1 33 37 89 47 73 67 55 56 59 57 66 65 64 60 61 62 63 ADDR
CONGERS-2 - 76  ::  1445 Appaloosa Court
[ BUILD: 20230931 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
--   --   Three Windows On Front Of Middle Level!
--   --   Farm sink ordered 11/5
--   --   Needs a door leading into the garage
--   --   Painting trim 3/6
--   --   Cover quartz
--   --   Cover upstairs countertops to avoid staining
--   --   Paint garage door Painters
--   --   Quite a few lightbulbs needed Jilll
--   --   Fix molding near hall bath tub (adjust to make square) Trim, George. In process 4/19. Needs final paint.
--   --   Drywall/Patch wall near master bedroom door that is uneven Drywaller
--   --   Adjust molding to be more straight on master bedroom door frame Trim, George
--   --   Adjust molding to be more straight on master bedroom door frame
--   --   Paint exposed to concrete space between townhouses Rock guys - Jill notified. In process 4/19
--   --   Paint touchup needed by front door Painter
--   --   Install screen door to patio And deck - Tom
--   --   Paint, touchup in hallway to kitchen Painter
--   --   Large blemish on molding of stairs, leading to upper floor Painter
--   --   Touch up paint Painter
--   --   Clean plumbing and dishwasher out of garage Jill
--   --   Patch nail heads in powder bath Painter. In process 4/12
--   --   Cannot locate the keys for this unit
--   --   Touch up paint on the ceiling in smaller bedroom Painter
--   --   Few blemishes on Master bedroom ceiling Painter
--   --   CODED LOCBOX 7676
--   --   A few more screws are needed an outside table cover Cable - Jill
--   --   Install white board on deck Tom
--   --   Install screen doors
--   --   Powder bath fan is not secured Jill, Mast & Brunk
--   --   clean paint off floors painters
--   --   shelves in tall kitchen cabinets are too short ordered- Fred
--   --   reclean floors and surfaces after punch out is completed Jill or Lynn
--   --   small wall in quest bathroom needs completed (trim) Drywallers
--   --   paint touch ups needed throughout painters
--   --   add screws and replace cable cover
--   --   finish patching holes in master bedroom ceiling painters
--   --   pin needed in hall bath door bottom hinge Jill
--   --   add trim around farmhouse sink Fred has ordered this
--   --   caulk gaps in cabinets (corners) painters
--   --   ceiling blemish in dining area and kitchen painters
--   --   paint underside of first step leading to upper level painters
--   --   address the bump in the stairwell (leading downstairs to basement) Drywallers/Painters
--   --   pressure wash front and back Jill
--   --   replace trim on bottom of front door George
--   --   Splash blocks in front/ back need set Tom
--   --   Pin needed in deck door Jill
--   --   Paint, touchup on doorway, leading to powder bath Painter
--   --   Where did the powder bath mirror go?
--   --   Suzanna- 540-241-8212
-- -- Ratified Contract? (0)  10.02.2023    
-- -- $2500 Deposit Received (0)  10.04.2023    
-- -- Association Packet Requested (0)  10.02.2023    
-- -- Association Packet Received (0)  10.08.2023    
-- -- Selections Meeting (0)  10.14.2023    
-- -- Selections Sheet Signed (0)  10.19.2023     10/14: Sent to Courtney
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  10.26.2023     10/25: sent to Jerry
-- -- Deposit For Upgrades Received (0)  10.26.2023    
-- -- Building Permit (30)  09.11.2023    
-- -- Order Roof & Floor Trusses (1)  11.20.2023    
-- -- Order Windows & Doors (0)  11.20.2023    
-- -- Stake Out Home (1)  09.11.2023    
-- -- Excavate (2)  09.11.2023    
-- -- Inspection (Footers) (1)  09.11.2023    
-- -- Inspection (Concrete Wall) (1)  10.16.2023    
-- -- Pour Footers (1)  09.11.2023    
-- -- Set Forms (2)  09.11.2023    
-- -- Pour Foundation Walls (1)  09.11.2023    
-- -- Plumb Slab (2)  10.05.2023    
-- -- Inspection (Plumbing Under Slab) (1)  10.05.2023    
-- -- Inspection (Conduit Under Slab) (1)  10.05.2023    
-- -- Prepare Slab (1)  10.16.2023    
-- -- Inspection (Slab) (1)  10.16.2023    
-- -- Inspection (Drain Tile) (0)  10.16.2023    
-- -- Pour Slab (1) *   10.16.2023    
-- -- Settlement Agent Confirmed (0)  10.25.2023    
-- -- Framing I (9)  11.27.2023    
-- -- Order Steps (0)  11.27.2023    
-- -- Order Tubs / Showers (0)  11.27.2023    
-- -- Framing II (8)  11.27.2023    
-- -- Framing III (8) *   11.27.2023    
-- -- Verify Window & Roof Structure (0)  12.20.2023    
-- -- Install Stairs (0)  12.20.2023    
-- -- Windows & Doors (0)  12.20.2023    
-- -- House Number and Status in Window (0)  01.31.2024    
-- -- Roofing (0)  12.20.2023    
-- -- Order Cabinets (0)  01.16.2024    
-- -- Order Appliances (0)  03.28.2024     FRENCH
-- -- Deck (0)  01.04.2024    
-- -- Gutters (0)  03.09.2024    
-- -- Driveway (0)  03.28.2024    
-- -- Patio (0)  02.07.2024    
-- -- Privacy Divider / Fence (0)  04.10.2024    
-- -- Sod / Seed / Landscaping (0)  04.19.2024    
-- -- HVAC Rough In (4)  01.06.2024     In process 1/3
-- -- Inspection (Rough In HVAC) (1)  01.25.2024    
-- -- Rough In Microwave Vent (0)  01.03.2024    
-- -- Plumbing Rough In (4)  01.13.2024     In process 1/10
-- -- Inspection (Rough In Plumbing) (1)  01.25.2024    
-- -- Electric Rough In (4)  01.25.2024     In process 1/19
-- -- Inspection (Rough In Electric) (1)  01.25.2024    
-- -- Inspection (Deck Piers) (0)  01.25.2024    
-- -- Inspection (Framing) (1)  01.25.2024    
-- -- Exterior Vinyl (0) *   03.07.2024     In process 2/21
-- -- Exterior Stone (0)  03.13.2024    
-- -- Insulation (2)  01.27.2024    
-- -- Inspection (Insulation) (1)  01.31.2024    
-- -- Inspection (Electric Service) (0)  03.07.2024    
-- -- Set Electric Meter (0)  03.29.2024    
-- -- Inspection (Main Sewer Line) (0)  02.15.2024    
-- -- Inspection (Main Water Line) (0)  02.15.2024    
-- -- Order Interior Doors & Trim (0)  02.21.2024    
-- -- Drywall (Hang) (4) *   02.03.2024     In process 1/31
-- -- Loan Approval (0)  10.19.2023     JoDee (80% LTV)
-- -- Deed Preparation (0)  03.28.2024    
-- -- Drywall (Tape, Block, Skim, Sand) (6) *   02.17.2024     In process 2/14. Final sanding.
-- -- Paint 1 (1)  02.17.2024    
-- -- Garage Door (0)  03.13.2024    
-- -- House Numbers (0)  04.06.2024    
-- -- Mailbox (0)  03.28.2024    
-- -- Cabinet Installation (2) *   02.21.2024     On site 2/17
-- -- Granite Installation (1) *   03.02.2024     March 1
-- -- Interior Trim - Install (3)  03.02.2024     In process 2/28
-- -- Order Plumbing / Lighting Fixtures (0)  03.14.2024    
-- -- Interior Trim - Paint (1)  03.02.2024    
-- -- Luxury Vinyl Plank (3) *   03.16.2024     In process 3/13
-- -- Luxury Vinyl Tile (0)  03.13.2024    
-- -- Paint 2 (3)  03.20.2024    
-- -- Cover Floors (1)  03.16.2024    
-- -- Deliver Plumbing / Lighting Fixtures (0)  03.14.2024    
-- -- Shoe Moulding (0)  03.30.2024     In process 3/20
-- -- Shelving, Door Knobs, Fire Extinguisher (0)  04.14.2024    
-- -- Install Coded Lockbox (add extra keys) (0)  04.10.2024    
-- -- Pay Water / Sewer Taps (0)  03.28.2024    
-- -- Set Water Meter (0)  03.28.2024    
-- -- Electric Trim Out (3)  04.06.2024     A few things left to be done
-- -- Ceiling Fans (0)  03.30.2024    
-- -- HVAC Trim Out (1)  03.30.2024     In process 3/13
-- -- Blower Door Test (1)  04.06.2024    
-- -- Plumbing Trim Out (2)  03.30.2024    
-- -- Install Appliances (0) *   04.04.2024     FRENCH- DELIVERY 3/18
-- -- Paint 3 (2) *   03.20.2024    
-- -- Carpet (2)  03.13.2024    
-- -- Appraiser Confirms Construction Completion (0)  04.18.2024     Diane Hirsch, Apr 10
-- -- Inspection (Final HVAC) (1)  04.06.2024    
-- -- Inspection (Final Plumbing) (1)  04.06.2024    
-- -- Inspection (Final Electric) (1)  04.06.2024    
-- -- Inspection (Final Building) (2) *   04.06.2024    
-- -- Pre Walk Through (0)  04.11.2024    
-- -- Stain Hardwood Stairs (1)  04.06.2024     In process 4/3
-- -- Cleaning (1)  04.17.2024    
-- -- Certificate of Occupancy (1) *   04.09.2024    
-- -- C.O. to Lender (0)  04.09.2024    
-- -- Schedule Closing (0)  04.16.2024     Thursday, April 18th
-- -- Buyer Walk Through (1)  04.17.2024     Monday, April 15th at 4:30pm
-- -- Payment for Upgrades (0)  04.09.2024    
-- -- Keys to Settlement Agent (0)  04.15.2024    
-- -- Review Settlement Statement (0)  04.16.2024    
-- -- Jerry Signs Closing Documents (0)  03.22.2024    
-- -- Request Trash Tote From POA Manager (0)  04.15.2024    
-- -- Closing (1)  04.19.2024     Brittany @ West View Title, Thursday, April 18th
-- -- Remove Coded Lockbox (0)  05.20.2024