| TO DO | ||||
| --- | ||||
| UPGRADES | ||||
| --- | ||||
| CRITICAL PATH | ||||
| --- | ||||
| TO DO - COMPLETED OR DELETED | ||||
| UPGRADES - COMPLETED | ||||
| Finish Bonus Room | ||||
| Three drawer stack 36" | ||||
| Three drawer stack island 24" | ||||
| French Model Refrigerator | ||||
| Painted Steps to bedroom level | ||||
| Gray Subway Tile Shower walls | ||||
| Shower Door with black Trim | ||||
| LVP Bonus Room | ||||
| 8 lb pad Upstairs | ||||
| 12 x 18 Deck | ||||
| Expanded Driveway | ||||
| White Painted Kitchen Cabinetry | ||||
| Microwave Vented to Exterior | ||||
| Spice Rack | ||||
| Amendment to increase price by $23,920 | ||||
| CRITICAL PATH - COMPLETED | ||||
| -- | -- | Inspection (Footers) (1) 09.29.2022 | ||
| -- | -- | Inspection (Concrete Wall) (1) 10.31.2022 | ||
| -- | -- | Inspection (Plumbing Under Slab) (1) 10.31.2022 | ||
| -- | -- | Inspection (Conduit Under Slab) (1) 10.31.2022 | ||
| -- | -- | Inspection (Slab) (1) 10.31.2022 | ||
| -- | -- | Inspection (Drain Tile) (0) 10.10.2022 | ||
| -- | -- | Inspection (Rough In HVAC) (1) 01.05.2023 | ||
| -- | -- | Inspection (Rough In Plumbing) (1) 01.05.2023 | ||
| -- | -- | Inspection (Rough In Electric) (1) 01.16.2023 | ||
| -- | -- | Inspection (Framing) (1) * 01.16.2023 | ||
| -- | -- | Inspection (Deck Piers) (0) 01.16.2023 | ||
| -- | -- | Inspection (Insulation) (1) 01.26.2023 | ||
| -- | -- | Inspection (Electric Service) (0) 04.06.2023 | ||
| -- | -- | Inspection (Main Sewer Line) (0) 03.20.2023 | ||
| -- | -- | Inspection (Main Water Line) (0) 03.20.2023 | ||
| -- | -- | Inspection (Final HVAC) (0) 04.29.2023 | Tue, Apr 25 | |
| -- | -- | Inspection (Final Plumbing) (0) 04.29.2023 | ||
| -- | -- | Inspection (Final Electric) (0) 04.29.2023 | ||
| -- | -- | Inspection (Final Building) (4) * 04.29.2023 | ||