CONGERS-2 - 30  ::  1476 Palomino Trail
[ BUILD: 20221532 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
Tue    Jul 1      Verify Window & Roof Structure (0)      
Tue    Jul 1      Rough In Microwave Vent (0)      
Tue    Jul 1      Order Plumbing / Lighting Fixtures (0)      
Tue    Jul 1      Blower Door Test (1)      
--   --   Pile of insulation in master bedroom-ok to inspect?
--   --   This garage back wall has a bump out. Does it matter?
--   --   Master bath plumbing repair
--   --   Appliances delivered April 19
--   --   Missing nickel hardware on master vanity Jill
--   --   Drywall finishing needed on edge of banister to main level Needs sanding 5/17
--   --   Odd line on banister railing
--   --   Would like to close by June 7
--   --   Trim needed side of kitchen island Tom
--   --   Add trim on main level banister after drywall repairs completed
--   --   Trim needed around basement window Exterior, Jeremy, Davenport
--   --   Remove all black light fixtures that are supposed to be nickel
--   --   Do not install toilet paper, hand towel or bath towel holders Leave them sitting in the bathrooms
--   --   Needs dining chandelier Electrician
--   --   Let cover laundry room needed Electrician
--   --   Scratch on fridge-can we touch up 6/19 - CJ will try the other color of touch up paint
--   --   Missing dining chandelier, and electric cover in master bath Electrician
--   --   Leave bathroom accessories in bathroom
--   --   All electric covers need installed after touch up paint Electrician
--   --   Lots of paint on upstairs flooring. Perhaps painters can clean up large spots? Painter
--   --   CODED LOCKBOX 3030
--   --   Cover extra outlets installed by buyer
--   --   Garage needs trim
--   --   Needs silver tub drain Plumber
--   --   screen door to patio is wonkie Tom
--   --   one of the shelves in the fridge has a scratch on the bottom 6/19 - Leisa will order a replacement shelf
--   --   paint around the electrical panel in garage Painter
--   --   the closet on the 1st level has a place that the painters missed Painter
--   --   paint touch ups needed on the 1st stairwell Painter
--   --   caulk both sides of the farmhouse sink Painter or Fred (Tom will look at it)
--   --   is the spice rack supposed to be soft close like the other cabinets in the kitchen??
--   --   try to touch up the side of fridge where the tape pulled the paint off Jill will custom mix appliance repair paint
--   --   touch up 2 of the cabinets in the kitchen Fred to order one (bottom pantry), Jill to touch up other
--   --   push attic access panel down into place Jill
--   --   sand place on the wall below the mirror in the master bathroom Painter
--   --   caulk around the vent in the wall at the top of the second set of stairs. Painter
--   --   touch up the paint in the bedroom closet (left room) Painter
--   --   the piece of rubber/foam along the bottom of the garage door is messed up, it seems to be flat on one end of it. Davenport, Jeremy
--   --   Two chips in the countertop in the kitchen Greg. One repair made-coming back for more repairs 7/6
--   --  
--   --   trim moulding at sides of farmhouse sink Fred
--   --   Replace kitchen drawer that is damaged above trash can Fred
--   --   Replace door panel with damage Fred
-- -- Ratified Contract? (0)  10.07.2022    
    Oak treads to bedroom level  
    Delete- master bath pantry nook wall (outlet on alternate wall TBD)  
    Bonus Room Egress Window  
    Amendment to increase price by $17,825  
-- -- $2500 Deposit Received (0)  10.12.2022    
-- -- Association Packet Requested (0)  10.07.2022    
-- -- Association Packet Received (0)  10.08.2022    
-- -- Selections Meeting (0)  12.30.2022    
-- -- Selections Sheet Signed (0)  02.03.2023     Sent to Brad on 12/30/2022
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  02.11.2023     2/11: sent to Jerry for signature
-- -- Deposit For Upgrades Received (0)  02.11.2023    
-- -- Building Permit (30)  08.15.2022    
-- -- Order Roof & Floor Trusses (1)  11.03.2022    
-- -- Order Windows & Doors (0)  11.03.2022    
-- -- Stake Out Home (1)  09.26.2022    
-- -- Excavate (2)  09.29.2022    
-- -- Inspection (Footers) (1)  10.09.2022    
-- -- Inspection (Concrete Wall) (1)  10.09.2022    
-- -- Pour Footers (1) *   10.09.2022    
-- -- Set Forms (2)  10.31.2022    
-- -- Pour Foundation Walls (1)  11.03.2022    
-- -- Plumb Slab (2)  12.01.2022    
-- -- Inspection (Plumbing Under Slab) (1)  12.05.2022    
-- -- Inspection (Conduit Under Slab) (1)  12.08.2022    
-- -- Prepare Slab (1)  12.08.2022    
-- -- Inspection (Slab) (1)  12.27.2022    
-- -- Inspection (Drain Tile) (0)  12.27.2022    
-- -- Pour Slab (1) *   12.27.2022    
-- -- Settlement Agent Confirmed (0)  05.16.2023    
-- -- Framing I (9)  01.05.2023    
-- -- Order Steps (0)  02.02.2023    
-- -- Order Tubs / Showers (0)  02.20.2023    
-- -- Framing II (8)  01.12.2023    
-- -- Framing III (8) *   01.31.2023    
-- -- Install Stairs (0)  02.02.2023    
-- -- Windows & Doors (0) *   02.18.2023    
-- -- House Number and Status in Window (0)  02.22.2023    
-- -- Roofing (0) *   02.20.2023    
-- -- Order Cabinets (0)  03.02.2023    
-- -- Order Appliances (0)  05.22.2023     French Upgrade
-- -- Deck (0)  02.23.2023    
-- -- Gutters (0)  04.03.2023    
-- -- Driveway (0) *   04.26.2023    
    Expanded driveway  
-- -- Patio (0)  03.15.2023    
    Expanding patio 10 x 18  
-- -- Privacy Divider / Fence (0)  06.11.2023    
-- -- Sod / Seed / Landscaping (0)  07.20.2023    
-- -- HVAC Rough In (4)  02.22.2023     In process 2/18
-- -- Inspection (Rough In HVAC) (1)  03.15.2023    
-- -- Plumbing Rough In (4)  02.22.2023     In process 2/18
-- -- Inspection (Rough In Plumbing) (1)  03.15.2023    
-- -- Electric Rough In (4)  03.05.2023    
-- -- Inspection (Rough In Electric) (1)  03.15.2023    
-- -- Inspection (Deck Piers) (0)  05.18.2023    
-- -- Inspection (Framing) (1) *   03.15.2023    
-- -- Exterior Vinyl (0) *   04.10.2023    
-- -- Exterior Stone (0)  05.18.2023     In process 4/29
-- -- Insulation (2) *   03.15.2023    
-- -- Inspection (Insulation) (1)  03.16.2023    
-- -- Inspection (Electric Service) (0)  06.12.2023    
-- -- Set Electric Meter (0) *   06.14.2023    
-- -- Inspection (Main Sewer Line) (0)  03.20.2023    
-- -- Inspection (Main Water Line) (0)  03.20.2023    
-- -- Order Interior Doors & Trim (0)  04.12.2023    
-- -- Drywall (Hang) (4) *   03.25.2023     Stocked 3/18
-- -- Loan Approval (0)  05.25.2023    
-- -- Deed Preparation (0)  06.01.2023    
-- -- Drywall (Tape, Block, Skim, Sand) (6) *   04.10.2023     In process 3/29
-- -- Paint 1 (1)  04.10.2023    
-- -- Garage Door (0) *   04.23.2023    
-- -- House Numbers (0)  05.06.2023    
-- -- Mailbox (0)  05.20.2023    
-- -- Cabinet Installation (2) *   04.10.2023     Wed, Apr 5. In process 4/5 drywall doesn’t appear finished…
    White kitchen cabinets  
    Five piece drawer front  
    Drawer stacks in base 36 and Island  
    Double pull out trashcan  
    Roll out trays and base 36 and pantry  
    White bathroom cabinetry  
    Master vanity - [2] VSD3035  
    White fire clay farmhouse sink  
    Spice Rack in Base 9  
-- -- Granite Installation (1) *   05.03.2023    
    Level 3 Quartz kitchen countertops  
-- -- Interior Trim - Install (3) *   05.06.2023     In process 5/3
-- -- Interior Trim - Paint (1)  05.06.2023    
-- -- Luxury Vinyl Plank (3) *   05.13.2023     In process 5/10
    Luxury vinyl plank on bedroom level  
-- -- Luxury Vinyl Tile (0)  05.13.2023    
-- -- Paint 2 (3)  04.23.2023     In process 4/19
-- -- Cover Floors (1)  05.28.2023    
-- -- Deliver Plumbing / Lighting Fixtures (0)  04.27.2023     BN Standard
-- -- Shoe Moulding (0)  05.20.2023    
-- -- Shelving, Door Knobs, Fire Extinguisher (0) *   06.03.2023     BN Accessories, in process 5/31
-- -- Install Coded Lockbox (add extra keys) (0)  06.12.2023    
-- -- Pay Water / Sewer Taps (0)  05.01.2023    
-- -- Set Water Meter (0) *   05.11.2023    
-- -- Electric Trim Out (3)  05.31.2023     BN Standard. In process 5/28
-- -- Ceiling Fans (0)  05.28.2023    
-- -- HVAC Trim Out (1)  06.11.2023     Needs hvac covers
-- -- Plumbing Trim Out (2)  05.20.2023     In process 5/17
-- -- Install Appliances (0) *   06.03.2023     French Delivery 5/11
    French model refrigerator  
-- -- Paint 3 (2) *   05.17.2023    
-- -- Carpet (2)  05.20.2023    
-- -- Appraiser Confirms Construction Completion (0)  06.21.2023     Jeff Eye
-- -- Inspection (Final HVAC) (1)  06.16.2023    
-- -- Inspection (Final Plumbing) (1)  06.16.2023    
-- -- Inspection (Final Electric) (1)  06.16.2023    
-- -- Inspection (Final Building) (2) *   06.16.2023    
-- -- Pre Walk Through (0)  06.19.2023    
-- -- Stain Hardwood Stairs (1)  06.03.2023     In process 5/28
-- -- Cleaning (1)  06.21.2023    
-- -- Certificate of Occupancy (1) *   06.20.2023    
-- -- C.O. to Lender (0)  06.20.2023    
-- -- Schedule Closing (0)  06.21.2023    
-- -- Buyer Walk Through (1)  06.19.2023    
-- -- Payment for Upgrades (0)  06.19.2023    
-- -- Keys to Settlement Agent (0)  06.21.2023    
-- -- Review Settlement Statement (0)  06.22.2023    
-- -- Jerry Signs Closing Documents (0)  06.23.2023    
-- -- Request Trash Tote From POA Manager (0)  06.22.2023    
-- -- Closing (1)  06.26.2023     Cheryl Payne, Clark & Bradshaw
-- -- Remove Coded Lockbox (0)  07.10.2023