CONGERS-2 - 33  ::  1504 Palomino Trail
[ BUILD: 29221535 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
--   --   Attic ventilation Domingo needs to fix it
--   --   Jordan 540-271-4746
--   --   Missing boards in master bathroom
--   --   Appliances delivered May 11
--   --   Missing Shed Dormer On Roof Tom will have them add it-Country Beige, Davenport
--   --   Wrong Color Front Siding On Third Floor Should be green cedar shake, but it is brown
--   --   Remove sticker from whiteboard on side
--   --   One three drawer stack missing? Refund for this accessory
--   --   Replace PVC board on side return between 32 and 33 Between 2nd and 3rd floor, Davenport
--   --   Vinyl, siding, patched, and back patio is not matching color Tom or Kenny
--   --   Piece of siding stuck on side of townhouse Davenport
--   --   What happened to the glass in the front door? Tom
--   --   Refrigerator installed is not upgraded seems fridges need swamped 32/33
--   --   Cover carpet
--   --   Corner broken of back window Jill
--   --   Pendants not snap lights need installed in kitchen
--   --   Nail white patio board into place Kenny
--   --   Cover carpet Kristen
--   --   Outlet cover needed in kitchen Electrician
--   --   Aim level closet doorknob needed Trim
--   --   Trim closet door in master bedroom Cut off bottom of door - Trim guy
--   --   Needs electric trim out in bonus room and bonus bathroom And exterior at patio - electrician
--   --   Pieces of sitting in the kitchen look in complete. Some type of decorative trim needed.
--   --   Banquette area - trim at front of sitting area Fred
--   --   Banquette area - caulk at back of sitting area Painter
--   --   Banquette area - trim at kick plate area Trim guys
--   --   Banquette area - touch up at seam of sitting area Fred - waiting on material
--   --   Powder bath mirror needed Paul
--   --   Remove glue in master bathroom Jill
--   --   Vanity light in bonus bathroom needed Electrician
--   --   CODED LOCKBOX 3333
--   --   Push attic cover into place Jill
--   --   Need to trim in front of bathtub in bonus room Trim
--   --   Need to write a check for $300 to the buyers It is at West View Title
--   --   Bathtub stopper needed hall bath In at Northeastern
--   --   Clean blue spots in master floor Jill
--   --   Clean pendant lights in Island Lynn
--   --   Plugs in screw holes front door Jill
--   --   Light in bonus room Light is upside down-flip. Electrician
--   --   Clean paint off the floor, luxury vinyl living room Painter
--   --   Shelf needed cabinet above the microwave Jill
--   --   Pressure wash outside Tom
--   --   Repaint steps to third-floor Jill will tell painters
--   --  
--   --   Banquette seating has nail holes that need to be filled inside doors
--   --   Banquette seating has nail holes that need to be filled inside doors Fred
--   --   Clean glue off bonus bathtub Jill
--   --   Touch up paint Painters
--   --   Siding piece not right color
--   --   Front door touch up Painter
--   --   Repair landscaping bTween driveways Pettit
--   --   paint dormer windows Buddy. Needed 9/16
--   --   Attic insulation Home inspection report
--   --   Josie (571)245-4656
-- -- Ratified Contract? (0)  12.22.2022    
-- -- $2500 Deposit Received (0)  12.30.2022    
-- -- Association Packet Requested (0)  12.22.2022    
-- -- Association Packet Received (0)  12.23.2022    
-- -- Selections Meeting (0)  01.26.2023    
-- -- Selections Sheet Signed (0)  03.08.2023     2/15: waiting on edits by Kate
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  03.10.2023     3/10: sent to Jerry
-- -- Deposit For Upgrades Received (0)  03.10.2023    
-- -- Building Permit (30)  10.08.2022    
-- -- Order Roof & Floor Trusses (1)  11.03.2022    
-- -- Order Windows & Doors (0)  03.06.2023    
-- -- Stake Out Home (1)  10.17.2022    
-- -- Excavate (2)  10.17.2022    
-- -- Inspection (Footers) (1)  10.17.2022    
-- -- Inspection (Concrete Wall) (1)  11.10.2022     11/4/22
-- -- Pour Footers (1)  10.17.2022    
-- -- Set Forms (2)  11.10.2022    
-- -- Pour Foundation Walls (1)  11.10.2022    
-- -- Plumb Slab (2)  12.08.2022    
-- -- Inspection (Plumbing Under Slab) (1)  12.08.2022    
-- -- Inspection (Conduit Under Slab) (1)  12.08.2022    
-- -- Prepare Slab (1)  01.31.2023    
-- -- Inspection (Slab) (1)  01.31.2023    
-- -- Inspection (Drain Tile) (0)  01.31.2023    
-- -- Pour Slab (1) *   01.31.2023    
-- -- Settlement Agent Confirmed (0)  01.04.2023    
-- -- Framing I (9)  01.31.2023    
-- -- Order Steps (0)  03.06.2023    
-- -- Order Tubs / Showers (0)  03.06.2023    
-- -- Framing II (8)  02.23.2023    
-- -- Framing III (8) *   03.06.2023    
-- -- Verify Window & Roof Structure (0)  08.03.2024    
-- -- Install Stairs (0)  03.22.2023    
-- -- Windows & Doors (0)  03.06.2023    
-- -- House Number and Status in Window (0)  04.05.2023    
-- -- Roofing (0)  03.06.2023    
-- -- Order Cabinets (0)  04.12.2023    
-- -- Order Appliances (0)  06.11.2023     French Upgrade
-- -- Deck (0)  04.11.2023    
-- -- Gutters (0)  05.20.2023    
-- -- Driveway (0)  05.31.2023    
-- -- Patio (0)  05.20.2023    
-- -- Privacy Divider / Fence (0)  07.12.2023    
-- -- Sod / Seed / Landscaping (0)  07.16.2023    
-- -- HVAC Rough In (4)  03.22.2023     In process 3/15
-- -- Inspection (Rough In HVAC) (1)  04.06.2023    
-- -- Rough In Microwave Vent (0)  08.03.2024    
-- -- Plumbing Rough In (4)  03.29.2023     In process 3/25
-- -- Inspection (Rough In Plumbing) (1)  04.06.2023    
-- -- Electric Rough In (4)  04.10.2023    
-- -- Inspection (Rough In Electric) (1)  04.13.2023    
-- -- Inspection (Deck Piers) (0)  06.12.2023    
-- -- Inspection (Framing) (1)  04.13.2023    
-- -- Exterior Vinyl (0) *   05.31.2023    
-- -- Exterior Stone (0)  05.31.2023    
-- -- Insulation (2)  04.15.2023    
-- -- Inspection (Insulation) (1)  04.23.2023    
-- -- Inspection (Electric Service) (0)  06.28.2023    
-- -- Set Electric Meter (0)  07.08.2023    
-- -- Inspection (Main Sewer Line) (0)  03.20.2023    
-- -- Inspection (Main Water Line) (0)  03.20.2023    
-- -- Order Interior Doors & Trim (0)  05.18.2023    
-- -- Drywall (Hang) (4) *   04.23.2023    
-- -- Loan Approval (0)  06.19.2023    
-- -- Deed Preparation (0)  05.10.2023    
-- -- Drywall (Tape, Block, Skim, Sand) (6) *   05.06.2023     In process 5/3
-- -- Paint 1 (1)  05.17.2023    
-- -- Garage Door (0)  06.03.2023    
-- -- House Numbers (0)  05.25.2023    
-- -- Mailbox (0)  06.12.2023    
-- -- Cabinet Installation (2) *   05.17.2023    
-- -- Granite Installation (1) *   05.31.2023    
-- -- Interior Trim - Install (3)  05.28.2023     In process 5/24
-- -- Order Plumbing / Lighting Fixtures (0)  07.26.2023    
-- -- Interior Trim - Paint (1)  05.31.2023    
-- -- Luxury Vinyl Plank (3) *   06.11.2023    
-- -- Luxury Vinyl Tile (0)  06.11.2023     In process 6/7
-- -- Paint 2 (3)  06.07.2023    
-- -- Cover Floors (1)  06.26.2023    
-- -- Deliver Plumbing / Lighting Fixtures (0)  06.01.2023    
-- -- Shoe Moulding (0)  06.28.2023    
-- -- Shelving, Door Knobs, Fire Extinguisher (0)  07.12.2023     In process 6/28. Still quite a bit to do 7/9Shelving and mirrors needed.
-- -- Install Coded Lockbox (add extra keys) (0)  07.12.2023    
-- -- Pay Water / Sewer Taps (0)  06.19.2023    
-- -- Set Water Meter (0)  07.20.2023     Mon, July 17
-- -- Electric Trim Out (3)  07.09.2023     Bonus bathroom needs electrical trim out
-- -- Ceiling Fans (0)  06.14.2023    
-- -- HVAC Trim Out (1)  06.28.2023    
-- -- Blower Door Test (1)  08.03.2024    
-- -- Plumbing Trim Out (2)  06.28.2023    
-- -- Install Appliances (0) *   06.11.2023     Delivery 5/23
-- -- Paint 3 (2) *   06.28.2023    
-- -- Carpet (2)  06.14.2023    
-- -- Appraiser Confirms Construction Completion (0)  07.28.2023    
-- -- Inspection (Final HVAC) (1)  07.19.2023    
-- -- Inspection (Final Plumbing) (1)  07.19.2023    
-- -- Inspection (Final Electric) (1)  07.19.2023    
-- -- Inspection (Final Building) (2) *   07.19.2023     Tuesday, July 18
-- -- Pre Walk Through (0)  07.20.2023    
-- -- Stain Hardwood Stairs (1)  06.28.2023    
-- -- Cleaning (1)  07.20.2023     In process 7/19
-- -- Certificate of Occupancy (1) *   07.20.2023    
-- -- C.O. to Lender (0)  07.20.2023     Patrick Linn
-- -- Schedule Closing (0)  07.28.2023     buyers mentioned about 10 days from 7/21
-- -- Buyer Walk Through (1)  07.22.2023     Friday, July 21, 3PM
-- -- Payment for Upgrades (0)  07.17.2023    
-- -- Keys to Settlement Agent (0)  07.17.2023    
-- -- Review Settlement Statement (0)  07.28.2023    
-- -- Jerry Signs Closing Documents (0)  07.19.2023    
-- -- Request Trash Tote From POA Manager (0)  07.17.2023    
-- -- Closing (1)  08.03.2023     Brittany @ West View Title
-- -- Remove Coded Lockbox (0)  08.03.2023