1 28 33 37 45 46 47 48 71 52 70 69 67 53 54 55 56 59 58 57 66 65 64 60 61 62 63 ADDR
CONGERS-2 - 102  ::  1471 Palomino Trail
[ BUILD: 20221538 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
Fri    Sep 20      Verify Window & Roof Structure (0)      
Fri    Sep 20      Rough In Microwave Vent (0)      
Fri    Sep 20      Order Plumbing / Lighting Fixtures (0)      
Fri    Sep 20      Blower Door Test (1)      
--   --   Wants to pay for upgrades ahead of time
--   --   Crooked cripple stud under double window in master bedroom
--   --   Patio doors needed 103-100
--   --   Missing black handle kitchen cabinet
--   --   MB cabinet front panel looks odd 2/15
--   --   Peeling paint on garage wall
--   --   Holes in wall on landing between second and third floor
--   --   Missing master bathroom vanity handle Fred
--   --   Garage trim issue Davenport
--   --   Garage trim
--   --   Cover carpet
--   --   Microwave venting is behind drywall, right? tell Scott
--   --   Broken corner of kitchen window when viewed from outside Just the corner is broken. Got pics 3/22
--   --   Shower Walls Mast & Brunk
--   --   Garage trim needed Davenport
--   --   Drywall hole in ceiling Painter
--   --   Closing May 8?
--   --   Call needs patching and powder bath light
--   --   Hole needs patching in powder bath light Drywaller
--   --   Light switch cover needed in hall bath Electric
--   --   Black shower drain needed Plumber
--   --   Electric outlet needed on the back deck Electrician
--   --   Remote control attached to this fan as well Electrician
--   --   Outlets needed on the kitchen island Electrician
--   --   Drywall gap at switch plate cover in primary bathroom Painter?
--   --   There appears to be a patio screen, door track and 102 in the basement bonus room
--   --   CODED LOCKBOX 0102
--   --   Remove extra screens and patio doors Jill
--   --   Needs quite a bit of touchup painting Painter. In process 4/29
--   --   Remove extra cabinet items from living room Jill
--   --   Anchor dishwasher-is cj supposed to do this? CJ
--   --   Anchor dishwasher-is cj supposed to do this?
--   --   Repair hole in hall bathroom bathtub Repair guy scheduled for Monday 5-1-23
--   --   Lots of glue in hall shower
--   --   Cabinet nicks and scratches in kitchen perimeter cabinets
--   --   Empty garage Jill
--   --  
--   --   Missing weatherstripping at the front door
--   --   Push down door pins Jill
--   --   Extra filter needed Jill
--   --   Screen door latches is not working
--   --   Deadbolt and patio door of the bonus room not lined up
--   --   Replace white island outlets with gray Electrician
--   --   Missing bracket for top shelf in cabinet pantry Jill
--   --   Touch up paint In process 5/3
--   --   Install bottom part of dishwasher CJ/Tom
--   --   Change pendant bulbs to warm white Jill
--   --   missing weatherstripping at front door Jill
--   --   Push down door pins
--   --   Screen door latches not working Tom
--   --   Patio door lack out of line Joe
--   --   Replace White Island outlets to gray
--   --   Missing bracket in cabinet pantry for shelf Jill
--   --   Replace master closet door handle Joe
--   --   Replace attic access door Tom
--   --   Receptacle cover needed on garage ceiling Electrician
--   --   garage door not working Davenport
--   --   Left bottom corner kitchen exterior window ( builder discussion)
--   --   Adjust water pressure Jill
--   --   CODED LOCKBOX 1102
--   --   Water leak
--   --   Police Parking Only Sign
-- -- Ratified Contract? (0)  05.26.2022    
-- -- $2500 Deposit Received (0)  05.31.2022    
-- -- Association Packet Requested (0)  05.26.2022    
-- -- Association Packet Received (0)  06.03.2022    
-- -- Selections Meeting (0)  07.16.2022    
-- -- Selections Sheet Signed (0)  07.27.2022     7/16: sent to Carolyn for signatures
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  08.06.2022     7/27: sent to Carolyn
-- -- Deposit For Upgrades Received (0)  08.06.2022    
-- -- Building Permit (30)  08.15.2022    
-- -- Order Roof & Floor Trusses (1)  11.03.2022    
-- -- Order Windows & Doors (0)  11.03.2022    
-- -- Stake Out Home (1)  09.22.2022    
-- -- Excavate (2)  09.29.2022    
-- -- Inspection (Footers) (1)  09.29.2022    
-- -- Inspection (Concrete Wall) (1)  10.31.2022    
-- -- Pour Footers (1)  09.29.2022    
-- -- Set Forms (2)  10.31.2022    
-- -- Pour Foundation Walls (1)  10.31.2022    
-- -- Plumb Slab (2)  10.31.2022    
-- -- Inspection (Plumbing Under Slab) (1)  10.31.2022    
-- -- Inspection (Conduit Under Slab) (1)  10.31.2022    
-- -- Prepare Slab (1)  10.31.2022    
-- -- Inspection (Slab) (1)  10.31.2022    
-- -- Inspection (Drain Tile) (0)  10.10.2022    
-- -- Pour Slab (1)  11.03.2022    
-- -- Settlement Agent Confirmed (0)  03.20.2023    
-- -- Framing I (9)  11.17.2022    
-- -- Order Steps (0)  12.08.2022    
-- -- Order Tubs / Showers (0)  10.10.2022    
-- -- Framing II (8)  12.05.2022    
-- -- Framing III (8)  12.07.2022    
-- -- Install Stairs (0)  12.28.2022    
-- -- Windows & Doors (0)  12.28.2022    
-- -- House Number and Status in Window (0)  01.02.2023    
-- -- Roofing (0)  12.28.2022    
-- -- Order Cabinets (0)  12.30.2022    
-- -- Order Appliances (0)  08.30.2022     French Model Upgrade
-- -- Deck (0)  01.07.2023     Expanded 12 x 18 Deck
-- -- Gutters (0)  03.01.2023    
-- -- Driveway (0)  03.18.2023     Expanded Driveway
-- -- Patio (0)  02.25.2023     Standard
-- -- Privacy Divider / Fence (0)  03.05.2023    
-- -- Sod / Seed / Landscaping (0)  04.23.2023    
-- -- HVAC Rough In (4)  12.28.2022    
-- -- Inspection (Rough In HVAC) (1)  01.05.2023    
-- -- Plumbing Rough In (4)  01.04.2023     In process 1/1
-- -- Inspection (Rough In Plumbing) (1)  01.05.2023    
-- -- Electric Rough In (4)  01.14.2023     In process 1/11
-- -- Inspection (Rough In Electric) (1)  01.16.2023    
-- -- Inspection (Deck Piers) (0)  01.16.2023    
-- -- Inspection (Framing) (1)  01.16.2023    
-- -- Exterior Vinyl (0)  03.01.2023     in process 2/25
-- -- Exterior Stone (0)  03.20.2023    
-- -- Insulation (2)  01.18.2023    
-- -- Inspection (Insulation) (1)  01.26.2023    
-- -- Inspection (Electric Service) (0)  04.06.2023    
-- -- Set Electric Meter (0)  04.20.2023    
-- -- Inspection (Main Sewer Line) (0)  03.20.2023    
-- -- Inspection (Main Water Line) (0)  03.20.2023    
-- -- Order Interior Doors & Trim (0)  03.16.2023    
-- -- Drywall (Hang) (4)  01.28.2023     BONUS ROOM ONLY
-- -- Loan Approval (0)  07.03.2022    
-- -- Deed Preparation (0)  04.03.2023     send to Cheryl at Clark & Bradshaw
-- -- Drywall (Tape, Block, Skim, Sand) (6)  02.08.2023     In process 2/1. Be done Monday 2/5
-- -- Paint 1 (1)  02.08.2023    
-- -- Garage Door (0)  03.15.2023    
-- -- House Numbers (0)  04.05.2023    
-- -- Mailbox (0)  04.03.2023    
-- -- Cabinet Installation (2)  02.15.2023     Feb. 11
-- -- Granite Installation (1)  02.15.2023    
-- -- Interior Trim - Install (3)  03.01.2023     In process 2/25
-- -- Interior Trim - Paint (1)  03.05.2023    
-- -- Luxury Vinyl Plank (3)  03.18.2023     In process 3/15
-- -- Luxury Vinyl Tile (0)  03.18.2023    
-- -- Paint 2 (3)  03.08.2023    
-- -- Cover Floors (1)  04.01.2023    
-- -- Deliver Plumbing / Lighting Fixtures (0)  03.20.2023     Black lighting
-- -- Shoe Moulding (0)  03.25.2023    
-- -- Shelving, Door Knobs, Fire Extinguisher (0)  04.24.2023     In process 4/19
-- -- Install Coded Lockbox (add extra keys) (0)  04.20.2023    
-- -- Pay Water / Sewer Taps (0)  03.16.2023    
-- -- Set Water Meter (0)  05.01.2023    
-- -- Electric Trim Out (3)  04.05.2023     Black lighting
-- -- Ceiling Fans (0)  04.05.2023    
-- -- HVAC Trim Out (1)  03.22.2023    
-- -- Plumbing Trim Out (2)  04.01.2023     Black Plumbing. In process 3/25
-- -- Install Appliances (0)  04.19.2023     Delivery 10/31- Schedule install with CJ
-- -- Paint 3 (2)  03.22.2023    
-- -- Carpet (2)  03.18.2023    
-- -- Appraiser Confirms Construction Completion (0)  05.08.2023    
-- -- Inspection (Final HVAC) (1)  04.29.2023     Tue, Apr 25
-- -- Inspection (Final Plumbing) (1)  04.29.2023    
-- -- Inspection (Final Electric) (1)  04.29.2023    
-- -- Inspection (Final Building) (2)  04.29.2023    
-- -- Pre Walk Through (0)  04.29.2023    
-- -- Stain Hardwood Stairs (1)  04.23.2023     In process 3/29
-- -- Cleaning (1)  05.01.2023     In process 4/29
-- -- Certificate of Occupancy (1)  04.29.2023    
-- -- C.O. to Lender (0)  04.29.2023    
-- -- Schedule Closing (0)  05.08.2023    
-- -- Buyer Walk Through (1)  05.03.2023     Monday, May 1, 4:00 PM
-- -- Payment for Upgrades (0)  05.04.2023    
-- -- Keys to Settlement Agent (0)  05.01.2023    
-- -- Review Settlement Statement (0)  05.08.2023     Four deposits
-- -- Jerry Signs Closing Documents (0)  05.09.2023    
-- -- Request Trash Tote From POA Manager (0)  04.21.2023    
-- -- Closing (1)  05.09.2023     Cheryl Payne, Clark & Bradshaw
-- -- Remove Coded Lockbox (0)  05.08.2023