|
-- |
-- |
Closet framed out? |
|
|
-- |
-- |
Water coming in basement |
|
|
-- |
-- |
Must (must, must) close by January 15, 2023 |
daughter, basketball, eligibility |
|
-- |
-- |
Cover new carpets |
|
|
-- |
-- |
Remove large drywall pieces from master bathroom and upstairs small bedroom |
All pieces of drywall have been stacked into smaller upstairs bedroom |
|
-- |
-- |
Extra appliances are in this house |
CJ, Leisa |
|
-- |
-- |
One piece of counter top missing |
Installing 1/5 |
|
-- |
-- |
Attic cover |
Jill |
|
-- |
-- |
Finish gutters |
Tom |
|
-- |
-- |
Few lightbulbs needed and kitchen |
Jill |
|
-- |
-- |
Plug is needed so that microwave can be used |
|
|
-- |
-- |
All door knobs needed |
Mon, Jan 8 |
|
-- |
-- |
Drywall repair needed in powder bath |
Painter in process 1/13 |
|
-- |
-- |
Final paint, touchup needed |
Painter |
|
-- |
-- |
Can’t check micro vent as micro isn’t powered |
|
|
-- |
-- |
Whiteboard needed above front Stoop |
Tom |
|
-- |
-- |
Final paint, touchup needed |
|
|
-- |
-- |
Sand and repaint banisters |
Painter |
|
-- |
-- |
Paint front door |
Painter |
|
-- |
-- |
CODED LOCKBOX 8383 |
|
|
-- |
-- |
Finnish landscaping |
|
|
-- |
-- |
Finnish landscaping |
|
|
-- |
-- |
General paint touch ups throughout |
|
|
-- |
-- |
Pressure wash out front and back patio |
|
|
-- |
-- |
Paint front door, after cleaning it |
|
|
-- |
-- |
Need extra paint left for owners |
Painter |
|
-- |
-- |
A few scratches on the floor inside the front door |
Denny |
|
-- |
-- |
Pocket door does not close smoothly |
|
|
-- |
-- |
Mud on the carpet going t |
|
|
-- |
-- |
A few stairs have mud on them |
Jill |
|
-- |
-- |
Deck posts are not nailed down at the bottom |
Domingo |
|
-- |
-- |
Reclean the floors and surfaces throughout home |
Jill |
|
-- |
-- |
Clean the tops of all the cabinets in the kitchen |
|
|
-- |
-- |
Clean the tops of all the cabinets in the kitchen |
|
|
-- |
-- |
Replace damaged front door threshold |
We have them |
|
-- |
-- |
Ratified Contract? (0)
09.29.2023 |
|
|
-- |
-- |
$2500 Deposit Received (0)
10.03.2023 |
|
|
-- |
-- |
Association Packet Requested (0)
09.29.2023 |
|
|
-- |
-- |
Association Packet Received (0)
09.30.2023 |
|
|
-- |
-- |
Selections Meeting (0)
10.25.2023 |
|
|
-- |
-- |
Selections Sheet Signed (0)
10.26.2023 |
10/25: sent to Isaac |
|
-- |
-- |
Amendment for Upgrades (B,S,L,T,BCP) (0)
11.08.2023 |
11/6: Sent to Jerry for signature |
|
-- |
-- |
Deposit For Upgrades Received (0)
11.07.2023 |
|
|
-- |
-- |
Building Permit (30)
06.01.2023 |
|
|
-- |
-- |
Order Roof & Floor Trusses (1)
09.25.2023 |
|
|
-- |
-- |
Order Windows & Doors (0)
10.28.2023 |
|
|
-- |
-- |
Stake Out Home (1)
06.01.2023 |
|
|
-- |
-- |
Excavate (2)
06.01.2023 |
|
|
-- |
-- |
Inspection (Footers) (1)
06.01.2023 |
|
|
-- |
-- |
Inspection (Concrete Wall) (1)
06.01.2023 |
|
|
-- |
-- |
Pour Footers (1)
06.01.2023 |
|
|
-- |
-- |
Set Forms (2)
06.12.2023 |
|
|
-- |
-- |
Pour Foundation Walls (1)
06.12.2023 |
|
|
-- |
-- |
Plumb Slab (2)
06.26.2023 |
|
|
-- |
-- |
Inspection (Plumbing Under Slab) (1)
06.26.2023 |
|
|
-- |
-- |
Inspection (Conduit Under Slab) (1)
07.24.2023 |
|
|
-- |
-- |
Prepare Slab (1)
07.24.2023 |
|
|
-- |
-- |
Inspection (Slab) (1)
07.24.2023 |
|
|
-- |
-- |
Inspection (Drain Tile) (0)
07.24.2023 |
|
|
-- |
-- |
Pour Slab (1)
07.24.2023 |
|
|
-- |
-- |
Settlement Agent Confirmed (0)
12.22.2023 |
sent to Brittany 11/8 |
|
-- |
-- |
Framing I (9)
09.11.2023 |
in process 8/30 |
|
-- |
-- |
Order Steps (0)
10.12.2023 |
|
|
-- |
-- |
Order Tubs / Showers (0)
10.28.2023 |
|
|
-- |
-- |
Framing II (8)
09.11.2023 |
|
|
-- |
-- |
Framing III (8)
10.05.2023 |
|
|
-- |
-- |
Verify Window & Roof Structure (0)
12.11.2023 |
|
|
-- |
-- |
Install Stairs (0)
10.12.2023 |
|
|
-- |
-- |
Windows & Doors (0)
12.16.2023 |
|
|
-- |
-- |
House Number and Status in Window (0)
11.02.2023 |
|
|
-- |
-- |
Roofing (0)
10.30.2023 |
|
|
-- |
-- |
Order Cabinets (0)
11.02.2023 |
|
|
-- |
-- |
Order Appliances (0)
09.14.2023 |
STANDARD SS |
|
-- |
-- |
Deck (0)
10.28.2023 |
|
|
-- |
-- |
Gutters (0)
12.20.2023 |
|
|
-- |
-- |
Driveway (0)
01.06.2024 |
|
|
-- |
-- |
Patio (0)
12.16.2023 |
|
|
-- |
-- |
Privacy Divider / Fence (0)
01.17.2024 |
|
|
-- |
-- |
Sod / Seed / Landscaping (0)
02.12.2024 |
|
|
-- |
-- |
HVAC Rough In (4)
10.25.2023 |
in process 10/14 |
|
-- |
-- |
Inspection (Rough In HVAC) (1)
11.16.2023 |
|
|
-- |
-- |
Rough In Microwave Vent (0)
12.11.2023 |
|
|
-- |
-- |
Plumbing Rough In (4)
11.04.2023 |
In process 11/1 |
|
-- |
-- |
Inspection (Rough In Plumbing) (1)
11.16.2023 |
|
|
-- |
-- |
Electric Rough In (4)
11.12.2023 |
In process 11/8 |
|
-- |
-- |
Inspection (Rough In Electric) (1)
11.16.2023 |
|
|
-- |
-- |
Inspection (Deck Piers) (0)
11.16.2023 |
|
|
-- |
-- |
Inspection (Framing) (1)
11.16.2023 |
|
|
-- |
-- |
Exterior Vinyl (0)
12.20.2023 |
|
|
-- |
-- |
Exterior Stone (0)
01.06.2024 |
|
|
-- |
-- |
Insulation (2)
11.16.2023 |
|
|
-- |
-- |
Inspection (Insulation) (1)
11.16.2023 |
|
|
-- |
-- |
Inspection (Electric Service) (0)
12.18.2023 |
|
|
-- |
-- |
Set Electric Meter (0)
01.03.2024 |
|
|
-- |
-- |
Inspection (Main Sewer Line) (0)
12.18.2023 |
|
|
-- |
-- |
Inspection (Main Water Line) (0)
12.18.2023 |
|
|
-- |
-- |
Order Interior Doors & Trim (0)
12.18.2023 |
|
|
-- |
-- |
Drywall (Hang) (4)
11.20.2023 |
|
|
-- |
-- |
Loan Approval (0)
12.28.2023 |
|
|
-- |
-- |
Deed Preparation (0)
12.28.2023 |
|
|
-- |
-- |
Drywall (Tape, Block, Skim, Sand) (6)
12.09.2023 |
In process 12/6 |
|
-- |
-- |
Paint 1 (1)
12.09.2023 |
|
|
-- |
-- |
Garage Door (0)
12.04.2023 |
|
|
-- |
-- |
House Numbers (0)
01.11.2024 |
|
|
-- |
-- |
Mailbox (0)
01.03.2024 |
|
|
-- |
-- |
Cabinet Installation (2)
12.16.2023 |
In process 12/13 |
|
-- |
-- |
Granite Installation (1)
01.03.2024 |
Waiting on one countertop |
|
-- |
-- |
Interior Trim - Install (3)
12.16.2023 |
In process 12/13 |
|
-- |
-- |
Order Plumbing / Lighting Fixtures (0)
12.18.2023 |
|
|
-- |
-- |
Interior Trim - Paint (1)
12.16.2023 |
|
|
-- |
-- |
Luxury Vinyl Plank (3)
12.20.2023 |
|
|
-- |
-- |
Luxury Vinyl Tile (0)
12.20.2023 |
|
|
-- |
-- |
Paint 2 (3)
12.23.2023 |
|
|
-- |
-- |
Cover Floors (1)
01.03.2024 |
|
|
-- |
-- |
Deliver Plumbing / Lighting Fixtures (0)
12.28.2023 |
|
|
-- |
-- |
Shoe Moulding (0)
01.03.2024 |
|
|
-- |
-- |
Shelving, Door Knobs, Fire Extinguisher (0)
01.06.2024 |
In process. Needs doorknobs 1/3 |
|
-- |
-- |
Install Coded Lockbox (add extra keys) (0)
01.15.2024 |
|
|
-- |
-- |
Pay Water / Sewer Taps (0)
12.28.2023 |
|
|
-- |
-- |
Set Water Meter (0)
01.11.2024 |
Mon, Jan 8 |
|
-- |
-- |
Electric Trim Out (3)
01.02.2024 |
|
|
-- |
-- |
Ceiling Fans (0)
01.03.2024 |
|
|
-- |
-- |
HVAC Trim Out (1)
10.25.2023 |
|
|
-- |
-- |
Blower Door Test (1)
01.09.2024 |
Tue, Jan 9 |
|
-- |
-- |
Plumbing Trim Out (2)
01.03.2024 |
|
|
-- |
-- |
Install Appliances (0)
01.06.2024 |
|
|
-- |
-- |
Paint 3 (2)
01.03.2024 |
|
|
-- |
-- |
Carpet (2)
12.20.2023 |
|
|
-- |
-- |
Appraiser Confirms Construction Completion (0)
01.12.2024 |
|
|
-- |
-- |
Inspection (Final HVAC) (1)
01.12.2024 |
|
|
-- |
-- |
Inspection (Final Plumbing) (1)
01.12.2024 |
|
|
-- |
-- |
Inspection (Final Electric) (1)
01.12.2024 |
|
|
-- |
-- |
Inspection (Final Building) (2)
01.15.2024 |
Thu, Jan 11 |
|
-- |
-- |
Pre Walk Through (0)
01.16.2024 |
|
|
-- |
-- |
Stain Hardwood Stairs (1)
01.03.2024 |
|
|
-- |
-- |
Cleaning (1)
01.15.2024 |
|
|
-- |
-- |
Certificate of Occupancy (1)
01.16.2024 |
|
|
-- |
-- |
C.O. to Lender (0)
01.16.2024 |
|
|
-- |
-- |
Schedule Closing (0)
01.16.2024 |
|
|
-- |
-- |
Buyer Walk Through (1)
01.16.2024 |
Mon, Jan 15, 3PM |
|
-- |
-- |
Payment for Upgrades (0)
01.12.2024 |
|
|
-- |
-- |
Keys to Settlement Agent (0)
01.12.2024 |
|
|
-- |
-- |
Review Settlement Statement (0)
01.12.2024 |
|
|
-- |
-- |
Jerry Signs Closing Documents (0)
01.18.2024 |
|
|
-- |
-- |
Request Trash Tote From POA Manager (0)
01.12.2024 |
|
|
-- |
-- |
Closing (1)
01.18.2024 |
Brittany @ West View Title |
|
-- |
-- |
Remove Coded Lockbox (0)
01.27.2024 |
|
|