| TO DO | ||||
| --- | ||||
| UPGRADES | ||||
| --- | ||||
| CRITICAL PATH | ||||
| --- | ||||
| TO DO - COMPLETED OR DELETED | ||||
| UPGRADES - COMPLETED | ||||
| White Kitchen Cabinetry | ||||
| Level III Quartz Countertop in Kitchen | ||||
| Farmhouse Sink | ||||
| Three Drawer Stack Kitchen | ||||
| White Bath vanity- up hallway only | ||||
| Painted Steps to bedroom level | ||||
| 12 x 18 Deck | ||||
| Digital Deadbolt, front door | ||||
| Ship Lap Living Room Wall | ||||
| Expanded Driveway | ||||
| Microwave Vented to Exterior | ||||
| LVP in up hallway and landing | ||||
| CRITICAL PATH - COMPLETED | ||||
| -- | -- | Inspection (Footers) (1) 09.29.2022 | ||
| -- | -- | Inspection (Concrete Wall) (1) 10.31.2022 | ||
| -- | -- | Inspection (Plumbing Under Slab) (1) 10.31.2022 | ||
| -- | -- | Inspection (Conduit Under Slab) (1) 10.31.2022 | ||
| -- | -- | Inspection (Slab) (1) 10.31.2022 | ||
| -- | -- | Inspection (Drain Tile) (0) 10.10.2022 | ||
| -- | -- | Inspection (Rough In HVAC) (1) 01.05.2023 | ||
| -- | -- | Inspection (Rough In Plumbing) (1) 01.05.2023 | ||
| -- | -- | Inspection (Rough In Electric) (1) 01.12.2023 | ||
| -- | -- | Inspection (Framing) (1) * 01.12.2023 | ||
| -- | -- | Inspection (Deck Piers) (0) 03.16.2023 | ||
| -- | -- | Inspection (Insulation) (1) 01.16.2023 | ||
| -- | -- | Inspection (Electric Service) (0) 04.06.2023 | ||
| -- | -- | Inspection (Main Sewer Line) (0) 03.20.2023 | ||
| -- | -- | Inspection (Main Water Line) (0) 03.20.2023 | ||
| -- | -- | Inspection (Final HVAC) (0) 04.26.2023 | Tue, Apr 25 | |
| -- | -- | Inspection (Final Plumbing) (0) 04.26.2023 | ||
| -- | -- | Inspection (Final Electric) (0) 04.26.2023 | ||
| -- | -- | Inspection (Final Building) (4) * 04.26.2023 | ||