TO DO
---
UPGRADES
---
CRITICAL PATH
    Verify Window & Roof Structure (0)      
    Rough In Microwave Vent (0)      
    Order Plumbing / Lighting Fixtures (0)      
Tue    Feb 3      Blower Door Test (1)      
TO DO - COMPLETED OR DELETED
Wants to pay for upgrades ahead of time
Crooked cripple stud under double window in master bedroom
Patio doors needed 103-100
Missing black handle kitchen cabinet
MB cabinet front panel looks odd 2/15
Peeling paint on garage wall
Holes in wall on landing between second and third floor
Missing master bathroom vanity handle Fred
Garage trim issue Davenport
Garage trim
Cover carpet
Microwave venting is behind drywall, right? tell Scott
Broken corner of kitchen window when viewed from outside Just the corner is broken. Got pics 3/22
Shower Walls Mast & Brunk
Garage trim needed Davenport
Drywall hole in ceiling Painter
Closing May 8?
Call needs patching and powder bath light
Hole needs patching in powder bath light Drywaller
Light switch cover needed in hall bath Electric
Black shower drain needed Plumber
Electric outlet needed on the back deck Electrician
Remote control attached to this fan as well Electrician
Outlets needed on the kitchen island Electrician
Drywall gap at switch plate cover in primary bathroom Painter?
There appears to be a patio screen, door track and 102 in the basement bonus room
CODED LOCKBOX 0102
Remove extra screens and patio doors Jill
Needs quite a bit of touchup painting Painter. In process 4/29
Remove extra cabinet items from living room Jill
Anchor dishwasher-is cj supposed to do this? CJ
Anchor dishwasher-is cj supposed to do this?
Repair hole in hall bathroom bathtub Repair guy scheduled for Monday 5-1-23
Lots of glue in hall shower
Cabinet nicks and scratches in kitchen perimeter cabinets
Empty garage Jill
Missing weatherstripping at the front door
Push down door pins Jill
Extra filter needed Jill
Screen door latches is not working
Deadbolt and patio door of the bonus room not lined up
Replace white island outlets with gray Electrician
Missing bracket for top shelf in cabinet pantry Jill
Touch up paint In process 5/3
Install bottom part of dishwasher CJ/Tom
Change pendant bulbs to warm white Jill
missing weatherstripping at front door Jill
Push down door pins
Screen door latches not working Tom
Patio door lack out of line Joe
Replace White Island outlets to gray
Missing bracket in cabinet pantry for shelf Jill
Replace master closet door handle Joe
Replace attic access door Tom
Receptacle cover needed on garage ceiling Electrician
garage door not working Davenport
Left bottom corner kitchen exterior window ( builder discussion)
Adjust water pressure Jill
CODED LOCKBOX 1102
Water leak
Police Parking Only Sign
UPGRADES - COMPLETED
    Finish Bonus Room  
    Three drawer stack 36"  
    Three drawer stack island 24"  
    French Model Refrigerator  
    Painted Steps to bedroom level  
    Gray Subway Tile Shower walls  
    Shower Door with black Trim  
    LVP Bonus Room  
    8 lb pad Upstairs  
    12 x 18 Deck  
    Expanded Driveway  
    White Painted Kitchen Cabinetry  
    Microwave Vented to Exterior  
    Spice Rack  
    Amendment to increase price by $23,920  
CRITICAL PATH - COMPLETED
-- -- Ratified Contract? (0)  05.26.2022    
-- -- $2500 Deposit Received (0)  05.31.2022    
-- -- Association Packet Requested (0)  05.26.2022    
-- -- Association Packet Received (0)  06.03.2022    
-- -- Selections Meeting (0)  07.16.2022    
-- -- Selections Sheet Signed (0)  07.27.2022     7/16: sent to Carolyn for signatures
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  08.06.2022     7/27: sent to Carolyn
-- -- Deposit For Upgrades Received (0)  08.06.2022    
-- -- Building Permit (30) *   08.15.2022    
-- -- Order Roof & Floor Trusses (1)  11.03.2022    
-- -- Order Windows & Doors (0)  11.03.2022    
-- -- Stake Out Home (1)  09.22.2022    
-- -- Excavate (2)  09.29.2022    
-- -- Inspection (Footers) (1)  09.29.2022    
-- -- Inspection (Concrete Wall) (1)  10.31.2022    
-- -- Pour Footers (1) *   09.29.2022    
-- -- Set Forms (2)  10.31.2022    
-- -- Pour Foundation Walls (1)  10.31.2022    
-- -- Plumb Slab (2)  10.31.2022    
-- -- Inspection (Plumbing Under Slab) (1)  10.31.2022    
-- -- Inspection (Conduit Under Slab) (1)  10.31.2022    
-- -- Prepare Slab (1)  10.31.2022    
-- -- Inspection (Slab) (1)  10.31.2022    
-- -- Inspection (Drain Tile) (0)  10.10.2022    
-- -- Pour Slab (1) *   11.03.2022    
-- -- Settlement Agent Confirmed (0)  03.20.2023    
-- -- Framing I (9)  11.17.2022    
-- -- Order Steps (0)  12.08.2022    
-- -- Order Tubs / Showers (0)  10.10.2022    
-- -- Framing II (8)  12.05.2022    
-- -- Framing III (8) *   12.07.2022    
-- -- Install Stairs (0) *   12.28.2022    
-- -- Windows & Doors (0) *   12.28.2022    
-- -- House Number and Status in Window (0)  01.02.2023    
-- -- Roofing (0) *   12.28.2022    
-- -- Order Cabinets (0)  12.30.2022    
-- -- Order Appliances (0)  08.30.2022     French Model Upgrade
-- -- Deck (0)  01.07.2023     Expanded 12 x 18 Deck
-- -- Gutters (0)  03.01.2023    
-- -- Driveway (0) *   03.18.2023     Expanded Driveway
-- -- Patio (0)  02.25.2023     Standard
-- -- Privacy Divider / Fence (0) *   03.05.2023    
-- -- Sod / Seed / Landscaping (0)  04.23.2023    
-- -- HVAC Rough In (4)  12.28.2022    
-- -- Plumbing Rough In (4)  01.04.2023     In process 1/1
-- -- Electric Rough In (4)  01.14.2023     In process 1/11
-- -- Inspection (Rough In HVAC) (1)  01.05.2023    
-- -- Inspection (Rough In Plumbing) (1)  01.05.2023    
-- -- Inspection (Rough In Electric) (1)  01.16.2023    
-- -- Inspection (Framing) (1) *   01.16.2023    
-- -- Inspection (Deck Piers) (0)  01.16.2023    
-- -- Exterior Vinyl (0) *   03.01.2023     in process 2/25
-- -- Exterior Stone (0)  03.20.2023    
-- -- Insulation (2) *   01.18.2023    
-- -- Inspection (Insulation) (1)  01.26.2023    
-- -- Inspection (Electric Service) (0)  04.06.2023    
-- -- Set Electric Meter (0) *   04.20.2023    
-- -- Inspection (Main Sewer Line) (0)  03.20.2023    
-- -- Inspection (Main Water Line) (0)  03.20.2023    
-- -- Order Interior Doors & Trim (0)  03.16.2023    
-- -- Drywall (Hang) (4) *   01.28.2023     BONUS ROOM ONLY
-- -- Loan Approval (0)  07.03.2022    
-- -- Deed Preparation (0)  04.03.2023     send to Cheryl at Clark & Bradshaw
-- -- Drywall (Tape, Block, Skim, Sand) (6) *   02.08.2023     In process 2/1. Be done Monday 2/5
-- -- Paint 1 (1)  02.08.2023    
-- -- Garage Door (0)  03.15.2023    
-- -- House Numbers (0)  04.05.2023    
-- -- Mailbox (0)  04.03.2023    
-- -- Cabinet Installation (2) *   02.15.2023     Feb. 11
-- -- Granite Installation (1) *   02.15.2023    
-- -- Interior Trim - Install (3) *   03.01.2023     In process 2/25
-- -- Interior Trim - Paint (1)  03.05.2023    
-- -- Luxury Vinyl Plank (3) *   03.18.2023     In process 3/15
-- -- Luxury Vinyl Tile (0)  03.18.2023    
-- -- Paint 2 (3)  03.08.2023    
-- -- Cover Floors (0)  04.01.2023    
-- -- Deliver Plumbing / Lighting Fixtures (0)  03.20.2023     Black lighting
-- -- Shoe Moulding (0)  03.25.2023    
-- -- Shelving, Door Knobs, Fire Extinguisher (1) *   04.24.2023     In process 4/19
-- -- Install Coded Lockbox (add extra keys) (0)  04.20.2023    
-- -- Pay Water / Sewer Taps (0)  03.16.2023    
-- -- Set Water Meter (1) *   05.01.2023    
-- -- Electric Trim Out (3) *   04.05.2023     Black lighting
-- -- Ceiling Fans (0)  04.05.2023    
-- -- HVAC Trim Out (1) *   03.22.2023    
-- -- Plumbing Trim Out (2) *   04.01.2023     Black Plumbing. In process 3/25
-- -- Install Appliances (0) *   04.19.2023     Delivery 10/31- Schedule install with CJ
-- -- Paint 3 (2) *   03.22.2023    
-- -- Carpet (2)  03.18.2023    
-- -- Appraiser Confirms Construction Completion (0)  05.08.2023    
-- -- Inspection (Final HVAC) (0)  04.29.2023     Tue, Apr 25
-- -- Inspection (Final Plumbing) (0)  04.29.2023    
-- -- Inspection (Final Electric) (0)  04.29.2023    
-- -- Inspection (Final Building) (4) *   04.29.2023    
-- -- Pre Walk Through (0)  04.29.2023    
-- -- Stain Hardwood Stairs (1) *   04.23.2023     In process 3/29
-- -- Cleaning (1)  05.01.2023     In process 4/29
-- -- Certificate of Occupancy (1) *   04.29.2023    
-- -- C.O. to Lender (0)  04.29.2023    
-- -- Schedule Closing (0)  05.08.2023    
-- -- Buyer Walk Through (1) *   05.03.2023     Monday, May 1, 4:00 PM
-- -- Payment for Upgrades (0)  05.04.2023    
-- -- Keys to Settlement Agent (0)  05.01.2023    
-- -- Review Settlement Statement (0)  05.08.2023     Four deposits
-- -- Jerry Signs Closing Documents (0)  05.09.2023    
-- -- Request Trash Tote From POA Manager (0)  04.21.2023    
-- -- Closing (1)  05.09.2023     Cheryl Payne, Clark & Bradshaw
-- -- Remove Coded Lockbox (0)  05.08.2023