USDA loan - closing approx 20 days after completion |
|
|
-- |
-- |
H/w treads to 2nd level |
|
|
-- |
-- |
Covered attic access w drywall 12/10 |
|
|
-- |
-- |
Farmhouse sink in kitchen 1/4 |
|
|
-- |
-- |
|
|
|
-- |
-- |
2nd patio panel needed 2/1 |
|
|
-- |
-- |
Brown kitchen island covers needed |
|
|
-- |
-- |
Cable covers needed |
|
|
-- |
-- |
Needs mirrors |
Joe |
|
-- |
-- |
Drywall touch up living room |
Painter |
|
-- |
-- |
Attic cover |
Painter |
|
-- |
-- |
Black mb shower drain needed |
Plumber |
|
-- |
-- |
Missing one house number |
Jill |
|
-- |
-- |
CODED LOCKBOX 2525 |
|
|
-- |
-- |
Final touch up needed stairs |
|
|
-- |
-- |
Plastic needed to cover outside hose |
Beauty ring - Davenport |
|
-- |
-- |
Cover for washer/dryer hookup |
Plumber |
|
-- |
-- |
|
|
|
-- |
-- |
Plugs for all screw holes indoors |
Jill |
|
-- |
-- |
Adjust closet doors |
Jill |
|
-- |
-- |
Add bracket to bottom of hand rail going to bed or level |
Trim |
|
-- |
-- |
Can we cut down the white water pump out front? |
Sewer clean out |
|
-- |
-- |
Cut black paper off all back patios below whiteboard? Needs completed all units. |
Jill |
|
-- |
-- |
Beeping smoke detectors |
Tom |
|
-- |
-- |
Change dining chandelier to one wiht chain |
Electrician |
|
-- |
-- |
Cleanup/paint exterior patio doors. |
Jill |
|
-- |
-- |
Install covers and screw holes in patio door |
Jill |
|
-- |
-- |
Small hole above showerhead in hall bathroom |
Painter |
|
-- |
-- |
Install attic access cover |
Jill |
|
-- |
-- |
Clean out bonus room and garage |
Just bonus room |
|
-- |
-- |
Install screw hole covers |
|
|
-- |
-- |
Corner piece of island trim very scuffed |
Jill |
|
-- |
-- |
I’m just upstairs closet doors |
|
|
-- |
-- |
Patch small hole under showerhead in hall bathroom |
Painter |
|
-- |
-- |
Adjust upstairs closet doors |
Jill |
|
-- |
-- |
Remove black paper from back patio |
|
|
-- |
-- |
Install the door to the bonus room |
Jill |
|
-- |
-- |
Drywall patch needed beside electrical covers in garage |
Painter |
|
-- |
-- |
Remove glue in tub |
Jill |
|
-- |
-- |
Remove splash of concrete on front door |
Jill |
|
-- |
-- |
Install screens throughout |
|
|
-- |
-- |
Scratches on patio door |
Jill |
|
-- |
-- |
Remove mud from carpet on the stairs |
Jill |
|
-- |
-- |
Stove has a scratch on the back f |
|
|
-- |
-- |
There is a scratch on the back in about y |
|
|
-- |
-- |
Stove is scratched in the middle of the top |
CJ |
|
-- |
-- |
Drywall repair in garage by panel box needed |
Drywaller |
|
-- |
-- |
CODED LOCKBOX 2525 |
|
|
-- |
-- |
Hairline crack in bath tub |
8/21: Jill is coordinating a visit with the tub repair person |
|
-- |
-- |
Ratified Contract? (0) 03.31.2022 |
|
|
-- |
-- |
$2500 Deposit Received (0) 04.13.2022 |
|
|
-- |
-- |
Association Packet Requested (0) 03.31.2022 |
|
|
-- |
-- |
Association Packet Received (0) 04.02.2022 |
|
|
-- |
-- |
Selections Meeting (0) 05.06.2022 |
|
|
-- |
-- |
Selections Sheet Signed (0) 06.21.2022 |
6/14/2022: sent to Kozhin for signatures |
|
-- |
-- |
Amendment for Upgrades (B,S,L,T,BCP) (0) 07.29.2022 |
7/28: sent to Jerry for signatures |
|
-- |
-- |
Deposit For Upgrades Received (0) 07.28.2022 |
|
|
-- |
-- |
Building Permit (30) 07.22.2022 |
|
|
-- |
-- |
Order Roof & Floor Trusses (1) 09.08.2022 |
|
|
-- |
-- |
Order Windows & Doors (0) 09.08.2022 |
|
|
-- |
-- |
Stake Out Home (1) 07.28.2022 |
|
|
-- |
-- |
Excavate (2) 08.08.2022 |
|
|
-- |
-- |
Inspection (Footers) (1) 08.08.2022 |
|
|
-- |
-- |
Inspection (Concrete Wall) (1) 09.07.2022 |
|
|
-- |
-- |
Pour Footers (1) 08.08.2022 |
|
|
-- |
-- |
Set Forms (2) 08.08.2022 |
|
|
-- |
-- |
Pour Foundation Walls (1) 08.15.2022 |
|
|
-- |
-- |
Plumb Slab (2) 09.06.2022 |
|
|
-- |
-- |
Inspection (Plumbing Under Slab) (1) 09.06.2022 |
|
|
-- |
-- |
Inspection (Conduit Under Slab) (1) 09.08.2022 |
|
|
-- |
-- |
Prepare Slab (1) 09.06.2022 |
|
|
-- |
-- |
Inspection (Slab) (1) 09.08.2022 |
|
|
-- |
-- |
Inspection (Drain Tile) (0) 10.10.2022 |
|
|
-- |
-- |
Pour Slab (1) * 09.12.2022 |
|
|
-- |
-- |
Settlement Agent Confirmed (0) 01.31.2023 |
|
|
-- |
-- |
Framing I (9) 09.29.2022 |
|
|
-- |
-- |
Order Steps (0) 10.10.2022 |
|
|
-- |
-- |
Order Tubs / Showers (0) 10.10.2022 |
|
|
-- |
-- |
Framing II (8) 10.09.2022 |
|
|
-- |
-- |
Framing III (8) * 10.17.2022 |
|
|
-- |
-- |
Verify Window & Roof Structure (0) 04.25.2024 |
|
|
-- |
-- |
Install Stairs (0) 11.19.2022 |
|
|
-- |
-- |
Windows & Doors (0) 11.19.2022 |
|
|
-- |
-- |
House Number and Status in Window (0) 11.30.2022 |
|
|
-- |
-- |
Roofing (0) 11.19.2022 |
|
|
-- |
-- |
Order Cabinets (0) 11.22.2022 |
|
|
-- |
-- |
Order Appliances (0) 08.30.2022 |
French Upgrade |
|
-- |
-- |
Deck (0) 11.19.2022 |
Standard |
|
-- |
-- |
Gutters (0) 03.05.2023 |
|
|
-- |
-- |
Driveway (0) 02.08.2023 |
Standard |
|
-- |
-- |
Patio (0) 01.01.2023 |
Standard |
|
-- |
-- |
Privacy Divider / Fence (0) 02.08.2023 |
|
|
-- |
-- |
Sod / Seed / Landscaping (0) 02.18.2023 |
|
|
-- |
-- |
HVAC Rough In (4) 11.12.2022 |
In process 11/9 |
|
-- |
-- |
Inspection (Rough In HVAC) (1) 12.03.2022 |
|
|
-- |
-- |
Rough In Microwave Vent (0) 04.25.2024 |
|
|
-- |
-- |
Plumbing Rough In (4) 11.16.2022 |
In process11/12 |
|
-- |
-- |
Inspection (Rough In Plumbing) (1) 12.03.2022 |
11/17 |
|
-- |
-- |
Electric Rough In (4) 11.26.2022 |
|
|
-- |
-- |
Inspection (Rough In Electric) (1) 12.03.2022 |
|
|
-- |
-- |
Inspection (Deck Piers) (0) 02.13.2023 |
|
|
-- |
-- |
Inspection (Framing) (1) 12.03.2022 |
|
|
-- |
-- |
Exterior Vinyl (0) * 02.08.2023 |
|
|
-- |
-- |
Exterior Stone (0) 04.14.2022 |
|
|
-- |
-- |
Insulation (2) 12.03.2022 |
|
|
-- |
-- |
Inspection (Insulation) (1) 12.08.2022 |
|
|
-- |
-- |
Inspection (Electric Service) (0) 04.06.2023 |
|
|
-- |
-- |
Set Electric Meter (0) 04.20.2023 |
|
|
-- |
-- |
Inspection (Main Sewer Line) (0) 02.13.2023 |
|
|
-- |
-- |
Inspection (Main Water Line) (0) 02.13.2023 |
|
|
-- |
-- |
Order Interior Doors & Trim (0) 12.08.2022 |
|
|
-- |
-- |
Drywall (Hang) (4) * 12.10.2022 |
NONE |
|
-- |
-- |
Loan Approval (0) 03.05.2023 |
|
|
-- |
-- |
Deed Preparation (0) 03.05.2023 |
|
|
-- |
-- |
Drywall (Tape, Block, Skim, Sand) (6) * 01.04.2023 |
In process 1/1 |
|
-- |
-- |
Paint 1 (1) 01.04.2023 |
|
|
-- |
-- |
Garage Door (0) 02.22.2023 |
|
|
-- |
-- |
House Numbers (0) 03.01.2023 |
|
|
-- |
-- |
Mailbox (0) 02.20.2023 |
|
|
-- |
-- |
Cabinet Installation (2) * 01.07.2023 |
Jan 6 |
|
-- |
-- |
Granite Installation (1) * 01.28.2023 |
Jan 27 |
|
-- |
-- |
Interior Trim - Install (3) 01.21.2023 |
In process 1/18 |
|
-- |
-- |
Order Plumbing / Lighting Fixtures (0) 07.26.2023 |
|
|
-- |
-- |
Interior Trim - Paint (1) 01.21.2023 |
|
|
-- |
-- |
Luxury Vinyl Plank (3) * 02.04.2023 |
In process 2/4 |
|
-- |
-- |
Luxury Vinyl Tile (0) 02.04.2023 |
|
|
-- |
-- |
Paint 2 (3) 01.28.2023 |
In process 1/25 |
|
-- |
-- |
Cover Floors (1) 02.15.2023 |
Carpet |
|
-- |
-- |
Deliver Plumbing / Lighting Fixtures (0) 02.13.2023 |
|
|
-- |
-- |
Shoe Moulding (0) 02.15.2023 |
|
|
-- |
-- |
Shelving, Door Knobs, Fire Extinguisher (0) 02.22.2023 |
Black accessories |
|
-- |
-- |
Install Coded Lockbox (add extra keys) (0) 03.08.2023 |
|
|
-- |
-- |
Pay Water / Sewer Taps (0) 02.16.2023 |
|
|
-- |
-- |
Set Water Meter (0) 03.16.2023 |
|
|
-- |
-- |
Electric Trim Out (3) 02.15.2023 |
Black standard |
|
-- |
-- |
Ceiling Fans (0) 02.15.2023 |
|
|
-- |
-- |
HVAC Trim Out (1) 02.18.2023 |
|
|
-- |
-- |
Blower Door Test (1) 04.25.2024 |
|
|
-- |
-- |
Plumbing Trim Out (2) 02.15.2023 |
Farmhouse Plumbing Black. In process 2/11 |
|
-- |
-- |
Install Appliances (0) * 03.05.2023 |
Delivery 10/31- Schedule install with CJ |
|
-- |
-- |
Paint 3 (2) * 01.28.2023 |
|
|
-- |
-- |
Carpet (2) 02.08.2023 |
In process 2/4 |
|
-- |
-- |
Appraiser Confirms Construction Completion (0) 07.21.2023 |
|
|
-- |
-- |
Inspection (Final HVAC) (1) 04.22.2023 |
|
|
-- |
-- |
Inspection (Final Plumbing) (1) 04.22.2023 |
|
|
-- |
-- |
Inspection (Final Electric) (1) 04.22.2023 |
|
|
-- |
-- |
Inspection (Final Building) (2) * 04.22.2023 |
|
|
-- |
-- |
Pre Walk Through (0) 03.27.2023 |
|
|
-- |
-- |
Stain Hardwood Stairs (1) 02.25.2023 |
In process 2/18 |
|
-- |
-- |
Cleaning (1) 04.23.2023 |
|
|
-- |
-- |
Certificate of Occupancy (1) * 04.24.2023 |
|
|
-- |
-- |
C.O. to Lender (0) 04.24.2023 |
|
|
-- |
-- |
Schedule Closing (0) 07.13.2023 |
|
|
-- |
-- |
Buyer Walk Through (1) 04.26.2023 |
Monday, April 24, 2:00 PM |
|
-- |
-- |
Payment for Upgrades (0) 03.05.2023 |
|
|
-- |
-- |
Keys to Settlement Agent (0) 04.20.2023 |
|
|
-- |
-- |
Review Settlement Statement (0) 07.17.2023 |
|
|
-- |
-- |
Jerry Signs Closing Documents (0) 07.19.2023 |
|
|
-- |
-- |
Request Trash Tote From POA Manager (0) 04.20.2023 |
|
|
-- |
-- |
Closing (1) 07.21.2023 |
Brittany @ West View Title - likely July 20 |
|
-- |
-- |
Remove Coded Lockbox (0) 05.17.2023 |
|
|