CONGERS-2 - 76  ::  1445 Appaloosa Court
[ BUILD: 20230931 ]      
CRITICAL PATH   |   INSPECTIONS   |   FLOOR PLANS   |   SELECTIONS   |   SPECS   |   CHANGES   |   NHS
view photo archive
 
TO DO
UPGRADES
---
CRITICAL PATH
---
TO DO - COMPLETED OR DELETED
Three Windows On Front Of Middle Level!
Farm sink ordered 11/5
Needs a door leading into the garage
Painting trim 3/6
Cover quartz
Cover upstairs countertops to avoid staining
Paint garage door Painters
Quite a few lightbulbs needed Jilll
Fix molding near hall bath tub (adjust to make square) Trim, George. In process 4/19. Needs final paint.
Drywall/Patch wall near master bedroom door that is uneven Drywaller
Adjust molding to be more straight on master bedroom door frame Trim, George
Adjust molding to be more straight on master bedroom door frame
Paint exposed to concrete space between townhouses Rock guys - Jill notified. In process 4/19
Paint touchup needed by front door Painter
Install screen door to patio And deck - Tom
Paint, touchup in hallway to kitchen Painter
Large blemish on molding of stairs, leading to upper floor Painter
Touch up paint Painter
Clean plumbing and dishwasher out of garage Jill
Patch nail heads in powder bath Painter. In process 4/12
Cannot locate the keys for this unit
Touch up paint on the ceiling in smaller bedroom Painter
Few blemishes on Master bedroom ceiling Painter
CODED LOCBOX 7676
A few more screws are needed an outside table cover Cable - Jill
Install white board on deck Tom
Install screen doors
Powder bath fan is not secured Jill, Mast & Brunk
clean paint off floors painters
shelves in tall kitchen cabinets are too short ordered- Fred
reclean floors and surfaces after punch out is completed Jill or Lynn
small wall in quest bathroom needs completed (trim) Drywallers
paint touch ups needed throughout painters
add screws and replace cable cover
finish patching holes in master bedroom ceiling painters
pin needed in hall bath door bottom hinge Jill
add trim around farmhouse sink Fred has ordered this
caulk gaps in cabinets (corners) painters
ceiling blemish in dining area and kitchen painters
paint underside of first step leading to upper level painters
address the bump in the stairwell (leading downstairs to basement) Drywallers/Painters
pressure wash front and back Jill
replace trim on bottom of front door George
Splash blocks in front/ back need set Tom
Pin needed in deck door Jill
Paint, touchup on doorway, leading to powder bath Painter
Where did the powder bath mirror go?
Suzanna- 540-241-8212
UPGRADES - COMPLETED
    Expanded Driveway  
    Expanded 12 x 18 deck  
    Level 3 Quartz  
    French Model Fridge  
    White Kitchen Cabinetry  
    Farmhouse Sink  
    3 Drawer Stack 36" to exterior wall  
    Microwave vented tio exterior  
    Painted Stairs to bedroom level  
    LVP whole upstairs  
    Level 1 Quartz Upstairs Bathrooms  
    Amendment to increase price by $14,600  
CRITICAL PATH - COMPLETED
-- -- Ratified Contract? (0)  10.02.2023    
-- -- $2500 Deposit Received (0)  10.04.2023    
-- -- Association Packet Requested (0)  10.02.2023    
-- -- Association Packet Received (0)  10.08.2023    
-- -- Selections Meeting (0)  10.14.2023    
-- -- Selections Sheet Signed (0)  10.19.2023     10/14: Sent to Courtney
-- -- Amendment for Upgrades (B,S,L,T,BCP) (0)  10.26.2023     10/25: sent to Jerry
-- -- Deposit For Upgrades Received (0)  10.26.2023    
-- -- Building Permit (30) *   09.11.2023    
-- -- Order Roof & Floor Trusses (1)  11.20.2023    
-- -- Order Windows & Doors (0)  11.20.2023    
-- -- Stake Out Home (1)  09.11.2023    
-- -- Excavate (2)  09.11.2023    
-- -- Inspection (Footers) (1)  09.11.2023    
-- -- Inspection (Concrete Wall) (1)  10.16.2023    
-- -- Pour Footers (1) *   09.11.2023    
-- -- Set Forms (2)  09.11.2023    
-- -- Pour Foundation Walls (1)  09.11.2023    
-- -- Plumb Slab (2)  10.05.2023    
-- -- Inspection (Plumbing Under Slab) (1)  10.05.2023    
-- -- Inspection (Conduit Under Slab) (1)  10.05.2023    
-- -- Prepare Slab (1)  10.16.2023    
-- -- Inspection (Slab) (1)  10.16.2023    
-- -- Inspection (Drain Tile) (0)  10.16.2023    
-- -- Pour Slab (1) *   10.16.2023    
-- -- Settlement Agent Confirmed (0)  10.25.2023    
-- -- Framing I (9)  11.27.2023    
-- -- Order Steps (0)  11.27.2023    
-- -- Order Tubs / Showers (0)  11.27.2023    
-- -- Framing II (8)  11.27.2023    
-- -- Framing III (8) *   11.27.2023    
-- -- Verify Window & Roof Structure (0)  12.20.2023    
-- -- Install Stairs (0) *   12.20.2023    
-- -- Windows & Doors (0) *   12.20.2023    
-- -- House Number and Status in Window (0)  01.31.2024    
-- -- Roofing (0) *   12.20.2023    
-- -- Order Cabinets (0)  01.16.2024    
-- -- Order Appliances (0)  03.28.2024     FRENCH
-- -- Deck (0)  01.04.2024    
-- -- Gutters (0)  03.09.2024    
-- -- Driveway (0) *   03.28.2024    
-- -- Patio (0)  02.07.2024    
-- -- Privacy Divider / Fence (0) *   04.10.2024    
-- -- Sod / Seed / Landscaping (0)  04.19.2024    
-- -- HVAC Rough In (4)  01.06.2024     In process 1/3
-- -- Rough In Microwave Vent (0)  01.03.2024    
-- -- Plumbing Rough In (4)  01.13.2024     In process 1/10
-- -- Electric Rough In (4)  01.25.2024     In process 1/19
-- -- Inspection (Rough In HVAC) (1)  01.25.2024    
-- -- Inspection (Rough In Plumbing) (1)  01.25.2024    
-- -- Inspection (Rough In Electric) (1)  01.25.2024    
-- -- Inspection (Framing) (1) *   01.25.2024    
-- -- Inspection (Deck Piers) (0)  01.25.2024    
-- -- Exterior Vinyl (0) *   03.07.2024     In process 2/21
-- -- Exterior Stone (0)  03.13.2024    
-- -- Insulation (2) *   01.27.2024    
-- -- Inspection (Insulation) (1)  01.31.2024    
-- -- Inspection (Electric Service) (0)  03.07.2024    
-- -- Set Electric Meter (0) *   03.29.2024    
-- -- Inspection (Main Sewer Line) (0)  02.15.2024    
-- -- Inspection (Main Water Line) (0)  02.15.2024    
-- -- Order Interior Doors & Trim (0)  02.21.2024    
-- -- Drywall (Hang) (4) *   02.03.2024     In process 1/31
-- -- Loan Approval (0)  10.19.2023     JoDee (80% LTV)
-- -- Deed Preparation (0)  03.28.2024    
-- -- Drywall (Tape, Block, Skim, Sand) (6) *   02.17.2024     In process 2/14. Final sanding.
-- -- Paint 1 (1)  02.17.2024    
-- -- Garage Door (0)  03.13.2024    
-- -- House Numbers (0)  04.06.2024    
-- -- Mailbox (0)  03.28.2024    
-- -- Cabinet Installation (2) *   02.21.2024     On site 2/17
-- -- Granite Installation (1) *   03.02.2024     March 1
-- -- Interior Trim - Install (3) *   03.02.2024     In process 2/28
-- -- Order Plumbing / Lighting Fixtures (0)  03.14.2024    
-- -- Interior Trim - Paint (1)  03.02.2024    
-- -- Luxury Vinyl Plank (3) *   03.16.2024     In process 3/13
-- -- Luxury Vinyl Tile (0)  03.13.2024    
-- -- Paint 2 (3)  03.20.2024    
-- -- Cover Floors (0)  03.16.2024    
-- -- Deliver Plumbing / Lighting Fixtures (0)  03.14.2024    
-- -- Shoe Moulding (0)  03.30.2024     In process 3/20
-- -- Shelving, Door Knobs, Fire Extinguisher (1) *   04.14.2024    
-- -- Install Coded Lockbox (add extra keys) (0)  04.10.2024    
-- -- Pay Water / Sewer Taps (0)  03.28.2024    
-- -- Set Water Meter (1) *   03.28.2024    
-- -- Electric Trim Out (3) *   04.06.2024     A few things left to be done
-- -- Ceiling Fans (0)  03.30.2024    
-- -- HVAC Trim Out (1) *   03.30.2024     In process 3/13
-- -- Blower Door Test (1)  04.06.2024    
-- -- Plumbing Trim Out (2) *   03.30.2024    
-- -- Install Appliances (0) *   04.04.2024     FRENCH- DELIVERY 3/18
-- -- Paint 3 (2) *   03.20.2024    
-- -- Carpet (2)  03.13.2024    
-- -- Appraiser Confirms Construction Completion (0)  04.18.2024     Diane Hirsch, Apr 10
-- -- Inspection (Final HVAC) (0)  04.06.2024    
-- -- Inspection (Final Plumbing) (0)  04.06.2024    
-- -- Inspection (Final Electric) (0)  04.06.2024    
-- -- Inspection (Final Building) (4) *   04.06.2024    
-- -- Pre Walk Through (0)  04.11.2024    
-- -- Stain Hardwood Stairs (1) *   04.06.2024     In process 4/3
-- -- Cleaning (1)  04.17.2024    
-- -- Certificate of Occupancy (1) *   04.09.2024    
-- -- C.O. to Lender (0)  04.09.2024    
-- -- Schedule Closing (0)  04.16.2024     Thursday, April 18th
-- -- Buyer Walk Through (1) *   04.17.2024     Monday, April 15th at 4:30pm
-- -- Payment for Upgrades (0)  04.09.2024    
-- -- Keys to Settlement Agent (0)  04.15.2024    
-- -- Review Settlement Statement (0)  04.16.2024    
-- -- Jerry Signs Closing Documents (0)  03.22.2024    
-- -- Request Trash Tote From POA Manager (0)  04.15.2024    
-- -- Closing (1)  04.19.2024     Brittany @ West View Title, Thursday, April 18th
-- -- Remove Coded Lockbox (0)  05.20.2024