| TO DO | ||||
| --- | ||||
| UPGRADES | ||||
| Level 1 Quartz | ||||
| Microwave vented to exterior | ||||
| Digital Deadbolt | ||||
| Amendment to increase price by $5,710 | ||||
| CRITICAL PATH | ||||
| --- | ||||
| TO DO - COMPLETED OR DELETED | ||||
| UPGRADES - COMPLETED | ||||
| Expanded Deck 12 x 18 with three added deck supports | ||||
| Ceiling fan Living Room | ||||
| CRITICAL PATH - COMPLETED | ||||
| -- | -- | Inspection (Footers) (1) 12.14.2025 | ||
| -- | -- | Inspection (Concrete Wall) (1) 06.01.2023 | ||
| -- | -- | Inspection (Plumbing Under Slab) (1) 06.26.2023 | ||
| -- | -- | Inspection (Conduit Under Slab) (1) 07.24.2023 | ||
| -- | -- | Inspection (Slab) (1) 07.24.2023 | ||
| -- | -- | Inspection (Drain Tile) (0) 07.24.2023 | ||
| -- | -- | Inspection (Rough In HVAC) (1) 11.16.2023 | ||
| -- | -- | Inspection (Rough In Plumbing) (1) 11.16.2023 | ||
| -- | -- | Inspection (Rough In Electric) (1) 11.16.2023 | ||
| -- | -- | Inspection (Framing) (1) * 11.16.2023 | ||
| -- | -- | Inspection (Deck Piers) (0) 11.16.2023 | ||
| -- | -- | Inspection (Insulation) (1) 11.16.2023 | ||
| -- | -- | Inspection (Electric Service) (0) 12.14.2025 | ||
| -- | -- | Inspection (Main Sewer Line) (0) 12.18.2023 | ||
| -- | -- | Inspection (Main Water Line) (0) 12.18.2023 | ||
| -- | -- | Inspection (Final HVAC) (0) 01.12.2024 | ||
| -- | -- | Inspection (Final Plumbing) (0) 01.12.2024 | ||
| -- | -- | Inspection (Final Electric) (0) 01.12.2024 | ||
| -- | -- | Inspection (Final Building) (4) * 01.15.2024 | Thu, Jan 11 | |