| TO DO | ||||
| --- | ||||
| UPGRADES | ||||
| --- | ||||
| CRITICAL PATH | ||||
| --- | ||||
| TO DO - COMPLETED OR DELETED | ||||
| UPGRADES - COMPLETED | ||||
| Expanded Driveway | ||||
| Expanded Patio 10 x 18 | ||||
| Garage Door Keypad | ||||
| 8 lb carpet pad | ||||
| Shower Door with black Trim | ||||
| Window in basement | ||||
| Ceiling Fan in Living Room | ||||
| Three Drawer Stack | ||||
| Amendment to increase price by $6,620 | ||||
| CRITICAL PATH - COMPLETED | ||||
| -- | -- | Inspection (Footers) (1) 10.09.2022 | ||
| -- | -- | Inspection (Concrete Wall) (1) 10.09.2022 | ||
| -- | -- | Inspection (Plumbing Under Slab) (1) 12.05.2022 | ||
| -- | -- | Inspection (Conduit Under Slab) (1) 12.08.2022 | ||
| -- | -- | Inspection (Slab) (1) 12.27.2022 | ||
| -- | -- | Inspection (Drain Tile) (0) 12.27.2022 | ||
| -- | -- | Inspection (Rough In HVAC) (1) 02.27.2023 | ||
| -- | -- | Inspection (Rough In Plumbing) (1) 02.27.2023 | ||
| -- | -- | Inspection (Rough In Electric) (1) 02.27.2023 | ||
| -- | -- | Inspection (Framing) (1) * 02.27.2023 | ||
| -- | -- | Inspection (Deck Piers) (0) 02.27.2023 | ||
| -- | -- | Inspection (Insulation) (1) 03.06.2023 | ||
| -- | -- | Inspection (Electric Service) (0) 06.12.2023 | Fri, June 2 | |
| -- | -- | Inspection (Main Sewer Line) (0) 03.20.2023 | ||
| -- | -- | Inspection (Main Water Line) (0) 03.20.2023 | ||
| -- | -- | Inspection (Final HVAC) (0) 06.26.2023 | ||
| -- | -- | Inspection (Final Plumbing) (0) 06.26.2023 | ||
| -- | -- | Inspection (Final Electric) (0) 06.26.2023 | ||
| -- | -- | Inspection (Final Building) (4) * 06.29.2023 | Reinspect Tuesday June 27 | |