Basement window needs trim on exterior |
|
|
-- |
-- |
Farm sink ordered 11/5 |
|
|
-- |
-- |
Three farmhouse sinks in basement |
two now... |
|
-- |
-- |
Missing trash drawer hardware |
Fred |
|
-- |
-- |
Missing piece of countertop |
Joy. December 28th should be installed |
|
-- |
-- |
Cover carpets asap |
Jill |
|
-- |
-- |
Two farm sinks in the basement |
One 1/6 |
|
-- |
-- |
CODED LOCKBOX 8585 |
Finish electrical panel box |
|
-- |
-- |
HVAC vent covers needed 1/17 |
|
|
-- |
-- |
Hall bathroom outlet cover needed |
Electrician |
|
-- |
-- |
Outlet cover, needed in laundry room |
Electrician |
|
-- |
-- |
Few drywall patches needed in master bathroom and paint touchup needed throughout |
Painter |
|
-- |
-- |
Lightbulbs needed, and kitchen, and in the hallway sconce |
Electrician |
|
-- |
-- |
Outside faucet needs cover between faucet and siding |
Jeremy, Davenport |
|
-- |
-- |
Move extra farm sink out of basement |
Maybe Lot 76 |
|
-- |
-- |
Attic cover needed |
|
|
-- |
-- |
Light needed in powder bath |
Electrician |
|
-- |
-- |
Paint, attic, cover |
Paint it |
|
-- |
-- |
Touch up paint needed around powder bath light fixture |
Painter |
|
-- |
-- |
Painted staircase, may need to be repainted or at least have serious touchups |
Painter |
|
-- |
-- |
Add more rock to front of house |
Stone guys |
|
-- |
-- |
White board on front porch |
Tom |
|
-- |
-- |
Add rock to front |
|
|
-- |
-- |
Adjust patio screen door |
Tom |
|
-- |
-- |
Stairs need second second coat of black paint |
Painter |
|
-- |
-- |
Pressure washe driveway |
|
|
-- |
-- |
Phil sand and paint screw holes above vanity light and powder bath |
Painter |
|
-- |
-- |
Fill nail holes in the master bath by the towel bars |
Painter |
|
-- |
-- |
Paint, touchup throughout |
Painter |
|
-- |
-- |
Mop out basement |
Lynn |
|
-- |
-- |
Few muddy spots on carpet |
Jill |
|
-- |
-- |
Touch up the kitchen island trim |
Jill |
|
-- |
-- |
Sod |
|
|
-- |
-- |
Put gutter back together |
|
|
-- |
-- |
Can we cut down that outside water pipe that’s green and ugly? |
Tom |
|
-- |
-- |
Damage siding from the weed eater outback |
davenport |
|
-- |
-- |
Ratified Contract? (0)
07.01.2023 |
|
|
-- |
-- |
$2500 Deposit Received (0)
07.11.2023 |
|
|
-- |
-- |
Association Packet Requested (0)
07.01.2023 |
|
|
-- |
-- |
Association Packet Received (0)
07.08.2023 |
|
|
-- |
-- |
Selections Meeting (0)
08.24.2023 |
|
|
-- |
-- |
Selections Sheet Signed (0)
08.30.2023 |
8/27: Sent to Kozhin; |
|
-- |
-- |
Amendment for Upgrades (B,S,L,T,BCP) (0)
09.13.2023 |
9/12: Sent to Jerry; |
|
-- |
-- |
Deposit For Upgrades Received (0)
09.12.2023 |
50% of Upgrade Cost |
|
-- |
-- |
Building Permit (30)
06.01.2023 |
|
|
-- |
-- |
Order Roof & Floor Trusses (1)
09.25.2023 |
|
|
-- |
-- |
Order Windows & Doors (0)
10.28.2023 |
|
|
-- |
-- |
Stake Out Home (1)
06.01.2023 |
|
|
-- |
-- |
Excavate (2)
06.01.2023 |
|
|
-- |
-- |
Inspection (Footers) (1)
06.01.2023 |
|
|
-- |
-- |
Inspection (Concrete Wall) (1)
06.01.2023 |
|
|
-- |
-- |
Pour Footers (1)
06.01.2023 |
|
|
-- |
-- |
Set Forms (2)
06.12.2023 |
|
|
-- |
-- |
Pour Foundation Walls (1)
06.12.2023 |
|
|
-- |
-- |
Plumb Slab (2)
06.26.2023 |
|
|
-- |
-- |
Inspection (Plumbing Under Slab) (1)
06.26.2023 |
|
|
-- |
-- |
Inspection (Conduit Under Slab) (1)
07.24.2023 |
|
|
-- |
-- |
Prepare Slab (1)
07.24.2023 |
|
|
-- |
-- |
Inspection (Slab) (1)
07.24.2023 |
|
|
-- |
-- |
Inspection (Drain Tile) (0)
07.24.2023 |
|
|
-- |
-- |
Pour Slab (1)
07.24.2023 |
|
|
-- |
-- |
Settlement Agent Confirmed (0)
09.15.2023 |
|
|
-- |
-- |
Framing I (9)
09.11.2023 |
in process 8/30 |
|
-- |
-- |
Order Steps (0)
10.12.2023 |
|
|
-- |
-- |
Order Tubs / Showers (0)
10.28.2023 |
|
|
-- |
-- |
Framing II (8)
09.11.2023 |
|
|
-- |
-- |
Framing III (8)
10.05.2023 |
|
|
-- |
-- |
Verify Window & Roof Structure (0)
12.11.2023 |
|
|
-- |
-- |
Install Stairs (0)
10.12.2023 |
|
|
-- |
-- |
Windows & Doors (0)
11.01.2023 |
|
|
-- |
-- |
House Number and Status in Window (0)
11.02.2023 |
|
|
-- |
-- |
Roofing (0)
10.30.2023 |
|
|
-- |
-- |
Order Cabinets (0)
11.02.2023 |
|
|
-- |
-- |
Order Appliances (0)
09.14.2023 |
STANDARD SS |
|
-- |
-- |
Deck (0)
10.28.2023 |
12 x 18 DECK |
|
-- |
-- |
Gutters (0)
12.20.2023 |
|
|
-- |
-- |
Driveway (0)
01.27.2024 |
NO UPGRADE |
|
-- |
-- |
Patio (0)
11.15.2023 |
NO UPGRADE |
|
-- |
-- |
Privacy Divider / Fence (0)
01.17.2024 |
|
|
-- |
-- |
Sod / Seed / Landscaping (0)
02.10.2024 |
|
|
-- |
-- |
HVAC Rough In (4)
11.01.2023 |
in process 10/28 |
|
-- |
-- |
Inspection (Rough In HVAC) (1)
11.08.2023 |
|
|
-- |
-- |
Rough In Microwave Vent (0)
12.11.2023 |
|
|
-- |
-- |
Plumbing Rough In (4)
10.25.2023 |
|
|
-- |
-- |
Inspection (Rough In Plumbing) (1)
11.08.2023 |
|
|
-- |
-- |
Electric Rough In (4)
11.04.2023 |
|
|
-- |
-- |
Inspection (Rough In Electric) (1)
11.08.2023 |
|
|
-- |
-- |
Inspection (Deck Piers) (0)
12.28.2023 |
|
|
-- |
-- |
Inspection (Framing) (1)
11.08.2023 |
|
|
-- |
-- |
Exterior Vinyl (0)
12.16.2023 |
In process 12/13 |
|
-- |
-- |
Exterior Stone (0)
01.25.2024 |
Tuesday, Jan 23 |
|
-- |
-- |
Insulation (2)
11.08.2023 |
|
|
-- |
-- |
Inspection (Insulation) (1)
11.15.2023 |
|
|
-- |
-- |
Inspection (Electric Service) (0)
12.18.2023 |
|
|
-- |
-- |
Set Electric Meter (0)
12.29.2023 |
|
|
-- |
-- |
Inspection (Main Sewer Line) (0)
12.18.2023 |
|
|
-- |
-- |
Inspection (Main Water Line) (0)
12.18.2023 |
|
|
-- |
-- |
Order Interior Doors & Trim (0)
12.18.2023 |
|
|
-- |
-- |
Drywall (Hang) (4)
11.15.2023 |
NO UPGRADE. Stocked 11/12 |
|
-- |
-- |
Loan Approval (0)
01.18.2024 |
|
|
-- |
-- |
Deed Preparation (0)
01.02.2024 |
|
|
-- |
-- |
Drywall (Tape, Block, Skim, Sand) (6)
11.25.2023 |
In process 11/15 |
|
-- |
-- |
Paint 1 (1)
11.25.2023 |
|
|
-- |
-- |
Garage Door (0)
12.05.2023 |
|
|
-- |
-- |
House Numbers (0)
01.29.2024 |
|
|
-- |
-- |
Mailbox (0)
01.06.2024 |
|
|
-- |
-- |
Cabinet Installation (2)
11.29.2023 |
Mon, Nov 27 |
|
-- |
-- |
Granite Installation (1)
12.13.2023 |
|
|
-- |
-- |
Interior Trim - Install (3)
12.03.2023 |
In process 11/29 |
|
-- |
-- |
Order Plumbing / Lighting Fixtures (0)
12.18.2023 |
|
|
-- |
-- |
Interior Trim - Paint (1)
12.09.2023 |
|
|
-- |
-- |
Luxury Vinyl Plank (3)
12.13.2023 |
In process 12/9 |
|
-- |
-- |
Luxury Vinyl Tile (0)
12.13.2023 |
|
|
-- |
-- |
Paint 2 (3)
12.16.2023 |
In process 12/13 |
|
-- |
-- |
Cover Floors (1)
12.23.2023 |
|
|
-- |
-- |
Deliver Plumbing / Lighting Fixtures (0)
01.06.2024 |
|
|
-- |
-- |
Shoe Moulding (0)
12.21.2023 |
In process 12/16 |
|
-- |
-- |
Shelving, Door Knobs, Fire Extinguisher (0)
01.03.2024 |
Black accessories, Shower Door, Black Trim, Digital Deadbolt |
|
-- |
-- |
Install Coded Lockbox (add extra keys) (0)
01.06.2024 |
|
|
-- |
-- |
Pay Water / Sewer Taps (0)
12.28.2023 |
|
|
-- |
-- |
Set Water Meter (0)
01.15.2024 |
|
|
-- |
-- |
Electric Trim Out (3)
01.17.2024 |
Black. In process 1/13. Still a bit to be done. |
|
-- |
-- |
Ceiling Fans (0)
01.13.2024 |
NO UPGRADE |
|
-- |
-- |
HVAC Trim Out (1)
01.17.2024 |
|
|
-- |
-- |
Blower Door Test (1)
01.22.2024 |
|
|
-- |
-- |
Plumbing Trim Out (2)
12.23.2023 |
Black |
|
-- |
-- |
Install Appliances (0)
01.10.2024 |
On site 12/20 |
|
-- |
-- |
Paint 3 (2)
12.23.2023 |
|
|
-- |
-- |
Carpet (2)
12.13.2023 |
|
|
-- |
-- |
Appraiser Confirms Construction Completion (0)
02.12.2024 |
|
|
-- |
-- |
Inspection (Final HVAC) (1)
01.30.2024 |
|
|
-- |
-- |
Inspection (Final Plumbing) (1)
01.30.2024 |
|
|
-- |
-- |
Inspection (Final Electric) (1)
01.30.2024 |
|
|
-- |
-- |
Inspection (Final Building) (2)
01.30.2024 |
Mon, Jan 29 |
|
-- |
-- |
Pre Walk Through (0)
01.29.2024 |
|
|
-- |
-- |
Stain Hardwood Stairs (1)
01.03.2024 |
|
|
-- |
-- |
Cleaning (1)
02.03.2024 |
in process 1/31 |
|
-- |
-- |
Certificate of Occupancy (1)
01.30.2024 |
|
|
-- |
-- |
C.O. to Lender (0)
01.30.2024 |
|
|
-- |
-- |
Schedule Closing (0)
02.15.2024 |
|
|
-- |
-- |
Buyer Walk Through (1)
02.03.2024 |
|
|
-- |
-- |
Payment for Upgrades (0)
01.25.2024 |
|
|
-- |
-- |
Keys to Settlement Agent (0)
01.25.2024 |
|
|
-- |
-- |
Review Settlement Statement (0)
01.31.2024 |
|
|
-- |
-- |
Jerry Signs Closing Documents (0)
01.31.2024 |
|
|
-- |
-- |
Request Trash Tote From POA Manager (0)
02.02.2024 |
|
|
-- |
-- |
Closing (1)
02.15.2024 |
Brittany @ West View Title |
|
-- |
-- |
Remove Coded Lockbox (0)
02.19.2024 |
|
|