
|
|
-- |
-- |
Insulation (2) 11.12.2022 |
|
|
-- |
-- |
Inspection (Insulation) (1) 11.17.2022 |
|
|
-- |
-- |
Inspection (Electric Service) (0) 03.08.2023 |
|
|
-- |
-- |
Set Electric Meter (0) 04.06.2023 |
|
|
-- |
-- |
Inspection (Main Sewer Line) (0) 01.23.2023 |
|
|
-- |
-- |
Inspection (Main Water Line) (0) 01.23.2023 |
|
|
-- |
-- |
Order Interior Doors & Trim (0) 12.08.2022 |
|
|
-- |
-- |
Drywall (Hang) (4) * 11.27.2022 |
Bonus Room, Bath. Stocked 11/19 |
|
-- |
-- |
Loan Approval (0) 01.31.2023 |
|
|
-- |
-- |
Deed Preparation (0) 01.31.2023 |
|
|
-- |
-- |
Drywall (Tape, Block, Skim, Sand) (6) * 12.07.2022 |
In process11/27 |
|
-- |
-- |
Paint 1 (1) 12.10.2022 |
|
|
-- |
-- |
Garage Door (0) 01.28.2023 |
|
|
-- |
-- |
House Numbers (0) 02.15.2023 |
Jill |
|
-- |
-- |
Mailbox (0) 02.09.2023 |
|
|
-- |
-- |
Cabinet Installation (2) * 12.17.2022 |
Dec 14. In process 12/14 |
|
-- |
-- |
Granite Installation (1) * 01.28.2023 |
Jan 27 |
|
-- |
-- |
Interior Trim - Install (3) 01.07.2023 |
In process 1/1 |
|
-- |
-- |
Interior Trim - Paint (1) 01.07.2023 |
|
|
-- |
-- |
Luxury Vinyl Plank (3) * 01.21.2023 |
In process 1/18 |
|
-- |
-- |
Luxury Vinyl Tile (0) 01.14.2023 |
|
|
-- |
-- |
Paint 2 (3) 01.07.2023 |
|
|
-- |
-- |
Cover Floors (1) 01.28.2023 |
|
|
-- |
-- |
Deliver Plumbing / Lighting Fixtures (0) 01.16.2023 |
|
|
-- |
-- |
Shoe Moulding (0) 01.25.2023 |
|
|
-- |
-- |
Shelving, Door Knobs, Fire Extinguisher (0) 02.08.2023 |
Few knobs needed in basement. In process 2/4 |
|
-- |
-- |
Install Coded Lockbox (add extra keys) (0) 02.01.2023 |
|
|
-- |
-- |
Pay Water / Sewer Taps (0) 01.10.2023 |
|
|
-- |
-- |
Set Water Meter (0) 01.23.2023 |
|
|
-- |
-- |
Electric Trim Out (3) 02.11.2023 |
Black Standard. In process 2/8 |
|
-- |
-- |
Ceiling Fans (0) 02.08.2023 |
|
|
-- |
-- |
HVAC Trim Out (1) 02.18.2023 |
|
|
-- |
-- |
Plumbing Trim Out (2) 01.28.2023 |
Farmhouse Plumbing Black. In process 1/25 |
|
-- |
-- |
Install Appliances (0) * 02.08.2023 |
Delivery 10/31- Schedule install with CJ |
|
-- |
-- |
Paint 3 (2) * 01.11.2023 |
|
|
-- |
-- |
Carpet (2) 01.21.2023 |
In process 1/14 |
|
-- |
-- |
Appraiser Confirms Construction Completion (0) 03.23.2023 |
Joe Chadwell, 3/15 |
|
-- |
-- |
Inspection (Final HVAC) (1) 03.22.2023 |
|
|
-- |
-- |
Inspection (Final Plumbing) (1) 03.22.2023 |
|
|
-- |
-- |
Inspection (Final Electric) (1) 03.22.2023 |
|
|
-- |
-- |
Inspection (Final Building) (2) * 03.22.2023 |
|
|
-- |
-- |
Pre Walk Through (0) 03.18.2023 |
|
|
-- |
-- |
Stain Hardwood Stairs (1) 02.11.2023 |
In process 2/8 |
|
-- |
-- |
Cleaning (1) 03.22.2023 |
In process 3/1 |
|
-- |
-- |
Certificate of Occupancy (1) * 03.22.2023 |
|
|
-- |
-- |
C.O. to Lender (0) 03.22.2023 |
|
|
-- |
-- |
Schedule Closing (0) 03.23.2023 |
|
|
-- |
-- |
Buyer Walk Through (1) 03.22.2023 |
Monday, Mar 20, 4 PM |
|
-- |
-- |
Payment for Upgrades (0) 03.05.2023 |
|
|
-- |
-- |
Keys to Settlement Agent (0) 03.03.2023 |
|
|
-- |
-- |
Review Settlement Statement (0) 03.23.2023 |
|
|
-- |
-- |
Jerry Signs Closing Documents (0) 03.10.2023 |
|
|
-- |
-- |
Request Trash Tote From POA Manager (0) 03.18.2023 |
|
|
-- |
-- |
Closing (1) 03.27.2023 |
Brittany @ West View Title |
|
-- |
-- |
Remove Coded Lockbox (0) 03.27.2023 |
|
|