37 ADDR
CONGERS-2 - 91  ::  1537 Palomino Trail
[ BUILD: 20230699 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
TO DO
---
UPGRADES
    Basement kitchenette ( includes standard cabinetry, level 1 granite, sink, faucet, full appliance package, install, plumbing and electrical  
    Finished Basement Family Room (room without windows)  
    Finish Bonus Room ( room with windows)  
CRITICAL PATH
Tue    Feb 3      Plumbing Rough In (4)  08.12.2023     in process 8/9
    Cover Floors (0)  09.28.2023    
    Deliver Plumbing / Lighting Fixtures (0)  10.19.2023    
    Install Coded Lockbox (add extra keys) (0)  10.22.2023    
TO DO - COMPLETED OR DELETED
50% deposit based on amount of upgrades (not applicable any longer?)
7/12: Kate is waiting for buyer to review selections;
7/12: Kate is waiting for buyer to review selections Kate made revisions and sent to agent for review once again. 7/21
Hardware needed on all cabinetry
Cover all carpet asap
Cover upstairs carpet
Make sure all showers have insulation
Needs all silver hall bath trim out in tub Change black to brushed nickel - one tub - plumber
Smaller bedroom door needs sanding/repainted Painter
Attic cover needed
Do we do nothing on stairs to basement?
Pretty large crack and molding leading to upper level of townhouse on stairs Painter
CODED LOCKBOX 9191
Living room drywall repair Painter
French door plugs Jill
Repair insulation that is sticking out of dishwasher Jill
Put insulation back in basement wall Tom
White boards on d3cks and front steps needed Tom. In process 11/8
Light cover needed in hall bath Electrician
Paint attic cover Painter
All bath fans needed Electrician
Basement window needs exterior trim Davenport
Clean our basement Jill
Is their trash can out front?
Trash can hiders needed Tom - need more siding
Paint foundation
Basement steps painted? Painter
Handrails
Thermostat Thu, Nov 9
Dishwasher needs to be attached to countertop CJ
Electric cover needed at pantry Electrician
Glue in hall bath In tub - Jill
Few stains on carpet Near front door and up hallway - Jill
Fill nail holes and address, gapping at shoe mold at Island George
Clean off deck Jill
Back of pedestal sink, clean off paint, and add caulk Painter
Master LVP- clean off paint spots
Trim island better with caulk and nail holes
Very little paint touch up throughout
Water pipe coming through the concrete wall in basement has rain water leaking in around it, needs some silicone added Tom and Jill
Put basement insulation back in place
Few tassels hanging off the front porch awning Buddy
This townhouse looks great! I have fully locked all the doors to keep it clean. 12/3
Can we remove the port-a-potty in the driveway?
Basement leak
Siding on side of trash can hider is falling down
UPGRADES - COMPLETED
    Luxury Vinyl Plank in entire basement  
    Vent Microwave to Exterior  
    Amendment to increase price by $630  
CRITICAL PATH - COMPLETED
-- -- Ratified Contract? (0)  05.05.2023    
-- -- $2500 Deposit Received (0)  07.08.2023    
-- -- Association Packet Requested (0)  05.05.2023    
-- -- Association Packet Received (0)  05.06.2023    
-- -- Selections Meeting (0)  07.22.2023    
-- -- Selections Sheet Signed (0)  09.30.2023     9/7: Sent to Kozhin; 9/11; Reminded Kozhin;
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  10.01.2023     9/30: Sent to Jerry
-- -- Deposit For Upgrades Received (0)  08.01.2023     n/a
-- -- Building Permit (30) *   05.05.2023    
-- -- Order Roof & Floor Trusses (1)  06.26.2023    
-- -- Order Windows & Doors (0)  06.26.2023    
-- -- Stake Out Home (1)  05.18.2023    
-- -- Excavate (2)  05.18.2023    
-- -- Inspection (Footers) (1)  12.14.2025    
-- -- Inspection (Concrete Wall) (1)  05.18.2023    
-- -- Pour Footers (1) *   05.18.2023    
-- -- Set Forms (2)  06.01.2023    
-- -- Pour Foundation Walls (1)  06.01.2023    
-- -- Plumb Slab (2)  06.12.2023    
-- -- Inspection (Plumbing Under Slab) (1)  06.12.2023    
-- -- Inspection (Conduit Under Slab) (1)  06.12.2023    
-- -- Prepare Slab (1)  06.12.2023    
-- -- Inspection (Slab) (1)  06.12.2023    
-- -- Inspection (Drain Tile) (0)  06.19.2023    
-- -- Pour Slab (1) *   06.12.2023    
-- -- Settlement Agent Confirmed (0)  05.26.2023    
-- -- Framing I (9)  07.02.2023    
-- -- Order Steps (0)  08.16.2023    
-- -- Order Tubs / Showers (0)  08.16.2023    
-- -- Framing II (8)  07.17.2023    
-- -- Framing III (8) *   08.03.2023    
-- -- Verify Window & Roof Structure (0)  12.11.2023    
-- -- Install Stairs (0) *   08.03.2023    
-- -- Windows & Doors (0) *   08.03.2023    
-- -- House Number and Status in Window (0)  12.14.2025    
-- -- Roofing (0) *   08.03.2023    
-- -- Order Cabinets (0)  08.28.2023    
-- -- Order Appliances (0)  09.11.2023     STANDARD SS
-- -- Deck (0)  08.26.2023    
-- -- Gutters (0)  10.12.2023    
-- -- Driveway (0) *   10.26.2023     NO UPGRADE
-- -- Patio (0)  10.28.2023     NO UPGRADE
-- -- Privacy Divider / Fence (0) *   11.12.2023     Needs all patio privacy dividers. In process 11/8
-- -- Sod / Seed / Landscaping (0)  11.04.2023    
-- -- HVAC Rough In (4)  08.19.2023     in process 8/16
-- -- Rough In Microwave Vent (0)  12.11.2023    
-- -- Electric Rough In (4)  08.26.2023     In process 8/19. All done but basement.
-- -- Inspection (Rough In HVAC) (1)  08.30.2023    
-- -- Inspection (Rough In Plumbing) (1)  08.30.2023    
-- -- Inspection (Rough In Electric) (1)  08.30.2023    
-- -- Inspection (Framing) (1) *   09.03.2023    
-- -- Inspection (Deck Piers) (0)  10.12.2023    
-- -- Exterior Vinyl (0) *   10.07.2023    
-- -- Exterior Stone (0)  10.22.2023     in process 10/18
-- -- Insulation (2) *   08.26.2023    
-- -- Inspection (Insulation) (1)  08.30.2023     8/24
-- -- Inspection (Electric Service) (0)  09.28.2023    
-- -- Set Electric Meter (0) *   11.08.2023    
-- -- Inspection (Main Sewer Line) (0)  10.05.2023    
-- -- Inspection (Main Water Line) (0)  10.05.2023    
-- -- Order Interior Doors & Trim (0)  10.05.2023    
-- -- Drywall (Hang) (4) *   08.30.2023     In process 8/26
-- -- Loan Approval (0)  10.12.2023    
-- -- Deed Preparation (0)  10.12.2023    
-- -- Drywall (Tape, Block, Skim, Sand) (6) *   09.03.2023     In process 8/30
-- -- Paint 1 (1)  09.10.2023    
-- -- Garage Door (0)  09.03.2023    
-- -- House Numbers (0)  11.04.2023    
-- -- Mailbox (0)  11.04.2023    
-- -- Cabinet Installation (2) *   09.23.2023     9/20. In process.
-- -- Granite Installation (1) *   09.23.2023    
-- -- Interior Trim - Install (3) *   09.23.2023     In process 9/20
-- -- Order Plumbing / Lighting Fixtures (0)  10.11.2023    
-- -- Interior Trim - Paint (1)  09.23.2023    
-- -- Luxury Vinyl Plank (3) *   09.28.2023    
-- -- Luxury Vinyl Tile (0)  09.27.2023    
-- -- Paint 2 (3)  09.30.2023    
-- -- Shoe Moulding (0)  10.07.2023    
-- -- Shelving, Door Knobs, Fire Extinguisher (1) *   10.14.2023     BRUSHED NICKEL in process 10/11
-- -- Pay Water / Sewer Taps (0)  10.16.2023    
-- -- Set Water Meter (1) *   11.09.2023    
-- -- Electric Trim Out (3) *   10.25.2023     BRUSHED NICKEL
-- -- Ceiling Fans (0)  10.25.2023    
-- -- HVAC Trim Out (1) *   11.08.2023     Thermostat needed 5/4
-- -- Blower Door Test (1)  11.08.2023    
-- -- Plumbing Trim Out (2) *   10.11.2023     BRUSHED NICKEL
-- -- Install Appliances (0) *   10.18.2023    
-- -- Paint 3 (2) *   10.11.2023    
-- -- Carpet (2)  10.09.2023     Living room correct?
-- -- Appraiser Confirms Construction Completion (0)  11.30.2023     Marty Walters, 11/27
-- -- Inspection (Final HVAC) (0)  11.13.2023     Nov 3
-- -- Inspection (Final Plumbing) (0)  11.13.2023    
-- -- Inspection (Final Electric) (0)  11.13.2023    
-- -- Inspection (Final Building) (4) *   11.16.2023     Reinspect - Mon, Nov 13
-- -- Pre Walk Through (0)  11.13.2023    
-- -- Stain Hardwood Stairs (1) *   11.01.2023    
-- -- Cleaning (1)  11.12.2023    
-- -- Certificate of Occupancy (1) *   11.16.2023    
-- -- C.O. to Lender (0)  11.16.2023    
-- -- Schedule Closing (0)  12.18.2023    
-- -- Buyer Walk Through (1) *   12.04.2023     Hopefully soon
-- -- Payment for Upgrades (0)  11.16.2023    
-- -- Keys to Settlement Agent (0)  11.28.2023    
-- -- Review Settlement Statement (0)  11.29.2023    
-- -- Jerry Signs Closing Documents (0)  11.28.2023    
-- -- Request Trash Tote From POA Manager (0)  11.21.2023    
-- -- Closing (1)  12.26.2023     Brittany @ West View Title
-- -- Remove Coded Lockbox (0)  01.02.2024