| TO DO | ||||
| --- | ||||
| UPGRADES | ||||
| --- | ||||
| CRITICAL PATH | ||||
| --- | ||||
| TO DO - COMPLETED OR DELETED | ||||
| UPGRADES - COMPLETED | ||||
| 12 x 18 Deck | ||||
| Painted Cabinets ( White perimeter- Light Gray Island) | ||||
| White Farmhouse sink | ||||
| Double Trashcan | ||||
| Expanded Driveway | ||||
| Spice Rack in Base 9 | ||||
| Amendment to increase price by $6,630 | ||||
| CRITICAL PATH - COMPLETED | ||||
| -- | -- | Inspection (Footers) (1) 10.06.2022 | ||
| -- | -- | Inspection (Concrete Wall) (1) 11.10.2022 | ||
| -- | -- | Inspection (Plumbing Under Slab) (1) 11.10.2022 | ||
| -- | -- | Inspection (Conduit Under Slab) (1) 11.10.2022 | ||
| -- | -- | Inspection (Slab) (1) 11.19.2022 | ||
| -- | -- | Inspection (Drain Tile) (0) 12.27.2022 | ||
| -- | -- | Inspection (Rough In HVAC) (1) 02.10.2023 | ||
| -- | -- | Inspection (Rough In Plumbing) (1) 02.10.2023 | ||
| -- | -- | Inspection (Rough In Electric) (1) 02.10.2023 | ||
| -- | -- | Inspection (Framing) (1) * 02.10.2023 | ||
| -- | -- | Inspection (Deck Piers) (0) 04.11.2023 | ||
| -- | -- | Inspection (Insulation) (1) 02.13.2023 | ||
| -- | -- | Inspection (Electric Service) (0) 06.01.2023 | ||
| -- | -- | Inspection (Main Sewer Line) (0) 03.20.2023 | ||
| -- | -- | Inspection (Main Water Line) (0) 03.20.2023 | ||
| -- | -- | Inspection (Final HVAC) (0) 06.21.2023 | ||
| -- | -- | Inspection (Final Plumbing) (0) 06.21.2023 | ||
| -- | -- | Inspection (Final Electric) (0) 06.21.2023 | ||
| -- | -- | Inspection (Final Building) (4) * 06.21.2023 | June 21 | |