37 ADDR
CONGERS-2 - 78  ::  1459 Appaloosa Court
[ BUILD: 20230716 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
TO DO
---
UPGRADES
---
CRITICAL PATH
---
TO DO - COMPLETED OR DELETED
Scott Stoehr needs to move things
Reminder to use the brick molds for pouring foundation walls
LEISA TO ORDER A FRENCH FRIDGE Kate REQUESTED ON 9/14
Can screens located in backyard be relocated ASAP
Missing a few black hardware in the kitchen cabinets Fred
This house has silver door hinges (some) should be black - Jill
Cover carpet 2/10
Snap lights are installed in the bedrooms Electrician
Do we switch garage door hinge colors? Kenny
Garage door handle needed Buddy
Microwave vent does not function Buddy
Closet hinges need switched out for black Buddy
Few outlet covers still needed Electrician. Just one at the kitchen island.
Home Inspection, Thursday, Feb 29 @ 4PM
Paint attic cover Painter
Screens need installed Jill
Patio door needs installed off back deck Screen - Jill
Patch holes at powder, bath light fixture
Trim backing material for the stone facade Pettit - add landscaping stone
Water lines need hooked up to fridge CJ
Make sure dishwasher is functional CJ
Make sure hot water works properly in shower Tom
Ensure attic insulation is sufficient for building standards Tom, Greg Sigmon, Davenport
Intall wire retention nut on the water heater Passes code
Remove items from garage Jill
Install patio door
Trim down door leading into utility room Trim, George
Sm dent in fridge. Just seeing 3/2 Door is here, CJ
White board needed to back deck Kenny is aware and getting in place.
CODED LOCKBOX 7878
Install patio door
Complete drywall repair in her bathroom Hall
Paint attic cover Painter
Master bedroom, lights and fan don’t seem to work. Is there supposed to be a remote control?
Relatively large dent in quartz countertops in master bathroom backsplash, on order
On set of silver hinges on closet Jill
Add cardboard to mechanical closet Jill
Paint and sand door edges Painter
Round corner of stair moulding sticks out into living room George
Scratch front of dishwasher new dishwasher on order
Second coat black paint stairs Painter
Landscaping escrow 4/19: Working on getting this released
Replace the replaced refrigerator door 5/6: on order
Water leak in basement bonus room
UPGRADES - COMPLETED
    Finished Bonus Room  
    Finish Bonus Bathroom  
    White Kitchen Cabinetry  
    Level III Quartz  
    Three Drawer Base in place of Base 36  
    Double Pull Out Trash can  
    4 Roll Out Trays in 18  
    2 Roll Out Trays in Lower 36  
    Spice Rack in Base 9  
    Microwave vented to Exterior  
    Master Bath Vanity with drawer stack  
    Shower Door with Black Trim  
    Painted Carpet Grade Stairs  
    Garage Door Keypad  
    Expanded 12 x 12 Deck  
    Level I Quartz Bathroom Vanities ( up only)  
    French Model Refrigerator  
    Expanded Driveway  
    Amendment to increase price by $30,300  
CRITICAL PATH - COMPLETED
-- -- Ratified Contract? (0)  08.25.2023    
-- -- $2500 Deposit Received (0)  08.29.2023    
-- -- Association Packet Requested (0)  08.25.2023    
-- -- Association Packet Received (0)  08.29.2023    
-- -- Selections Meeting (0)  09.09.2023    
-- -- Selections Sheet Signed (0)  09.13.2023     9/12: Sent to Oleksii;
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  09.16.2023     9/15: Sent to Jerry for signature
-- -- Deposit For Upgrades Received (0)  09.15.2023    
-- -- Building Permit (30) *   06.22.2023    
-- -- Order Roof & Floor Trusses (1)  09.14.2023    
-- -- Order Windows & Doors (0)  09.14.2023    
-- -- Stake Out Home (1)  07.02.2023    
-- -- Excavate (2)  08.03.2023    
-- -- Inspection (Footers) (1)  09.25.2023    
-- -- Inspection (Concrete Wall) (1)  09.25.2023    
-- -- Pour Footers (1) *   09.11.2023    
-- -- Set Forms (2)  09.11.2023    
-- -- Pour Foundation Walls (1)  09.11.2023    
-- -- Plumb Slab (2)  09.11.2023     in process 8/30
-- -- Inspection (Plumbing Under Slab) (1)  09.25.2023    
-- -- Inspection (Conduit Under Slab) (1)  09.25.2023    
-- -- Prepare Slab (1)  09.18.2023    
-- -- Inspection (Slab) (1)  09.25.2023    
-- -- Inspection (Drain Tile) (0)  09.25.2023    
-- -- Pour Slab (1) *   09.18.2023    
-- -- Settlement Agent Confirmed (0)  09.09.2023    
-- -- Framing I (9)  10.05.2023    
-- -- Order Steps (0)  10.26.2023    
-- -- Order Tubs / Showers (0)  10.26.2023    
-- -- Framing II (8)  10.16.2023    
-- -- Framing III (8) *   10.16.2023    
-- -- Verify Window & Roof Structure (0)  12.13.2023    
-- -- Install Stairs (0) *   10.26.2023    
-- -- Windows & Doors (0) *   11.06.2023    
-- -- House Number and Status in Window (0)  11.13.2023    
-- -- Roofing (0) *   10.30.2023    
-- -- Order Cabinets (0)  12.06.2023    
-- -- Order Appliances (0)  02.17.2024     STANDRAD STAINLESS ORDERED- SWAP WITH FRENCH
-- -- Deck (0)  10.28.2023     12 x 12 DECK
-- -- Gutters (0)  01.27.2024    
-- -- Driveway (0) *   02.08.2024     EXPANDED
-- -- Patio (0)  01.03.2024     NO UPGRADE
-- -- Privacy Divider / Fence (0) *   02.24.2024     Patio privacy panels needed. In process 2/21
-- -- Sod / Seed / Landscaping (0)  03.30.2024    
-- -- HVAC Rough In (4)  11.08.2023    
-- -- Rough In Microwave Vent (0)  12.13.2023    
-- -- Plumbing Rough In (4)  11.15.2023    
-- -- Electric Rough In (4)  12.06.2023    
-- -- Inspection (Rough In HVAC) (1)  12.20.2023    
-- -- Inspection (Rough In Plumbing) (1)  12.20.2023    
-- -- Inspection (Rough In Electric) (1)  12.20.2023    
-- -- Inspection (Framing) (1) *   12.20.2023    
-- -- Inspection (Deck Piers) (0)  01.18.2024    
-- -- Exterior Vinyl (0) *   01.18.2024    
-- -- Exterior Stone (0)  02.14.2024     In process 2/10
-- -- Insulation (2) *   12.20.2023    
-- -- Inspection (Insulation) (1)  12.20.2023    
-- -- Inspection (Electric Service) (0)  01.15.2024    
-- -- Set Electric Meter (0) *   01.18.2024    
-- -- Inspection (Main Sewer Line) (0)  01.18.2024    
-- -- Inspection (Main Water Line) (0)  01.18.2024    
-- -- Order Interior Doors & Trim (0)  01.18.2024    
-- -- Drywall (Hang) (4) *   01.04.2024     In process 12/20
-- -- Loan Approval (0)  10.14.2023    
-- -- Deed Preparation (0)  02.08.2024    
-- -- Drywall (Tape, Block, Skim, Sand) (6) *   01.17.2024     In process 1/6
-- -- Paint 1 (1)  01.17.2024    
-- -- Garage Door (0)  02.03.2024    
-- -- House Numbers (0)  02.17.2024    
-- -- Mailbox (0)  02.24.2024     Patio privacy panels needed. In process 2/21
-- -- Cabinet Installation (2) *   01.19.2024     Dec 12. On site 1/17
-- -- Granite Installation (1) *   01.31.2024    
-- -- Interior Trim - Install (3) *   01.27.2024    
-- -- Order Plumbing / Lighting Fixtures (0)  01.25.2024    
-- -- Interior Trim - Paint (1)  01.27.2024    
-- -- Luxury Vinyl Plank (3) *   02.07.2024     In process 2/3
-- -- Luxury Vinyl Tile (0)  02.07.2024    
-- -- Paint 2 (3)  01.19.2024    
-- -- Cover Floors (0)  02.14.2024    
-- -- Deliver Plumbing / Lighting Fixtures (0)  02.05.2024    
-- -- Shoe Moulding (0)  02.17.2024     In process 2/14
-- -- Shelving, Door Knobs, Fire Extinguisher (1) *   02.24.2024     Black accessories. In process 2/21Shelving completed.
-- -- Install Coded Lockbox (add extra keys) (0)  03.02.2024    
-- -- Pay Water / Sewer Taps (0)  02.05.2024    
-- -- Set Water Meter (1) *   02.19.2024    
-- -- Electric Trim Out (3) *   02.21.2024     BLACK. In process 2/21
-- -- Ceiling Fans (0)  02.21.2024     NO UPGRADE
-- -- HVAC Trim Out (1) *   02.21.2024    
-- -- Blower Door Test (1)  02.21.2024    
-- -- Plumbing Trim Out (2) *   02.21.2024     BLACK. In process 2/17
-- -- Install Appliances (0) *   02.17.2024    
-- -- Paint 3 (2) *   02.14.2024    
-- -- Carpet (2)  02.10.2024     In process 2/7
-- -- Appraiser Confirms Construction Completion (0)  03.04.2024    
-- -- Inspection (Final HVAC) (0)  02.22.2024    
-- -- Inspection (Final Plumbing) (0)  02.22.2024    
-- -- Inspection (Final Electric) (0)  02.22.2024    
-- -- Inspection (Final Building) (4) *   02.22.2024    
-- -- Pre Walk Through (0)  03.04.2024    
-- -- Stain Hardwood Stairs (1) *   03.02.2024     In process 2/21
-- -- Cleaning (1)  03.06.2024    
-- -- Certificate of Occupancy (1) *   02.23.2024    
-- -- C.O. to Lender (0)  02.23.2024    
-- -- Schedule Closing (0)  03.05.2024    
-- -- Buyer Walk Through (1) *   03.07.2024     Wed, Mar 6 at 1:30 PM
-- -- Payment for Upgrades (0)  02.22.2024    
-- -- Keys to Settlement Agent (0)  03.04.2024    
-- -- Review Settlement Statement (0)  02.02.2024     Remove $1500 credit from settlement statement
-- -- Jerry Signs Closing Documents (0)  01.31.2024    
-- -- Request Trash Tote From POA Manager (0)  02.22.2024    
-- -- Closing (1)  03.11.2024     Brittany @ West View Title
-- -- Remove Coded Lockbox (0)  04.10.2024