37 ADDR
CONGERS-2 - 110  ::  1427 Palomino Trail
[ BUILD: 20221347 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
TO DO
---
UPGRADES
    LVP Up hallway ($1100) and Bonus Room ($1520)  
CRITICAL PATH
---
TO DO - COMPLETED OR DELETED
UPGRADES - COMPLETED
    Finished Bonus Room  
    Finished Bonus Bath  
    Expanded Driveway  
    Expanded Deck 12 x 18  
    White Kitchen Cabinets  
    Double Waste Basket Island  
    Roll Out Trays Pantry  
    Cabinet Crown Moulding  
    Three Drawer Stack  
    Farmhouse Sink  
    Shower Door with black trim  
    Garage Keypad  
    Oak Treads to Bedroom Level  
    Farmhouse Plumbing Package  
    Amendment to increase price by $29,770  
CRITICAL PATH - COMPLETED
-- -- Inspection (Footers) (1)  09.01.2022    
-- -- Inspection (Concrete Wall) (1)  09.07.2022    
-- -- Inspection (Plumbing Under Slab) (1)  09.06.2022    
-- -- Inspection (Conduit Under Slab) (1)  09.07.2022    
-- -- Inspection (Slab) (1)  09.06.2022    
-- -- Inspection (Drain Tile) (0)  09.08.2022    
-- -- Inspection (Rough In HVAC) (1)  11.07.2022    
-- -- Inspection (Rough In Plumbing) (1)  11.10.2022    
-- -- Inspection (Rough In Electric) (1)  11.10.2022    
-- -- Inspection (Framing) (1) *   11.10.2022    
-- -- Inspection (Deck Piers) (0)  11.10.2022    
-- -- Inspection (Insulation) (1)  11.17.2022    
-- -- Inspection (Electric Service) (0)  03.08.2023    
-- -- Inspection (Main Sewer Line) (0)  01.23.2023    
-- -- Inspection (Main Water Line) (0)  01.23.2023    
-- -- Inspection (Final HVAC) (0)  03.22.2023    
-- -- Inspection (Final Plumbing) (0)  03.22.2023    
-- -- Inspection (Final Electric) (0)  03.22.2023    
-- -- Inspection (Final Building) (4) *   03.22.2023