| TO DO | ||||
| --- | ||||
| UPGRADES | ||||
| --- | ||||
| CRITICAL PATH | ||||
| --- | ||||
| TO DO - COMPLETED OR DELETED | ||||
| UPGRADES - COMPLETED | ||||
| Finished Bonus Room | ||||
| Finish Bonus Bathroom | ||||
| White Kitchen Cabinetry | ||||
| Level III Quartz | ||||
| Three Drawer Base in place of Base 36 | ||||
| Double Pull Out Trash can | ||||
| 4 Roll Out Trays in 18 | ||||
| 2 Roll Out Trays in Lower 36 | ||||
| Spice Rack in Base 9 | ||||
| Microwave vented to Exterior | ||||
| Master Bath Vanity with drawer stack | ||||
| Shower Door with Black Trim | ||||
| Painted Carpet Grade Stairs | ||||
| Garage Door Keypad | ||||
| Expanded 12 x 12 Deck | ||||
| Level I Quartz Bathroom Vanities ( up only) | ||||
| French Model Refrigerator | ||||
| Expanded Driveway | ||||
| Amendment to increase price by $30,300 | ||||
| CRITICAL PATH - COMPLETED | ||||
| -- | -- | Inspection (Footers) (1) 09.25.2023 | ||
| -- | -- | Inspection (Concrete Wall) (1) 09.25.2023 | ||
| -- | -- | Inspection (Plumbing Under Slab) (1) 09.25.2023 | ||
| -- | -- | Inspection (Conduit Under Slab) (1) 09.25.2023 | ||
| -- | -- | Inspection (Slab) (1) 09.25.2023 | ||
| -- | -- | Inspection (Drain Tile) (0) 09.25.2023 | ||
| -- | -- | Inspection (Rough In HVAC) (1) 12.20.2023 | ||
| -- | -- | Inspection (Rough In Plumbing) (1) 12.20.2023 | ||
| -- | -- | Inspection (Rough In Electric) (1) 12.20.2023 | ||
| -- | -- | Inspection (Framing) (1) * 12.20.2023 | ||
| -- | -- | Inspection (Deck Piers) (0) 01.18.2024 | ||
| -- | -- | Inspection (Insulation) (1) 12.20.2023 | ||
| -- | -- | Inspection (Electric Service) (0) 01.15.2024 | ||
| -- | -- | Inspection (Main Sewer Line) (0) 01.18.2024 | ||
| -- | -- | Inspection (Main Water Line) (0) 01.18.2024 | ||
| -- | -- | Inspection (Final HVAC) (0) 02.22.2024 | ||
| -- | -- | Inspection (Final Plumbing) (0) 02.22.2024 | ||
| -- | -- | Inspection (Final Electric) (0) 02.22.2024 | ||
| -- | -- | Inspection (Final Building) (4) * 02.22.2024 | ||