Fri |
Sep 20 |
Verify Window & Roof Structure (0)
|
|
|
Fri |
Sep 20 |
Rough In Microwave Vent (0)
|
|
|
Fri |
Sep 20 |
Blower Door Test (1)
|
|
|
|
-- |
-- |
Kate task notes have flipped cabinet colors but selections sheet has correct ones. Please confirm all is correct. |
|
|
-- |
-- |
Countertops needed for the hall and master bathroom |
|
|
-- |
-- |
Garage door |
Davenport |
|
-- |
-- |
Kitchen faucet needs installed after counters |
|
|
-- |
-- |
Large crack in kitchen ware granite was installed. Well, the oven cover it? |
|
|
-- |
-- |
Cover carpet |
Jill |
|
-- |
-- |
Missing hvac cover living room |
And in kitchen |
|
-- |
-- |
Lightbulbs needed in dining chandelier |
Electrician |
|
-- |
-- |
PAUSE CONSTRUCTION / REMOVE UPGRADES |
Buyer has not made deposit upgrade |
|
-- |
-- |
Missing receptacle cover in the hall bathroom |
Electrician |
|
-- |
-- |
Remove remote control that is hanging from ceiling fan |
Electrician |
|
-- |
-- |
Trim, needed in garage |
Edgar, Trim |
|
-- |
-- |
Mirrors needed |
Monday, May 8 |
|
-- |
-- |
CODED LOCKBOX 9898 |
|
|
-- |
-- |
Please cut down dead tree trunk in backyard |
Tom |
|
-- |
-- |
Plug Screw holes in all doors |
Jill |
|
-- |
-- |
Missing floor vent living room |
HVAC |
|
-- |
-- |
That’s quick second to last carpeted stair to the third-floor |
|
|
-- |
-- |
All mirrors to be installed |
Monday, May 8 |
|
-- |
-- |
Bedroom three closet doors to be adjusted |
Jill |
|
-- |
-- |
Bad squeak in second to last step to third floor |
Denny |
|
-- |
-- |
Carpet - is the color correct? |
|
|
-- |
-- |
HVAC cover needed kitchen |
HVAC |
|
-- |
-- |
Needs electric covers in garage |
Electrician |
|
-- |
-- |
Needs electric covers in garage |
|
|
-- |
-- |
Touchup needed in Selene living room |
|
|
-- |
-- |
Touchup needed in ceiling of living room |
Painter |
|
-- |
-- |
Touch up wood at bottom of staircase |
Painter |
|
-- |
-- |
Weatherstripping needed |
Jill or Painter |
|
-- |
-- |
Replacing ALL carpet |
Incorrect color installed- on order. Installing Thursday, June 8 |
|
-- |
-- |
Needs a lot of electrical covers |
Basically the entire house, electrician |
|
-- |
-- |
Outdoor electric trim out needed |
Electrician - back deck outlet |
|
-- |
-- |
Push bathroom fan into place |
Jill |
|
-- |
-- |
Lots of paint on the steps from the basement to main level |
Painters-Jill following up |
|
-- |
-- |
Buyer hesitancy to proceed to closing |
Scott is following up |
|
-- |
-- |
Need bulbs in chandelier |
|
|
-- |
-- |
Fridge to be hooked up |
Plug in |
|
-- |
-- |
Sweep off deck |
|
|
-- |
-- |
Install fire extinguisher |
|
|
-- |
-- |
A few shallow scratches on the surface of island countertop behind sink |
Jill is coordinating a repair with Greg |
|
-- |
-- |
Master shower has a small crack in the shower wall |
Jill |
|
-- |
-- |
Pressure wash the bottom of house at patio and the patio too |
Jill |
|
-- |
-- |
Paint touch up throughout home |
Painter |
|
-- |
-- |
Missing hinge pin in the bedroom door to the left |
Tom |
|
-- |
-- |
Missing hinge pin in the closet door in the bedroom to the right |
Tom |
|
-- |
-- |
Guest bathroom has a crack in the shower wall |
In process 7/5 |
|
-- |
-- |
Guest bathroom has a crack in the shower wall |
|
|
-- |
-- |
|
|
|
-- |
-- |
Touch up paint cans in here. Do they need to be distributed? Big box |
|
|
-- |
-- |
Push attic cover into place |
Jill |
|
-- |
-- |
Few paint touchups |
|
|
-- |
-- |
Scratch on ceiling |
Painter |
|
-- |
-- |
Scratch on ceiling |
|
|
-- |
-- |
Lots of dead bugs in these lights |
|
|
-- |
-- |
Ratified Contract? (0)
12.13.2022 |
|
|
-- |
-- |
$2500 Deposit Received (0)
12.20.2022 |
|
|
-- |
-- |
Association Packet Requested (0)
12.13.2022 |
Requested 12/13 |
|
-- |
-- |
Association Packet Received (0)
12.15.2022 |
|
|
-- |
-- |
Selections Meeting (0)
01.25.2023 |
|
|
-- |
-- |
Selections Sheet Signed (0)
02.16.2023 |
2/7/2023: sent revised version to Kozhin |
|
-- |
-- |
Amendment for Upgrades (B,S,L,T,BCP) (0)
05.10.2023 |
2/16: buyer has signed, waiting on upgrade deposit |
|
-- |
-- |
Deposit For Upgrades Received (0)
05.10.2023 |
|
|
-- |
-- |
Building Permit (30)
10.08.2022 |
|
|
-- |
-- |
Order Roof & Floor Trusses (1)
11.03.2022 |
|
|
-- |
-- |
Order Windows & Doors (0)
11.03.2022 |
|
|
-- |
-- |
Stake Out Home (1)
10.06.2022 |
|
|
-- |
-- |
Excavate (2)
10.06.2022 |
|
|
-- |
-- |
Inspection (Footers) (1)
10.06.2022 |
|
|
-- |
-- |
Inspection (Concrete Wall) (1)
11.10.2022 |
|
|
-- |
-- |
Pour Footers (1)
10.06.2022 |
|
|
-- |
-- |
Set Forms (2)
11.10.2022 |
|
|
-- |
-- |
Pour Foundation Walls (1)
11.10.2022 |
|
|
-- |
-- |
Plumb Slab (2)
11.10.2022 |
|
|
-- |
-- |
Inspection (Plumbing Under Slab) (1)
11.10.2022 |
|
|
-- |
-- |
Inspection (Conduit Under Slab) (1)
11.10.2022 |
|
|
-- |
-- |
Prepare Slab (1)
11.17.2022 |
|
|
-- |
-- |
Inspection (Slab) (1)
11.19.2022 |
|
|
-- |
-- |
Inspection (Drain Tile) (0)
12.27.2022 |
|
|
-- |
-- |
Pour Slab (1)
11.19.2022 |
|
|
-- |
-- |
Settlement Agent Confirmed (0)
05.04.2023 |
|
|
-- |
-- |
Framing I (9)
12.05.2022 |
|
|
-- |
-- |
Order Steps (0)
01.12.2023 |
|
|
-- |
-- |
Order Tubs / Showers (0)
01.12.2023 |
|
|
-- |
-- |
Framing II (8)
12.27.2022 |
|
|
-- |
-- |
Framing III (8)
01.02.2023 |
|
|
-- |
-- |
Install Stairs (0)
01.12.2023 |
|
|
-- |
-- |
Windows & Doors (0)
01.12.2023 |
|
|
-- |
-- |
House Number and Status in Window (0)
02.23.2023 |
|
|
-- |
-- |
Roofing (0)
01.12.2023 |
|
|
-- |
-- |
Order Cabinets (0)
02.17.2023 |
|
|
-- |
-- |
Order Appliances (0)
05.08.2023 |
Standard SS |
|
-- |
-- |
Deck (0)
04.12.2023 |
In process 4/10 |
|
-- |
-- |
Gutters (0)
03.22.2023 |
|
|
-- |
-- |
Driveway (0)
04.05.2023 |
|
|
-- |
-- |
Patio (0)
04.05.2023 |
|
|
-- |
-- |
Privacy Divider / Fence (0)
05.06.2023 |
|
|
-- |
-- |
Sod / Seed / Landscaping (0)
06.03.2023 |
|
|
-- |
-- |
HVAC Rough In (4)
01.07.2023 |
|
|
-- |
-- |
Inspection (Rough In HVAC) (1)
02.10.2023 |
|
|
-- |
-- |
Plumbing Rough In (4)
01.21.2023 |
In process 1/18 |
|
-- |
-- |
Inspection (Rough In Plumbing) (1)
02.10.2023 |
|
|
-- |
-- |
Electric Rough In (4)
02.01.2023 |
|
|
-- |
-- |
Inspection (Rough In Electric) (1)
02.10.2023 |
|
|
-- |
-- |
Inspection (Deck Piers) (0)
04.11.2023 |
|
|
-- |
-- |
Inspection (Framing) (1)
02.10.2023 |
|
|
-- |
-- |
Exterior Vinyl (0)
03.22.2023 |
|
|
-- |
-- |
Exterior Stone (0)
03.22.2023 |
|
|
-- |
-- |
Insulation (2)
02.13.2023 |
In process 2/11 |
|
-- |
-- |
Inspection (Insulation) (1)
02.13.2023 |
|
|
-- |
-- |
Inspection (Electric Service) (0)
06.01.2023 |
|
|
-- |
-- |
Set Electric Meter (0)
06.16.2023 |
|
|
-- |
-- |
Inspection (Main Sewer Line) (0)
03.20.2023 |
|
|
-- |
-- |
Inspection (Main Water Line) (0)
03.20.2023 |
|
|
-- |
-- |
Order Interior Doors & Trim (0)
04.10.2023 |
|
|
-- |
-- |
Drywall (Hang) (4)
02.18.2023 |
|
|
-- |
-- |
Loan Approval (0)
06.01.2023 |
|
|
-- |
-- |
Deed Preparation (0)
05.22.2023 |
|
|
-- |
-- |
Drywall (Tape, Block, Skim, Sand) (6)
03.05.2023 |
In process 3/1 |
|
-- |
-- |
Paint 1 (1)
03.05.2023 |
|
|
-- |
-- |
Garage Door (0)
04.23.2023 |
|
|
-- |
-- |
House Numbers (0)
05.06.2023 |
|
|
-- |
-- |
Mailbox (0)
05.06.2023 |
|
|
-- |
-- |
Cabinet Installation (2)
03.15.2023 |
|
|
-- |
-- |
Granite Installation (1)
04.19.2023 |
|
|
-- |
-- |
Interior Trim - Install (3)
04.01.2023 |
In process 3/31 |
|
-- |
-- |
Order Plumbing / Lighting Fixtures (0)
07.26.2023 |
|
|
-- |
-- |
Interior Trim - Paint (1)
04.01.2023 |
|
|
-- |
-- |
Luxury Vinyl Plank (3)
04.12.2023 |
In process 4/10 |
|
-- |
-- |
Luxury Vinyl Tile (0)
04.15.2023 |
|
|
-- |
-- |
Paint 2 (3)
03.22.2023 |
In process 3/15 |
|
-- |
-- |
Cover Floors (1)
05.20.2023 |
|
|
-- |
-- |
Deliver Plumbing / Lighting Fixtures (0)
04.11.2023 |
|
|
-- |
-- |
Shoe Moulding (0)
04.23.2023 |
|
|
-- |
-- |
Shelving, Door Knobs, Fire Extinguisher (0)
05.06.2023 |
In process 5/6 |
|
-- |
-- |
Install Coded Lockbox (add extra keys) (0)
05.06.2023 |
|
|
-- |
-- |
Pay Water / Sewer Taps (0)
05.01.2023 |
|
|
-- |
-- |
Set Water Meter (0)
05.11.2023 |
|
|
-- |
-- |
Electric Trim Out (3)
04.26.2023 |
|
|
-- |
-- |
Ceiling Fans (0)
04.26.2023 |
|
|
-- |
-- |
HVAC Trim Out (1)
04.26.2023 |
|
|
-- |
-- |
Plumbing Trim Out (2)
04.15.2023 |
|
|
-- |
-- |
Install Appliances (0)
05.10.2023 |
Standard SS |
|
-- |
-- |
Paint 3 (2)
04.05.2023 |
|
|
-- |
-- |
Carpet (2)
04.15.2023 |
In process 4/12 |
|
-- |
-- |
Appraiser Confirms Construction Completion (0)
06.29.2023 |
|
|
-- |
-- |
Inspection (Final HVAC) (1)
06.21.2023 |
|
|
-- |
-- |
Inspection (Final Plumbing) (1)
06.21.2023 |
|
|
-- |
-- |
Inspection (Final Electric) (1)
06.21.2023 |
|
|
-- |
-- |
Inspection (Final Building) (2)
06.21.2023 |
June 21 |
|
-- |
-- |
Pre Walk Through (0)
05.22.2023 |
|
|
-- |
-- |
Stain Hardwood Stairs (1)
04.26.2023 |
|
|
-- |
-- |
Cleaning (1)
06.28.2023 |
|
|
-- |
-- |
Certificate of Occupancy (1)
06.28.2023 |
|
|
-- |
-- |
C.O. to Lender (0)
06.28.2023 |
|
|
-- |
-- |
Schedule Closing (0)
07.27.2023 |
|
|
-- |
-- |
Buyer Walk Through (1)
07.01.2023 |
Friday, June 30, 1:00 PM |
|
-- |
-- |
Payment for Upgrades (0)
06.26.2023 |
|
|
-- |
-- |
Keys to Settlement Agent (0)
06.29.2023 |
|
|
-- |
-- |
Review Settlement Statement (0)
07.27.2023 |
|
|
-- |
-- |
Jerry Signs Closing Documents (0)
07.19.2023 |
|
|
-- |
-- |
Request Trash Tote From POA Manager (0)
06.22.2023 |
|
|
-- |
-- |
Closing (1)
07.27.2023 |
Brittany @ West View Title |
|
-- |
-- |
Remove Coded Lockbox (0)
08.07.2023 |
|
|