Hardwood treads needed here! |
|
|
-- |
-- |
Back room LVP? |
CARPET AS PER SELECTIONS- KK 9/14 |
|
-- |
-- |
Back room finished? |
FAMILY ROOM UNFINISHED ( WITHOUT WINDOWS)- KK 9/14 |
|
-- |
-- |
Both basement spaces are drywalled. Thinking back room needs removed? |
Contacting Denee about her wishes (Kate) |
|
-- |
-- |
Few pieces of drywall need flung 9/16 |
Only back bonus room need finishing 9/27 |
|
-- |
-- |
I think electric in back room is completed 9/27 |
|
|
-- |
-- |
One piece of drywall needed in basement |
|
|
-- |
-- |
Finish drywall in the back room |
Drywaller |
|
-- |
-- |
Missing main level vanity 10/14 |
|
|
-- |
-- |
Paint doors to master closet |
|
|
-- |
-- |
Trim needed on balcony |
|
|
-- |
-- |
Cut white barrier from front door overhang |
Trim frayed house wrap - Tom |
|
-- |
-- |
Cracked vinyl on porch overhang |
Soffit - Davenport |
|
-- |
-- |
Drywall needs finished at top of stair banister |
Drywaller |
|
-- |
-- |
Drywall needs finished at top of stair banister |
|
|
-- |
-- |
Drywall needs finished at top of stair banister |
|
|
-- |
-- |
Drywall needs finished at top of stair banister |
|
|
-- |
-- |
Trim missing on kitchen island |
Fred - on order |
|
-- |
-- |
Faucet cover, an electric stone cover, needed on front of townhouse |
Stone guys |
|
-- |
-- |
Trim needed in main level bathroom |
|
|
-- |
-- |
Back room is luxury vinyl plank not carpet |
|
|
-- |
-- |
Finish lvp in downstairs bedroom |
|
|
-- |
-- |
Cover hardwood treads |
|
|
-- |
-- |
All luxury vinyl plank, transition strips needed |
|
|
-- |
-- |
Basement towel bar a bit crooked |
Jill thinks so too! |
|
-- |
-- |
Door knobs needed on closet door in master bedroom |
Paul |
|
-- |
-- |
Fan is in basement bedroom but remote is in other room |
|
|
-- |
-- |
Blemish on small bedroom ceiling |
Painter |
|
-- |
-- |
HVAC cover needed in back family room |
|
|
-- |
-- |
CODED LOCKBOX 8888 |
Leaving until painting is completed (owner request) |
|
-- |
-- |
Install microwave |
CJ |
|
-- |
-- |
Needs vanity light in full bath main level |
Electrician |
|
-- |
-- |
Drywall patches needed in basement bathroom |
Drywaller |
|
-- |
-- |
Water turnoff cover |
Tom |
|
-- |
-- |
Electric outlet in master bath needs installed |
Electrician |
|
-- |
-- |
2 vanity lights need installed |
Electrician |
|
-- |
-- |
Front splash block needed |
|
|
-- |
-- |
White boards below doors needed |
Tom |
|
-- |
-- |
Lots of concrete on the back of the siding |
Courtney |
|
-- |
-- |
Touch up shoe molding and fill hole on basement stair landing |
Trim guy |
|
-- |
-- |
Basement bath vanity light needed |
Electrician. Just needs set in place 11/29 |
|
-- |
-- |
Patch screw holes in main level bath |
Painter |
|
-- |
-- |
Finish staining stairs |
In process 11/25 |
|
-- |
-- |
Drywall repairs on landing |
Painter |
|
-- |
-- |
Paint new trim on landing? |
Painter |
|
-- |
-- |
Will need re-cleaned in a few spaces |
Lynn |
|
-- |
-- |
Pressure wash back of townhouses |
Buddy |
|
-- |
-- |
Pressure wash off concrete, and patio |
Tom |
|
-- |
-- |
Install cable cover |
Electrician |
|
-- |
-- |
Townhouse needs a partial re-cleaning before final walk-through |
|
|
-- |
-- |
Install screens |
Jill |
|
-- |
-- |
caulk left side splash under kitchen window |
Painter |
|
-- |
-- |
Patio door to be adjusted |
Paul - Deadbolt does not work |
|
-- |
-- |
Radon pipe installation? |
|
|
-- |
-- |
Install cable cover in basement correctly |
|
|
-- |
-- |
Re-clean steps to the basement and final floor touch up |
Lynn. Jil 12/15 |
|
-- |
-- |
Missing screens- a few |
Jill |
|
-- |
-- |
Clean basement vanity |
Lynn. Jill 12/15 |
|
-- |
-- |
Paint touch up |
Painter |
|
-- |
-- |
Ratified Contract? (0) 07.20.2023 |
|
|
-- |
-- |
$2500 Deposit Received (0) 07.25.2023 |
|
|
-- |
-- |
Association Packet Requested (0) 07.20.2023 |
|
|
-- |
-- |
Association Packet Received (0) 07.22.2023 |
|
|
-- |
-- |
Selections Meeting (0) 08.15.2023 |
Wednesday 8/2 at 10:00 AM |
|
-- |
-- |
Selections Sheet Signed (0) 08.23.2023 |
8/17: Sent to Kozhin for signatures; |
|
-- |
-- |
Amendment for Upgrades (B,S,L,T,BCP) (0) 10.01.2023 |
9/30: Sent to Jerry |
|
-- |
-- |
Deposit For Upgrades Received (0) 08.29.2023 |
|
|
-- |
-- |
Building Permit (30) 05.05.2023 |
|
|
-- |
-- |
Order Roof & Floor Trusses (1) 06.26.2023 |
|
|
-- |
-- |
Order Windows & Doors (0) 06.26.2023 |
|
|
-- |
-- |
Stake Out Home (1) 05.18.2023 |
|
|
-- |
-- |
Excavate (2) 05.18.2023 |
|
|
-- |
-- |
Inspection (Footers) (1) 05.18.2023 |
|
|
-- |
-- |
Inspection (Concrete Wall) (1) 05.18.2023 |
|
|
-- |
-- |
Pour Footers (1) 05.18.2023 |
|
|
-- |
-- |
Set Forms (2) 06.01.2023 |
|
|
-- |
-- |
Pour Foundation Walls (1) 06.01.2023 |
|
|
-- |
-- |
Plumb Slab (2) 06.12.2023 |
|
|
-- |
-- |
Inspection (Plumbing Under Slab) (1) 06.19.2023 |
|
|
-- |
-- |
Inspection (Conduit Under Slab) (1) 06.19.2023 |
|
|
-- |
-- |
Prepare Slab (1) 06.12.2023 |
|
|
-- |
-- |
Inspection (Slab) (1) 06.19.2023 |
|
|
-- |
-- |
Inspection (Drain Tile) (0) 06.19.2023 |
|
|
-- |
-- |
Pour Slab (1) * 06.19.2023 |
|
|
-- |
-- |
Settlement Agent Confirmed (0) 09.06.2023 |
|
|
-- |
-- |
Framing I (9) 07.02.2023 |
|
|
-- |
-- |
Order Steps (0) 07.24.2023 |
|
|
-- |
-- |
Order Tubs / Showers (0) 08.03.2023 |
|
|
-- |
-- |
Framing II (8) 07.17.2023 |
|
|
-- |
-- |
Framing III (8) * 07.31.2023 |
|
|
-- |
-- |
Verify Window & Roof Structure (0) 12.11.2023 |
|
|
-- |
-- |
Install Stairs (0) 08.03.2023 |
|
|
-- |
-- |
Windows & Doors (0) 08.03.2023 |
|
|
-- |
-- |
House Number and Status in Window (0) 08.30.2023 |
|
|
-- |
-- |
Roofing (0) 08.03.2023 |
|
|
-- |
-- |
Order Cabinets (0) 09.01.2023 |
|
|
-- |
-- |
Order Appliances (0) 09.11.2023 |
STANDARD SS |
|
-- |
-- |
Deck (0) 08.26.2023 |
|
|
-- |
-- |
Gutters (0) 10.12.2023 |
|
|
-- |
-- |
Driveway (0) 10.30.2023 |
NO UPGRADE |
|
-- |
-- |
Patio (0) 10.30.2023 |
10 X 10 PATIO |
|
-- |
-- |
Privacy Divider / Fence (0) 11.12.2023 |
|
|
-- |
-- |
Sod / Seed / Landscaping (0) 11.12.2023 |
|
|
-- |
-- |
HVAC Rough In (4) 08.23.2023 |
|
|
-- |
-- |
Inspection (Rough In HVAC) (1) 09.10.2023 |
|
|
-- |
-- |
Rough In Microwave Vent (0) 12.11.2023 |
|
|
-- |
-- |
Plumbing Rough In (4) 08.26.2023 |
In process 8/23 |
|
-- |
-- |
Inspection (Rough In Plumbing) (1) 09.10.2023 |
|
|
-- |
-- |
Electric Rough In (4) 09.03.2023 |
In process 8/30 |
|
-- |
-- |
Inspection (Rough In Electric) (1) 09.10.2023 |
|
|
-- |
-- |
Inspection (Deck Piers) (0) 10.12.2023 |
|
|
-- |
-- |
Inspection (Framing) (1) 09.10.2023 |
|
|
-- |
-- |
Exterior Vinyl (0) * 10.08.2023 |
in process 10/4 |
|
-- |
-- |
Exterior Stone (0) 10.14.2023 |
in process 10/11 |
|
-- |
-- |
Insulation (2) 09.10.2023 |
|
|
-- |
-- |
Inspection (Insulation) (1) 09.11.2023 |
|
|
-- |
-- |
Inspection (Electric Service) (0) 09.28.2023 |
|
|
-- |
-- |
Set Electric Meter (0) 11.09.2023 |
|
|
-- |
-- |
Inspection (Main Sewer Line) (0) 10.05.2023 |
|
|
-- |
-- |
Inspection (Main Water Line) (0) 10.05.2023 |
|
|
-- |
-- |
Order Interior Doors & Trim (0) 10.05.2023 |
|
|
-- |
-- |
Drywall (Hang) (4) * 09.16.2023 |
Bonus Room, Bonus Bath. In process 9/13 |
|
-- |
-- |
Loan Approval (0) 10.23.2023 |
|
|
-- |
-- |
Deed Preparation (0) 10.19.2023 |
|
|
-- |
-- |
Drywall (Tape, Block, Skim, Sand) (6) * 10.04.2023 |
In process 9/30 |
|
-- |
-- |
Paint 1 (1) 10.04.2023 |
|
|
-- |
-- |
Garage Door (0) 09.03.2023 |
|
|
-- |
-- |
House Numbers (0) 11.06.2023 |
|
|
-- |
-- |
Mailbox (0) 11.04.2023 |
|
|
-- |
-- |
Cabinet Installation (2) * 10.14.2023 |
install 10/11. In process 10/11 |
|
-- |
-- |
Granite Installation (1) * 10.18.2023 |
|
|
-- |
-- |
Interior Trim - Install (3) 10.14.2023 |
In process 10/7 |
|
-- |
-- |
Order Plumbing / Lighting Fixtures (0) 10.16.2023 |
|
|
-- |
-- |
Interior Trim - Paint (1) 10.14.2023 |
|
|
-- |
-- |
Luxury Vinyl Plank (3) * 10.26.2023 |
In process 10/21 |
|
-- |
-- |
Luxury Vinyl Tile (0) 10.25.2023 |
|
|
-- |
-- |
Paint 2 (3) 10.14.2023 |
|
|
-- |
-- |
Cover Floors (1) 11.02.2023 |
|
|
-- |
-- |
Deliver Plumbing / Lighting Fixtures (0) 10.26.2023 |
|
|
-- |
-- |
Shoe Moulding (0) 11.02.2023 |
In process 10/28 |
|
-- |
-- |
Shelving, Door Knobs, Fire Extinguisher (0) 11.15.2023 |
BRUSHED NICKEL, BONUS. Needs mirrors 11/12 |
|
-- |
-- |
Install Coded Lockbox (add extra keys) (0) 11.09.2023 |
|
|
-- |
-- |
Pay Water / Sewer Taps (0) 10.16.2023 |
|
|
-- |
-- |
Set Water Meter (0) 11.09.2023 |
|
|
-- |
-- |
Electric Trim Out (3) 11.15.2023 |
BRUSHED NICKEL- a few things remain 11/12 |
|
-- |
-- |
Ceiling Fans (0) 11.04.2023 |
Master, Living Room, 2 upstairs bedrooms, Bonus Room ( with windows) |
|
-- |
-- |
HVAC Trim Out (1) 11.12.2023 |
|
|
-- |
-- |
Blower Door Test (1) 11.20.2023 |
|
|
-- |
-- |
Plumbing Trim Out (2) 11.15.2023 |
BRUSHED NICKEL, BONUS. In process 11/12 |
|
-- |
-- |
Install Appliances (0) * 11.04.2023 |
|
|
-- |
-- |
Paint 3 (2) * 10.18.2023 |
|
|
-- |
-- |
Carpet (2) 11.04.2023 |
|
|
-- |
-- |
Appraiser Confirms Construction Completion (0) 12.08.2023 |
|
|
-- |
-- |
Inspection (Final HVAC) (1) 11.21.2023 |
|
|
-- |
-- |
Inspection (Final Plumbing) (1) 11.21.2023 |
|
|
-- |
-- |
Inspection (Final Electric) (1) 11.21.2023 |
|
|
-- |
-- |
Inspection (Final Building) (2) * 11.21.2023 |
Tue, Nov 21 |
|
-- |
-- |
Pre Walk Through (0) 12.04.2023 |
|
|
-- |
-- |
Stain Hardwood Stairs (1) 11.20.2023 |
|
|
-- |
-- |
Cleaning (1) 11.25.2023 |
|
|
-- |
-- |
Certificate of Occupancy (1) * 11.21.2023 |
|
|
-- |
-- |
C.O. to Lender (0) 11.21.2023 |
|
|
-- |
-- |
Schedule Closing (0) 12.08.2023 |
|
|
-- |
-- |
Buyer Walk Through (1) 12.06.2023 |
|
|
-- |
-- |
Payment for Upgrades (0) 11.30.2023 |
|
|
-- |
-- |
Keys to Settlement Agent (0) 11.28.2023 |
|
|
-- |
-- |
Review Settlement Statement (0) 12.09.2023 |
|
|
-- |
-- |
Jerry Signs Closing Documents (0) 12.16.2023 |
|
|
-- |
-- |
Request Trash Tote From POA Manager (0) 11.21.2023 |
|
|
-- |
-- |
Closing (1) 12.16.2023 |
Brittany @ West View Title |
|
-- |
-- |
Remove Coded Lockbox (0) 01.22.2024 |
|
|