37 ADDR
CONGERS-2 - 30  ::  1476 Palomino Trail
[ BUILD: 20221532 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
TO DO
---
UPGRADES
---
CRITICAL PATH
    Verify Window & Roof Structure (0)      
    Rough In Microwave Vent (0)      
    Order Plumbing / Lighting Fixtures (0)      
Tue    Feb 3      Blower Door Test (1)      
TO DO - COMPLETED OR DELETED
Pile of insulation in master bedroom-ok to inspect?
This garage back wall has a bump out. Does it matter?
Master bath plumbing repair
Appliances delivered April 19
Missing nickel hardware on master vanity Jill
Drywall finishing needed on edge of banister to main level Needs sanding 5/17
Odd line on banister railing
Would like to close by June 7
Trim needed side of kitchen island Tom
Add trim on main level banister after drywall repairs completed
Trim needed around basement window Exterior, Jeremy, Davenport
Remove all black light fixtures that are supposed to be nickel
Do not install toilet paper, hand towel or bath towel holders Leave them sitting in the bathrooms
Needs dining chandelier Electrician
Let cover laundry room needed Electrician
Scratch on fridge-can we touch up 6/19 - CJ will try the other color of touch up paint
Missing dining chandelier, and electric cover in master bath Electrician
Leave bathroom accessories in bathroom
All electric covers need installed after touch up paint Electrician
Lots of paint on upstairs flooring. Perhaps painters can clean up large spots? Painter
CODED LOCKBOX 3030
Cover extra outlets installed by buyer
Garage needs trim
Needs silver tub drain Plumber
screen door to patio is wonkie Tom
one of the shelves in the fridge has a scratch on the bottom 6/19 - Leisa will order a replacement shelf
paint around the electrical panel in garage Painter
the closet on the 1st level has a place that the painters missed Painter
paint touch ups needed on the 1st stairwell Painter
caulk both sides of the farmhouse sink Painter or Fred (Tom will look at it)
is the spice rack supposed to be soft close like the other cabinets in the kitchen??
try to touch up the side of fridge where the tape pulled the paint off Jill will custom mix appliance repair paint
touch up 2 of the cabinets in the kitchen Fred to order one (bottom pantry), Jill to touch up other
push attic access panel down into place Jill
sand place on the wall below the mirror in the master bathroom Painter
caulk around the vent in the wall at the top of the second set of stairs. Painter
touch up the paint in the bedroom closet (left room) Painter
the piece of rubber/foam along the bottom of the garage door is messed up, it seems to be flat on one end of it. Davenport, Jeremy
Two chips in the countertop in the kitchen Greg. One repair made-coming back for more repairs 7/6
trim moulding at sides of farmhouse sink Fred
Replace kitchen drawer that is damaged above trash can Fred
Replace door panel with damage Fred
UPGRADES - COMPLETED
    White kitchen cabinets  
    Five piece drawer front  
    Drawer stacks in base 36 and Island  
    Double pull out trashcan  
    Roll out trays and base 36 and pantry  
    White bathroom cabinetry  
    Master vanity - [2] VSD3035  
    French model refrigerator  
    White fire clay farmhouse sink  
    Level 3 Quartz kitchen countertops  
    Oak treads to bedroom level  
    Luxury vinyl plank on bedroom level  
    Expanding patio 10 x 18  
    Expanded driveway  
    Delete- master bath pantry nook wall (outlet on alternate wall TBD)  
    Spice Rack in Base 9  
    Bonus Room Egress Window  
    Amendment to increase price by $17,825  
CRITICAL PATH - COMPLETED
-- -- Ratified Contract? (0)  10.07.2022    
-- -- $2500 Deposit Received (0)  10.12.2022    
-- -- Association Packet Requested (0)  10.07.2022    
-- -- Association Packet Received (0)  10.08.2022    
-- -- Selections Meeting (0)  12.30.2022    
-- -- Selections Sheet Signed (0)  02.03.2023     Sent to Brad on 12/30/2022
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  02.11.2023     2/11: sent to Jerry for signature
-- -- Deposit For Upgrades Received (0)  02.11.2023    
-- -- Building Permit (30) *   08.15.2022    
-- -- Order Roof & Floor Trusses (1)  11.03.2022    
-- -- Order Windows & Doors (0)  11.03.2022    
-- -- Stake Out Home (1)  09.26.2022    
-- -- Excavate (2)  09.29.2022    
-- -- Inspection (Footers) (1)  10.09.2022    
-- -- Inspection (Concrete Wall) (1)  10.09.2022    
-- -- Pour Footers (1) *   10.09.2022    
-- -- Set Forms (2)  10.31.2022    
-- -- Pour Foundation Walls (1)  11.03.2022    
-- -- Plumb Slab (2)  12.01.2022    
-- -- Inspection (Plumbing Under Slab) (1)  12.05.2022    
-- -- Inspection (Conduit Under Slab) (1)  12.08.2022    
-- -- Prepare Slab (1)  12.08.2022    
-- -- Inspection (Slab) (1)  12.27.2022    
-- -- Inspection (Drain Tile) (0)  12.27.2022    
-- -- Pour Slab (1) *   12.27.2022    
-- -- Settlement Agent Confirmed (0)  05.16.2023    
-- -- Framing I (9)  01.05.2023    
-- -- Order Steps (0)  02.02.2023    
-- -- Order Tubs / Showers (0)  02.20.2023    
-- -- Framing II (8)  01.12.2023    
-- -- Framing III (8) *   01.31.2023    
-- -- Install Stairs (0) *   02.02.2023    
-- -- Windows & Doors (0) *   02.18.2023    
-- -- House Number and Status in Window (0)  02.22.2023    
-- -- Roofing (0) *   02.20.2023    
-- -- Order Cabinets (0)  03.02.2023    
-- -- Order Appliances (0)  05.22.2023     French Upgrade
-- -- Deck (0)  02.23.2023    
-- -- Gutters (0)  04.03.2023    
-- -- Driveway (0) *   04.26.2023    
-- -- Patio (0)  03.15.2023    
-- -- Privacy Divider / Fence (0) *   06.11.2023    
-- -- Sod / Seed / Landscaping (0)  07.20.2023    
-- -- HVAC Rough In (4)  02.22.2023     In process 2/18
-- -- Plumbing Rough In (4)  02.22.2023     In process 2/18
-- -- Electric Rough In (4)  03.05.2023    
-- -- Inspection (Rough In HVAC) (1)  03.15.2023    
-- -- Inspection (Rough In Plumbing) (1)  03.15.2023    
-- -- Inspection (Rough In Electric) (1)  03.15.2023    
-- -- Inspection (Framing) (1) *   03.15.2023    
-- -- Inspection (Deck Piers) (0)  05.18.2023    
-- -- Exterior Vinyl (0) *   04.10.2023    
-- -- Exterior Stone (0)  05.18.2023     In process 4/29
-- -- Insulation (2) *   03.15.2023    
-- -- Inspection (Insulation) (1)  03.16.2023    
-- -- Inspection (Electric Service) (0)  06.12.2023    
-- -- Set Electric Meter (0) *   06.14.2023    
-- -- Inspection (Main Sewer Line) (0)  03.20.2023    
-- -- Inspection (Main Water Line) (0)  03.20.2023    
-- -- Order Interior Doors & Trim (0)  04.12.2023    
-- -- Drywall (Hang) (4) *   03.25.2023     Stocked 3/18
-- -- Loan Approval (0)  05.25.2023    
-- -- Deed Preparation (0)  06.01.2023    
-- -- Drywall (Tape, Block, Skim, Sand) (6) *   04.10.2023     In process 3/29
-- -- Paint 1 (1)  04.10.2023    
-- -- Garage Door (0)  04.23.2023    
-- -- House Numbers (0)  05.06.2023    
-- -- Mailbox (0)  05.20.2023    
-- -- Cabinet Installation (2) *   04.10.2023     Wed, Apr 5. In process 4/5 drywall doesn’t appear finished…
-- -- Granite Installation (1) *   05.03.2023    
-- -- Interior Trim - Install (3) *   05.06.2023     In process 5/3
-- -- Interior Trim - Paint (1)  05.06.2023    
-- -- Luxury Vinyl Plank (3) *   05.13.2023     In process 5/10
-- -- Luxury Vinyl Tile (0)  05.13.2023    
-- -- Paint 2 (3)  04.23.2023     In process 4/19
-- -- Cover Floors (0)  05.28.2023    
-- -- Deliver Plumbing / Lighting Fixtures (0)  04.27.2023     BN Standard
-- -- Shoe Moulding (0)  05.20.2023    
-- -- Shelving, Door Knobs, Fire Extinguisher (1) *   06.03.2023     BN Accessories, in process 5/31
-- -- Install Coded Lockbox (add extra keys) (0)  06.12.2023    
-- -- Pay Water / Sewer Taps (0)  05.01.2023    
-- -- Set Water Meter (1) *   05.11.2023    
-- -- Electric Trim Out (3) *   05.31.2023     BN Standard. In process 5/28
-- -- Ceiling Fans (0)  05.28.2023    
-- -- HVAC Trim Out (1) *   06.11.2023     Needs hvac covers
-- -- Plumbing Trim Out (2) *   05.20.2023     In process 5/17
-- -- Install Appliances (0) *   06.03.2023     French Delivery 5/11
-- -- Paint 3 (2) *   05.17.2023    
-- -- Carpet (2)  05.20.2023    
-- -- Appraiser Confirms Construction Completion (0)  06.21.2023     Jeff Eye
-- -- Inspection (Final HVAC) (0)  06.16.2023    
-- -- Inspection (Final Plumbing) (0)  06.16.2023    
-- -- Inspection (Final Electric) (0)  06.16.2023    
-- -- Inspection (Final Building) (4) *   06.16.2023    
-- -- Pre Walk Through (0)  06.19.2023    
-- -- Stain Hardwood Stairs (1) *   06.03.2023     In process 5/28
-- -- Cleaning (1)  06.21.2023    
-- -- Certificate of Occupancy (1) *   06.20.2023    
-- -- C.O. to Lender (0)  06.20.2023    
-- -- Schedule Closing (0)  06.21.2023    
-- -- Buyer Walk Through (1) *   06.19.2023    
-- -- Payment for Upgrades (0)  06.19.2023    
-- -- Keys to Settlement Agent (0)  06.21.2023    
-- -- Review Settlement Statement (0)  06.22.2023    
-- -- Jerry Signs Closing Documents (0)  06.23.2023    
-- -- Request Trash Tote From POA Manager (0)  06.22.2023    
-- -- Closing (1)  06.26.2023     Cheryl Payne, Clark & Bradshaw
-- -- Remove Coded Lockbox (0)  07.10.2023