1 33 37 89 47 73 67 55 56 59 57 66 65 64 60 61 62 63 ADDR
CONGERS-2 - 30  ::  1476 Palomino Trail
[ BUILD: 20221532 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
Thu    Nov 28      Verify Window & Roof Structure (0)      
Thu    Nov 28      Rough In Microwave Vent (0)      
Thu    Nov 28      Order Plumbing / Lighting Fixtures (0)      
Thu    Nov 28      Blower Door Test (1)      
--   --   Pile of insulation in master bedroom-ok to inspect?
--   --   This garage back wall has a bump out. Does it matter?
--   --   Master bath plumbing repair
--   --   Appliances delivered April 19
--   --   Missing nickel hardware on master vanity Jill
--   --   Drywall finishing needed on edge of banister to main level Needs sanding 5/17
--   --   Odd line on banister railing
--   --   Would like to close by June 7
--   --   Trim needed side of kitchen island Tom
--   --   Add trim on main level banister after drywall repairs completed
--   --   Trim needed around basement window Exterior, Jeremy, Davenport
--   --   Remove all black light fixtures that are supposed to be nickel
--   --   Do not install toilet paper, hand towel or bath towel holders Leave them sitting in the bathrooms
--   --   Needs dining chandelier Electrician
--   --   Let cover laundry room needed Electrician
--   --   Scratch on fridge-can we touch up 6/19 - CJ will try the other color of touch up paint
--   --   Missing dining chandelier, and electric cover in master bath Electrician
--   --   Leave bathroom accessories in bathroom
--   --   All electric covers need installed after touch up paint Electrician
--   --   Lots of paint on upstairs flooring. Perhaps painters can clean up large spots? Painter
--   --   CODED LOCKBOX 3030
--   --   Cover extra outlets installed by buyer
--   --   Garage needs trim
--   --   Needs silver tub drain Plumber
--   --   screen door to patio is wonkie Tom
--   --   one of the shelves in the fridge has a scratch on the bottom 6/19 - Leisa will order a replacement shelf
--   --   paint around the electrical panel in garage Painter
--   --   the closet on the 1st level has a place that the painters missed Painter
--   --   paint touch ups needed on the 1st stairwell Painter
--   --   caulk both sides of the farmhouse sink Painter or Fred (Tom will look at it)
--   --   is the spice rack supposed to be soft close like the other cabinets in the kitchen??
--   --   try to touch up the side of fridge where the tape pulled the paint off Jill will custom mix appliance repair paint
--   --   touch up 2 of the cabinets in the kitchen Fred to order one (bottom pantry), Jill to touch up other
--   --   push attic access panel down into place Jill
--   --   sand place on the wall below the mirror in the master bathroom Painter
--   --   caulk around the vent in the wall at the top of the second set of stairs. Painter
--   --   touch up the paint in the bedroom closet (left room) Painter
--   --   the piece of rubber/foam along the bottom of the garage door is messed up, it seems to be flat on one end of it. Davenport, Jeremy
--   --   Two chips in the countertop in the kitchen Greg. One repair made-coming back for more repairs 7/6
--   --  
--   --   trim moulding at sides of farmhouse sink Fred
--   --   Replace kitchen drawer that is damaged above trash can Fred
--   --   Replace door panel with damage Fred
-- -- Ratified Contract? (0)  10.07.2022    
-- -- $2500 Deposit Received (0)  10.12.2022    
-- -- Association Packet Requested (0)  10.07.2022    
-- -- Association Packet Received (0)  10.08.2022    
-- -- Selections Meeting (0)  12.30.2022    
-- -- Selections Sheet Signed (0)  02.03.2023     Sent to Brad on 12/30/2022
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  02.11.2023     2/11: sent to Jerry for signature
-- -- Deposit For Upgrades Received (0)  02.11.2023    
-- -- Building Permit (30)  08.15.2022    
-- -- Order Roof & Floor Trusses (1)  11.03.2022    
-- -- Order Windows & Doors (0)  11.03.2022    
-- -- Stake Out Home (1)  09.26.2022    
-- -- Excavate (2)  09.29.2022    
-- -- Inspection (Footers) (1)  10.09.2022    
-- -- Inspection (Concrete Wall) (1)  10.09.2022    
-- -- Pour Footers (1)  10.09.2022    
-- -- Set Forms (2)  10.31.2022    
-- -- Pour Foundation Walls (1)  11.03.2022    
-- -- Plumb Slab (2)  12.01.2022    
-- -- Inspection (Plumbing Under Slab) (1)  12.05.2022    
-- -- Inspection (Conduit Under Slab) (1)  12.08.2022    
-- -- Prepare Slab (1)  12.08.2022    
-- -- Inspection (Slab) (1)  12.27.2022    
-- -- Inspection (Drain Tile) (0)  12.27.2022    
-- -- Pour Slab (1) *   12.27.2022    
-- -- Settlement Agent Confirmed (0)  05.16.2023    
-- -- Framing I (9)  01.05.2023    
-- -- Order Steps (0)  02.02.2023    
-- -- Order Tubs / Showers (0)  02.20.2023    
-- -- Framing II (8)  01.12.2023    
-- -- Framing III (8) *   01.31.2023    
-- -- Install Stairs (0)  02.02.2023    
-- -- Windows & Doors (0)  02.18.2023    
-- -- House Number and Status in Window (0)  02.22.2023    
-- -- Roofing (0)  02.20.2023    
-- -- Order Cabinets (0)  03.02.2023    
-- -- Order Appliances (0)  05.22.2023     French Upgrade
-- -- Deck (0)  02.23.2023    
-- -- Gutters (0)  04.03.2023    
-- -- Driveway (0)  04.26.2023    
-- -- Patio (0)  03.15.2023    
-- -- Privacy Divider / Fence (0)  06.11.2023    
-- -- Sod / Seed / Landscaping (0)  07.20.2023    
-- -- HVAC Rough In (4)  02.22.2023     In process 2/18
-- -- Inspection (Rough In HVAC) (1)  03.15.2023    
-- -- Plumbing Rough In (4)  02.22.2023     In process 2/18
-- -- Inspection (Rough In Plumbing) (1)  03.15.2023    
-- -- Electric Rough In (4)  03.05.2023    
-- -- Inspection (Rough In Electric) (1)  03.15.2023    
-- -- Inspection (Deck Piers) (0)  05.18.2023    
-- -- Inspection (Framing) (1)  03.15.2023    
-- -- Exterior Vinyl (0) *   04.10.2023    
-- -- Exterior Stone (0)  05.18.2023     In process 4/29
-- -- Insulation (2)  03.15.2023    
-- -- Inspection (Insulation) (1)  03.16.2023    
-- -- Inspection (Electric Service) (0)  06.12.2023    
-- -- Set Electric Meter (0)  06.14.2023    
-- -- Inspection (Main Sewer Line) (0)  03.20.2023    
-- -- Inspection (Main Water Line) (0)  03.20.2023    
-- -- Order Interior Doors & Trim (0)  04.12.2023    
-- -- Drywall (Hang) (4) *   03.25.2023     Stocked 3/18
-- -- Loan Approval (0)  05.25.2023    
-- -- Deed Preparation (0)  06.01.2023    
-- -- Drywall (Tape, Block, Skim, Sand) (6) *   04.10.2023     In process 3/29
-- -- Paint 1 (1)  04.10.2023    
-- -- Garage Door (0)  04.23.2023    
-- -- House Numbers (0)  05.06.2023    
-- -- Mailbox (0)  05.20.2023    
-- -- Cabinet Installation (2) *   04.10.2023     Wed, Apr 5. In process 4/5 drywall doesn’t appear finished…
-- -- Granite Installation (1) *   05.03.2023    
-- -- Interior Trim - Install (3)  05.06.2023     In process 5/3
-- -- Interior Trim - Paint (1)  05.06.2023    
-- -- Luxury Vinyl Plank (3) *   05.13.2023     In process 5/10
-- -- Luxury Vinyl Tile (0)  05.13.2023    
-- -- Paint 2 (3)  04.23.2023     In process 4/19
-- -- Cover Floors (1)  05.28.2023    
-- -- Deliver Plumbing / Lighting Fixtures (0)  04.27.2023     BN Standard
-- -- Shoe Moulding (0)  05.20.2023    
-- -- Shelving, Door Knobs, Fire Extinguisher (0)  06.03.2023     BN Accessories, in process 5/31
-- -- Install Coded Lockbox (add extra keys) (0)  06.12.2023    
-- -- Pay Water / Sewer Taps (0)  05.01.2023    
-- -- Set Water Meter (0)  05.11.2023    
-- -- Electric Trim Out (3)  05.31.2023     BN Standard. In process 5/28
-- -- Ceiling Fans (0)  05.28.2023    
-- -- HVAC Trim Out (1)  06.11.2023     Needs hvac covers
-- -- Plumbing Trim Out (2)  05.20.2023     In process 5/17
-- -- Install Appliances (0) *   06.03.2023     French Delivery 5/11
-- -- Paint 3 (2) *   05.17.2023    
-- -- Carpet (2)  05.20.2023    
-- -- Appraiser Confirms Construction Completion (0)  06.21.2023     Jeff Eye
-- -- Inspection (Final HVAC) (1)  06.16.2023    
-- -- Inspection (Final Plumbing) (1)  06.16.2023    
-- -- Inspection (Final Electric) (1)  06.16.2023    
-- -- Inspection (Final Building) (2) *   06.16.2023    
-- -- Pre Walk Through (0)  06.19.2023    
-- -- Stain Hardwood Stairs (1)  06.03.2023     In process 5/28
-- -- Cleaning (1)  06.21.2023    
-- -- Certificate of Occupancy (1) *   06.20.2023    
-- -- C.O. to Lender (0)  06.20.2023    
-- -- Schedule Closing (0)  06.21.2023    
-- -- Buyer Walk Through (1)  06.19.2023    
-- -- Payment for Upgrades (0)  06.19.2023    
-- -- Keys to Settlement Agent (0)  06.21.2023    
-- -- Review Settlement Statement (0)  06.22.2023    
-- -- Jerry Signs Closing Documents (0)  06.23.2023    
-- -- Request Trash Tote From POA Manager (0)  06.22.2023    
-- -- Closing (1)  06.26.2023     Cheryl Payne, Clark & Bradshaw
-- -- Remove Coded Lockbox (0)  07.10.2023