| TO DO | ||||
| --- | ||||
| UPGRADES | ||||
| --- | ||||
| CRITICAL PATH | ||||
| --- | ||||
| TO DO - COMPLETED OR DELETED | ||||
| UPGRADES - COMPLETED | ||||
| Finished Bonus Room | ||||
| Finished Bonus Bath | ||||
| Finished Family Room | ||||
| Expanded 12 x 12 Deck | ||||
| White Kitchen Cabinetry | ||||
| Microwave vented to Exterior | ||||
| Luxury Vinyl Plank in Basement Family Room | ||||
| Luxury Vinyl Plank in upstairs hallway | ||||
| Luxury Vinyl Plank in Bonus Room | ||||
| 1 Additional Ceiling fan | ||||
| Oak Stairs To Bedroom Level | ||||
| 15% discount on upgrades per contract | ||||
| Amendment to increase price by $31,297 | ||||
| CRITICAL PATH - COMPLETED | ||||
| -- | -- | Inspection (Footers) (1) 05.18.2023 | ||
| -- | -- | Inspection (Concrete Wall) (1) 05.18.2023 | ||
| -- | -- | Inspection (Plumbing Under Slab) (1) 06.12.2023 | ||
| -- | -- | Inspection (Conduit Under Slab) (1) 06.12.2023 | ||
| -- | -- | Inspection (Slab) (1) 06.12.2023 | ||
| -- | -- | Inspection (Drain Tile) (0) 06.19.2023 | ||
| -- | -- | Inspection (Rough In HVAC) (1) 09.03.2023 | ||
| -- | -- | Inspection (Rough In Plumbing) (1) 09.03.2023 | ||
| -- | -- | Inspection (Rough In Electric) (1) 09.03.2023 | ||
| -- | -- | Inspection (Framing) (1) * 09.08.2023 | ||
| -- | -- | Inspection (Deck Piers) (0) 10.12.2023 | ||
| -- | -- | Inspection (Insulation) (1) 09.05.2023 | ||
| -- | -- | Inspection (Electric Service) (0) 09.28.2023 | ||
| -- | -- | Inspection (Main Sewer Line) (0) 10.05.2023 | ||
| -- | -- | Inspection (Main Water Line) (0) 10.05.2023 | ||
| -- | -- | Inspection (Final HVAC) (0) 11.21.2023 | ||
| -- | -- | Inspection (Final Plumbing) (0) 11.21.2023 | ||
| -- | -- | Inspection (Final Electric) (0) 11.21.2023 | ||
| -- | -- | Inspection (Final Building) (4) * 11.21.2023 | Tue, Nov 21 | |