Three Windows On Front Of Middle Level! |
|
|
-- |
-- |
Farm sink ordered 11/5 |
|
|
-- |
-- |
Needs a door leading into the garage |
|
|
-- |
-- |
Painting trim 3/6 |
|
|
-- |
-- |
Cover quartz |
|
|
-- |
-- |
Cover upstairs countertops to avoid staining |
|
|
-- |
-- |
Paint garage door |
Painters |
|
-- |
-- |
Quite a few lightbulbs needed |
Jilll |
|
-- |
-- |
Fix molding near hall bath tub (adjust to make square) |
Trim, George. In process 4/19. Needs final paint. |
|
-- |
-- |
Drywall/Patch wall near master bedroom door that is uneven |
Drywaller |
|
-- |
-- |
Adjust molding to be more straight on master bedroom door frame |
Trim, George |
|
-- |
-- |
Adjust molding to be more straight on master bedroom door frame |
|
|
-- |
-- |
Paint exposed to concrete space between townhouses |
Rock guys - Jill notified. In process 4/19 |
|
-- |
-- |
Paint touchup needed by front door |
Painter |
|
-- |
-- |
Install screen door to patio |
And deck - Tom |
|
-- |
-- |
Paint, touchup in hallway to kitchen |
Painter |
|
-- |
-- |
Large blemish on molding of stairs, leading to upper floor |
Painter |
|
-- |
-- |
Touch up paint |
Painter |
|
-- |
-- |
Clean plumbing and dishwasher out of garage |
Jill |
|
-- |
-- |
Patch nail heads in powder bath |
Painter. In process 4/12 |
|
-- |
-- |
Cannot locate the keys for this unit |
|
|
-- |
-- |
Touch up paint on the ceiling in smaller bedroom |
Painter |
|
-- |
-- |
Few blemishes on Master bedroom ceiling |
Painter |
|
-- |
-- |
CODED LOCBOX 7676 |
|
|
-- |
-- |
A few more screws are needed an outside table cover |
Cable - Jill |
|
-- |
-- |
Install white board on deck |
Tom |
|
-- |
-- |
Install screen doors |
|
|
-- |
-- |
Powder bath fan is not secured |
Jill, Mast & Brunk |
|
-- |
-- |
clean paint off floors |
painters |
|
-- |
-- |
shelves in tall kitchen cabinets are too short |
ordered- Fred |
|
-- |
-- |
reclean floors and surfaces after punch out is completed |
Jill or Lynn |
|
-- |
-- |
small wall in quest bathroom needs completed (trim) |
Drywallers |
|
-- |
-- |
paint touch ups needed throughout |
painters |
|
-- |
-- |
add screws and replace cable cover |
|
|
-- |
-- |
finish patching holes in master bedroom ceiling |
painters |
|
-- |
-- |
pin needed in hall bath door bottom hinge |
Jill |
|
-- |
-- |
add trim around farmhouse sink |
Fred has ordered this |
|
-- |
-- |
caulk gaps in cabinets (corners) |
painters |
|
-- |
-- |
ceiling blemish in dining area and kitchen |
painters |
|
-- |
-- |
paint underside of first step leading to upper level |
painters |
|
-- |
-- |
address the bump in the stairwell (leading downstairs to basement) |
Drywallers/Painters |
|
-- |
-- |
pressure wash front and back |
Jill |
|
-- |
-- |
replace trim on bottom of front door |
George |
|
-- |
-- |
Splash blocks in front/ back need set |
Tom |
|
-- |
-- |
Pin needed in deck door |
Jill |
|
-- |
-- |
Paint, touchup on doorway, leading to powder bath |
Painter |
|
-- |
-- |
Where did the powder bath mirror go? |
|
|
-- |
-- |
Suzanna- 540-241-8212 |
|
|
-- |
-- |
Ratified Contract? (0) 10.02.2023 |
|
|
-- |
-- |
$2500 Deposit Received (0) 10.04.2023 |
|
|
-- |
-- |
Association Packet Requested (0) 10.02.2023 |
|
|
-- |
-- |
Association Packet Received (0) 10.08.2023 |
|
|
-- |
-- |
Selections Meeting (0) 10.14.2023 |
|
|
-- |
-- |
Selections Sheet Signed (0) 10.19.2023 |
10/14: Sent to Courtney |
|
-- |
-- |
Amendment for Upgrades (B,S,L,T,BCP) (0) 10.26.2023 |
10/25: sent to Jerry |
|
-- |
-- |
Deposit For Upgrades Received (0) 10.26.2023 |
|
|
-- |
-- |
Building Permit (30) 09.11.2023 |
|
|
-- |
-- |
Order Roof & Floor Trusses (1) 11.20.2023 |
|
|
-- |
-- |
Order Windows & Doors (0) 11.20.2023 |
|
|
-- |
-- |
Stake Out Home (1) 09.11.2023 |
|
|
-- |
-- |
Excavate (2) 09.11.2023 |
|
|
-- |
-- |
Inspection (Footers) (1) 09.11.2023 |
|
|
-- |
-- |
Inspection (Concrete Wall) (1) 10.16.2023 |
|
|
-- |
-- |
Pour Footers (1) 09.11.2023 |
|
|
-- |
-- |
Set Forms (2) 09.11.2023 |
|
|
-- |
-- |
Pour Foundation Walls (1) 09.11.2023 |
|
|
-- |
-- |
Plumb Slab (2) 10.05.2023 |
|
|
-- |
-- |
Inspection (Plumbing Under Slab) (1) 10.05.2023 |
|
|
-- |
-- |
Inspection (Conduit Under Slab) (1) 10.05.2023 |
|
|
-- |
-- |
Prepare Slab (1) 10.16.2023 |
|
|
-- |
-- |
Inspection (Slab) (1) 10.16.2023 |
|
|
-- |
-- |
Inspection (Drain Tile) (0) 10.16.2023 |
|
|
-- |
-- |
Pour Slab (1) * 10.16.2023 |
|
|
-- |
-- |
Settlement Agent Confirmed (0) 10.25.2023 |
|
|
-- |
-- |
Framing I (9) 11.27.2023 |
|
|
-- |
-- |
Order Steps (0) 11.27.2023 |
|
|
-- |
-- |
Order Tubs / Showers (0) 11.27.2023 |
|
|
-- |
-- |
Framing II (8) 11.27.2023 |
|
|
-- |
-- |
Framing III (8) * 11.27.2023 |
|
|
-- |
-- |
Verify Window & Roof Structure (0) 12.20.2023 |
|
|
-- |
-- |
Install Stairs (0) 12.20.2023 |
|
|
-- |
-- |
Windows & Doors (0) 12.20.2023 |
|
|
-- |
-- |
House Number and Status in Window (0) 01.31.2024 |
|
|
-- |
-- |
Roofing (0) 12.20.2023 |
|
|
-- |
-- |
Order Cabinets (0) 01.16.2024 |
|
|
-- |
-- |
Order Appliances (0) 03.28.2024 |
FRENCH |
|
-- |
-- |
Deck (0) 01.04.2024 |
|
|
-- |
-- |
Gutters (0) 03.09.2024 |
|
|
-- |
-- |
Driveway (0) 03.28.2024 |
|
|
-- |
-- |
Patio (0) 02.07.2024 |
|
|
-- |
-- |
Privacy Divider / Fence (0) 04.10.2024 |
|
|
-- |
-- |
Sod / Seed / Landscaping (0) 04.19.2024 |
|
|
-- |
-- |
HVAC Rough In (4) 01.06.2024 |
In process 1/3 |
|
-- |
-- |
Inspection (Rough In HVAC) (1) 01.25.2024 |
|
|
-- |
-- |
Rough In Microwave Vent (0) 01.03.2024 |
|
|
-- |
-- |
Plumbing Rough In (4) 01.13.2024 |
In process 1/10 |
|
-- |
-- |
Inspection (Rough In Plumbing) (1) 01.25.2024 |
|
|
-- |
-- |
Electric Rough In (4) 01.25.2024 |
In process 1/19 |
|
-- |
-- |
Inspection (Rough In Electric) (1) 01.25.2024 |
|
|
-- |
-- |
Inspection (Deck Piers) (0) 01.25.2024 |
|
|
-- |
-- |
Inspection (Framing) (1) 01.25.2024 |
|
|
-- |
-- |
Exterior Vinyl (0) * 03.07.2024 |
In process 2/21 |
|
-- |
-- |
Exterior Stone (0) 03.13.2024 |
|
|
-- |
-- |
Insulation (2) 01.27.2024 |
|
|
-- |
-- |
Inspection (Insulation) (1) 01.31.2024 |
|
|
-- |
-- |
Inspection (Electric Service) (0) 03.07.2024 |
|
|
-- |
-- |
Set Electric Meter (0) 03.29.2024 |
|
|
-- |
-- |
Inspection (Main Sewer Line) (0) 02.15.2024 |
|
|
-- |
-- |
Inspection (Main Water Line) (0) 02.15.2024 |
|
|
-- |
-- |
Order Interior Doors & Trim (0) 02.21.2024 |
|
|
-- |
-- |
Drywall (Hang) (4) * 02.03.2024 |
In process 1/31 |
|
-- |
-- |
Loan Approval (0) 10.19.2023 |
JoDee (80% LTV) |
|
-- |
-- |
Deed Preparation (0) 03.28.2024 |
|
|
-- |
-- |
Drywall (Tape, Block, Skim, Sand) (6) * 02.17.2024 |
In process 2/14. Final sanding. |
|
-- |
-- |
Paint 1 (1) 02.17.2024 |
|
|
-- |
-- |
Garage Door (0) 03.13.2024 |
|
|
-- |
-- |
House Numbers (0) 04.06.2024 |
|
|
-- |
-- |
Mailbox (0) 03.28.2024 |
|
|
-- |
-- |
Cabinet Installation (2) * 02.21.2024 |
On site 2/17 |
|
-- |
-- |
Granite Installation (1) * 03.02.2024 |
March 1 |
|
-- |
-- |
Interior Trim - Install (3) 03.02.2024 |
In process 2/28 |
|
-- |
-- |
Order Plumbing / Lighting Fixtures (0) 03.14.2024 |
|
|
-- |
-- |
Interior Trim - Paint (1) 03.02.2024 |
|
|
-- |
-- |
Luxury Vinyl Plank (3) * 03.16.2024 |
In process 3/13 |
|
-- |
-- |
Luxury Vinyl Tile (0) 03.13.2024 |
|
|
-- |
-- |
Paint 2 (3) 03.20.2024 |
|
|
-- |
-- |
Cover Floors (1) 03.16.2024 |
|
|
-- |
-- |
Deliver Plumbing / Lighting Fixtures (0) 03.14.2024 |
|
|
-- |
-- |
Shoe Moulding (0) 03.30.2024 |
In process 3/20 |
|
-- |
-- |
Shelving, Door Knobs, Fire Extinguisher (0) 04.14.2024 |
|
|
-- |
-- |
Install Coded Lockbox (add extra keys) (0) 04.10.2024 |
|
|
-- |
-- |
Pay Water / Sewer Taps (0) 03.28.2024 |
|
|
-- |
-- |
Set Water Meter (0) 03.28.2024 |
|
|
-- |
-- |
Electric Trim Out (3) 04.06.2024 |
A few things left to be done |
|
-- |
-- |
Ceiling Fans (0) 03.30.2024 |
|
|
-- |
-- |
HVAC Trim Out (1) 03.30.2024 |
In process 3/13 |
|
-- |
-- |
Blower Door Test (1) 04.06.2024 |
|
|
-- |
-- |
Plumbing Trim Out (2) 03.30.2024 |
|
|
-- |
-- |
Install Appliances (0) * 04.04.2024 |
FRENCH- DELIVERY 3/18 |
|
-- |
-- |
Paint 3 (2) * 03.20.2024 |
|
|
-- |
-- |
Carpet (2) 03.13.2024 |
|
|
-- |
-- |
Appraiser Confirms Construction Completion (0) 04.18.2024 |
Diane Hirsch, Apr 10 |
|
-- |
-- |
Inspection (Final HVAC) (1) 04.06.2024 |
|
|
-- |
-- |
Inspection (Final Plumbing) (1) 04.06.2024 |
|
|
-- |
-- |
Inspection (Final Electric) (1) 04.06.2024 |
|
|
-- |
-- |
Inspection (Final Building) (2) * 04.06.2024 |
|
|
-- |
-- |
Pre Walk Through (0) 04.11.2024 |
|
|
-- |
-- |
Stain Hardwood Stairs (1) 04.06.2024 |
In process 4/3 |
|
-- |
-- |
Cleaning (1) 04.17.2024 |
|
|
-- |
-- |
Certificate of Occupancy (1) * 04.09.2024 |
|
|
-- |
-- |
C.O. to Lender (0) 04.09.2024 |
|
|
-- |
-- |
Schedule Closing (0) 04.16.2024 |
Thursday, April 18th |
|
-- |
-- |
Buyer Walk Through (1) 04.17.2024 |
Monday, April 15th at 4:30pm |
|
-- |
-- |
Payment for Upgrades (0) 04.09.2024 |
|
|
-- |
-- |
Keys to Settlement Agent (0) 04.15.2024 |
|
|
-- |
-- |
Review Settlement Statement (0) 04.16.2024 |
|
|
-- |
-- |
Jerry Signs Closing Documents (0) 03.22.2024 |
|
|
-- |
-- |
Request Trash Tote From POA Manager (0) 04.15.2024 |
|
|
-- |
-- |
Closing (1) 04.19.2024 |
Brittany @ West View Title, Thursday, April 18th |
|
-- |
-- |
Remove Coded Lockbox (0) 05.20.2024 |
|
|