1 33 37 89 47 73 67 55 56 59 57 66 65 64 60 61 62 63 ADDR
CONGERS-2 - 98  ::  1493 Palomino Trail
[ BUILD: 20221354 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
Thu    Nov 28      Verify Window & Roof Structure (0)      
Thu    Nov 28      Rough In Microwave Vent (0)      
Thu    Nov 28      Blower Door Test (1)      
--   --   Kate task notes have flipped cabinet colors but selections sheet has correct ones. Please confirm all is correct.
--   --   Countertops needed for the hall and master bathroom
--   --   Garage door Davenport
--   --   Kitchen faucet needs installed after counters
--   --   Large crack in kitchen ware granite was installed. Well, the oven cover it?
--   --   Cover carpet Jill
--   --   Missing hvac cover living room And in kitchen
--   --   Lightbulbs needed in dining chandelier Electrician
--   --   PAUSE CONSTRUCTION / REMOVE UPGRADES Buyer has not made deposit upgrade
--   --   Missing receptacle cover in the hall bathroom Electrician
--   --   Remove remote control that is hanging from ceiling fan Electrician
--   --   Trim, needed in garage Edgar, Trim
--   --   Mirrors needed Monday, May 8
--   --   CODED LOCKBOX 9898
--   --   Please cut down dead tree trunk in backyard Tom
--   --   Plug Screw holes in all doors Jill
--   --   Missing floor vent living room HVAC
--   --   That’s quick second to last carpeted stair to the third-floor
--   --   All mirrors to be installed Monday, May 8
--   --   Bedroom three closet doors to be adjusted Jill
--   --   Bad squeak in second to last step to third floor Denny
--   --   Carpet - is the color correct?
--   --   HVAC cover needed kitchen HVAC
--   --   Needs electric covers in garage Electrician
--   --   Needs electric covers in garage
--   --   Touchup needed in Selene living room
--   --   Touchup needed in ceiling of living room Painter
--   --   Touch up wood at bottom of staircase Painter
--   --   Weatherstripping needed Jill or Painter
--   --   Replacing ALL carpet Incorrect color installed- on order. Installing Thursday, June 8
--   --   Needs a lot of electrical covers Basically the entire house, electrician
--   --   Outdoor electric trim out needed Electrician - back deck outlet
--   --   Push bathroom fan into place Jill
--   --   Lots of paint on the steps from the basement to main level Painters-Jill following up
--   --   Buyer hesitancy to proceed to closing Scott is following up
--   --   Need bulbs in chandelier
--   --   Fridge to be hooked up Plug in
--   --   Sweep off deck
--   --   Install fire extinguisher
--   --   A few shallow scratches on the surface of island countertop behind sink Jill is coordinating a repair with Greg
--   --   Master shower has a small crack in the shower wall Jill
--   --   Pressure wash the bottom of house at patio and the patio too Jill
--   --   Paint touch up throughout home Painter
--   --   Missing hinge pin in the bedroom door to the left Tom
--   --   Missing hinge pin in the closet door in the bedroom to the right Tom
--   --   Guest bathroom has a crack in the shower wall In process 7/5
--   --   Guest bathroom has a crack in the shower wall
--   --  
--   --   Touch up paint cans in here. Do they need to be distributed? Big box
--   --   Push attic cover into place Jill
--   --   Few paint touchups
--   --   Scratch on ceiling Painter
--   --   Scratch on ceiling
--   --   Lots of dead bugs in these lights
-- -- Ratified Contract? (0)  12.13.2022    
-- -- $2500 Deposit Received (0)  12.20.2022    
-- -- Association Packet Requested (0)  12.13.2022     Requested 12/13
-- -- Association Packet Received (0)  12.15.2022    
-- -- Selections Meeting (0)  01.25.2023    
-- -- Selections Sheet Signed (0)  02.16.2023     2/7/2023: sent revised version to Kozhin
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  05.10.2023     2/16: buyer has signed, waiting on upgrade deposit
-- -- Deposit For Upgrades Received (0)  05.10.2023    
-- -- Building Permit (30)  10.08.2022    
-- -- Order Roof & Floor Trusses (1)  11.03.2022    
-- -- Order Windows & Doors (0)  11.03.2022    
-- -- Stake Out Home (1)  10.06.2022    
-- -- Excavate (2)  10.06.2022    
-- -- Inspection (Footers) (1)  10.06.2022    
-- -- Inspection (Concrete Wall) (1)  11.10.2022    
-- -- Pour Footers (1)  10.06.2022    
-- -- Set Forms (2)  11.10.2022    
-- -- Pour Foundation Walls (1)  11.10.2022    
-- -- Plumb Slab (2)  11.10.2022    
-- -- Inspection (Plumbing Under Slab) (1)  11.10.2022    
-- -- Inspection (Conduit Under Slab) (1)  11.10.2022    
-- -- Prepare Slab (1)  11.17.2022    
-- -- Inspection (Slab) (1)  11.19.2022    
-- -- Inspection (Drain Tile) (0)  12.27.2022    
-- -- Pour Slab (1) *   11.19.2022    
-- -- Settlement Agent Confirmed (0)  05.04.2023    
-- -- Framing I (9)  12.05.2022    
-- -- Order Steps (0)  01.12.2023    
-- -- Order Tubs / Showers (0)  01.12.2023    
-- -- Framing II (8)  12.27.2022    
-- -- Framing III (8) *   01.02.2023    
-- -- Install Stairs (0)  01.12.2023    
-- -- Windows & Doors (0)  01.12.2023    
-- -- House Number and Status in Window (0)  02.23.2023    
-- -- Roofing (0)  01.12.2023    
-- -- Order Cabinets (0)  02.17.2023    
-- -- Order Appliances (0)  05.08.2023     Standard SS
-- -- Deck (0)  04.12.2023     In process 4/10
-- -- Gutters (0)  03.22.2023    
-- -- Driveway (0)  04.05.2023    
-- -- Patio (0)  04.05.2023    
-- -- Privacy Divider / Fence (0)  05.06.2023    
-- -- Sod / Seed / Landscaping (0)  06.03.2023    
-- -- HVAC Rough In (4)  01.07.2023    
-- -- Inspection (Rough In HVAC) (1)  02.10.2023    
-- -- Plumbing Rough In (4)  01.21.2023     In process 1/18
-- -- Inspection (Rough In Plumbing) (1)  02.10.2023    
-- -- Electric Rough In (4)  02.01.2023    
-- -- Inspection (Rough In Electric) (1)  02.10.2023    
-- -- Inspection (Deck Piers) (0)  04.11.2023    
-- -- Inspection (Framing) (1)  02.10.2023    
-- -- Exterior Vinyl (0) *   03.22.2023    
-- -- Exterior Stone (0)  03.22.2023    
-- -- Insulation (2)  02.13.2023     In process 2/11
-- -- Inspection (Insulation) (1)  02.13.2023    
-- -- Inspection (Electric Service) (0)  06.01.2023    
-- -- Set Electric Meter (0)  06.16.2023    
-- -- Inspection (Main Sewer Line) (0)  03.20.2023    
-- -- Inspection (Main Water Line) (0)  03.20.2023    
-- -- Order Interior Doors & Trim (0)  04.10.2023    
-- -- Drywall (Hang) (4) *   02.18.2023    
-- -- Loan Approval (0)  06.01.2023    
-- -- Deed Preparation (0)  05.22.2023    
-- -- Drywall (Tape, Block, Skim, Sand) (6) *   03.05.2023     In process 3/1
-- -- Paint 1 (1)  03.05.2023    
-- -- Garage Door (0)  04.23.2023    
-- -- House Numbers (0)  05.06.2023    
-- -- Mailbox (0)  05.06.2023    
-- -- Cabinet Installation (2) *   03.15.2023    
-- -- Granite Installation (1) *   04.19.2023    
-- -- Interior Trim - Install (3)  04.01.2023     In process 3/31
-- -- Order Plumbing / Lighting Fixtures (0)  07.26.2023    
-- -- Interior Trim - Paint (1)  04.01.2023    
-- -- Luxury Vinyl Plank (3) *   04.12.2023     In process 4/10
-- -- Luxury Vinyl Tile (0)  04.15.2023    
-- -- Paint 2 (3)  03.22.2023     In process 3/15
-- -- Cover Floors (1)  05.20.2023    
-- -- Deliver Plumbing / Lighting Fixtures (0)  04.11.2023    
-- -- Shoe Moulding (0)  04.23.2023    
-- -- Shelving, Door Knobs, Fire Extinguisher (0)  05.06.2023     In process 5/6
-- -- Install Coded Lockbox (add extra keys) (0)  05.06.2023    
-- -- Pay Water / Sewer Taps (0)  05.01.2023    
-- -- Set Water Meter (0)  05.11.2023    
-- -- Electric Trim Out (3)  04.26.2023    
-- -- Ceiling Fans (0)  04.26.2023    
-- -- HVAC Trim Out (1)  04.26.2023    
-- -- Plumbing Trim Out (2)  04.15.2023    
-- -- Install Appliances (0) *   05.10.2023     Standard SS
-- -- Paint 3 (2) *   04.05.2023    
-- -- Carpet (2)  04.15.2023     In process 4/12
-- -- Appraiser Confirms Construction Completion (0)  06.29.2023    
-- -- Inspection (Final HVAC) (1)  06.21.2023    
-- -- Inspection (Final Plumbing) (1)  06.21.2023    
-- -- Inspection (Final Electric) (1)  06.21.2023    
-- -- Inspection (Final Building) (2) *   06.21.2023     June 21
-- -- Pre Walk Through (0)  05.22.2023    
-- -- Stain Hardwood Stairs (1)  04.26.2023    
-- -- Cleaning (1)  06.28.2023    
-- -- Certificate of Occupancy (1) *   06.28.2023    
-- -- C.O. to Lender (0)  06.28.2023    
-- -- Schedule Closing (0)  07.27.2023    
-- -- Buyer Walk Through (1)  07.01.2023     Friday, June 30, 1:00 PM
-- -- Payment for Upgrades (0)  06.26.2023    
-- -- Keys to Settlement Agent (0)  06.29.2023    
-- -- Review Settlement Statement (0)  07.27.2023    
-- -- Jerry Signs Closing Documents (0)  07.19.2023    
-- -- Request Trash Tote From POA Manager (0)  06.22.2023    
-- -- Closing (1)  07.27.2023     Brittany @ West View Title
-- -- Remove Coded Lockbox (0)  08.07.2023