CONGERS-2 - 88  ::  1549 Palomino Trail
[ BUILD: 20230700 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
TO DO
---
UPGRADES
---
CRITICAL PATH
---
TO DO - COMPLETED OR DELETED
UPGRADES - COMPLETED
    Finished Bonus room ( room with window)  
    Finished Bathroom in in Bonus Room  
    Expanded 12x18 deck  
    Expanded 10x10 patio at basement level  
    Greyhound kitchen cabinetry  
    Three drawer base in place of 36” cabinet  
    Roll out trays in 18” pantry cabinet  
    Spice Rack  
    Vent microwave to exterior  
    Double pull out waste basket  
    LVP upstairs hall and bedrooms  
    LVP in bonus room behind garage  
    Hardwood treads to bedroom level  
    Powder Bath upgraded to Full Bath  
    Bonus room wall with pocket doors  
    Additional Master Bedroom closet (existing walk-in no shelving)  
    Painted Pine Steps to Basement Level  
    Ceiling fans- Living Room, 2 upstairs bedrooms and Bonus Room ($260) each  
    Completing drywall in basement family room  
    Completing electrical in basement family room  
    Amendment to increase price by $39,360  
CRITICAL PATH - COMPLETED
-- -- Inspection (Footers) (1)  05.18.2023    
-- -- Inspection (Concrete Wall) (1)  05.18.2023    
-- -- Inspection (Plumbing Under Slab) (1)  06.19.2023    
-- -- Inspection (Conduit Under Slab) (1)  06.19.2023    
-- -- Inspection (Slab) (1)  06.19.2023    
-- -- Inspection (Drain Tile) (0)  06.19.2023    
-- -- Inspection (Rough In HVAC) (1)  09.10.2023    
-- -- Inspection (Rough In Plumbing) (1)  09.10.2023    
-- -- Inspection (Rough In Electric) (1)  09.10.2023    
-- -- Inspection (Framing) (1) *   09.10.2023    
-- -- Inspection (Deck Piers) (0)  10.12.2023    
-- -- Inspection (Insulation) (1)  09.11.2023    
-- -- Inspection (Electric Service) (0)  09.28.2023    
-- -- Inspection (Main Sewer Line) (0)  10.05.2023    
-- -- Inspection (Main Water Line) (0)  10.05.2023    
-- -- Inspection (Final HVAC) (0)  11.21.2023    
-- -- Inspection (Final Plumbing) (0)  11.21.2023    
-- -- Inspection (Final Electric) (0)  11.21.2023    
-- -- Inspection (Final Building) (4) *   11.21.2023     Tue, Nov 21