| -- | -- | BUYER CONTACT- 703-969-7036 | ||
| -- | -- | Remove steps from front foyer | ||
| -- | -- | This starving is covered with drywall, but the wall is definitely boTeed | Bowed | |
| -- | -- | Top dormer windows have black plastic in them. That’s going to be removed, correct? | ||
| -- | -- | Paint garage | ||
| -- | -- | Hardware needed on cabinetry | ||
| -- | -- | Remove pile of damaged drywall in living room | Before may 10. They are walking through with realtor | |
| -- | -- | Very large squeak at middle landing of stairs leading to upper level | Denny | |
| -- | -- | There are large holes at the bottom of all of the trim in this townhouse. Any reason why? | Painter | |
| -- | -- | Replace molding behind master bedroom door | George | |
| -- | -- | Trim upstairs bedroom doors so they open easily over carpet | George | |
| -- | -- | Cover carpet | Jill | |
| -- | -- | Have painters patch holes from trim screws | ||
| -- | -- | Fit splash box under gutters | Tom | |
| -- | -- | Hole needs to be patched behind bonus bath? | ||
| -- | -- | Powder bath light needs installed | Electrician | |
| -- | -- | Attic cover needed | Painters | |
| -- | -- | Trim door to utility space | George | |
| -- | -- | CODED LOCKBOX 7272 | ||
| -- | -- | Thermostat needs installed | ||
| -- | -- | Final paint touchup needed | Painters | |
| -- | -- | Hole in powder bath | Painter | |
| -- | -- | Side trim needed on kitchen island | George, corner piece | |
| -- | -- | Gap and molding on staircase leading to upper level | Painter | |
| -- | -- | Drywall issues in hall bathroom | Drywaller, Painter | |
| -- | -- | Repaint exterior door trim on front door | Painter | |
| -- | -- | Clean out garage | Jill | |
| -- | -- | Shower rod needs installed | Paul | |
| -- | -- | Remove blue tape bonus bath | Jill | |
| -- | -- | Remove glue bonus bath | Jill | |
| -- | -- | Touch up paint trim bonus bath | Painter | |
| -- | -- | Install cable cover garage | Jill | |
| -- | -- | Few screws needed switchplate hall bath | Jill | |
| -- | -- | Glue on hall tub | Jill | |
| -- | -- | Glue in master bath | Jill | |
| -- | -- | Paint throughout | Painter | |
| -- | -- | remove paint for upper kitchen cabinet | Painter | |
| -- | -- | remove mud from carpet on bonus room floor | Jill | |
| -- | -- | replace garage door to interior | ||
| -- | -- | Adjust bonus room closet and bonus closet door | ||
| -- | -- | Pressure wash front and back | ||
| -- | -- | Paint deck and bonus exterior door trim | Painter | |
| -- | -- | Fix broken piece bonus room window | Tom | |
| -- | -- | caulk kitchen counter backsplash | Painter | |
| -- | -- | clean paint off stair hinges | Painter | |
| -- | -- | hammer down nails in carpet up hallway | Tom | |
| -- | -- | adjust pantry pocket door | ||
| -- | -- | Fix master tray ceiling | Drywall | |
| -- | -- | Missing screw in hall bath switchplate | Jill | |
| -- | -- | adjust water pressure all showers | Tom | |
| -- | -- | Adjust upstairs closet doors | Jill | |
| -- | -- | leave extra paint | Painter | |
| -- | -- | add small piece of drywall to utility closet | Painter | |
| -- | -- | Remove glue in bonus bath | ||
| -- | -- | CODED LOCKBOX 7272 | ||
| -- | -- | Ratified Contract? (0) 11.10.2023 | ||
| Bonus Room | ||||
| Bonus Bathroom | ||||
| Double Waste basket | ||||
| Spice Rack | ||||
| Expanded Driveway | ||||
| Amendment to increase price by $17,840 | ||||
| -- | -- | $2500 Deposit Received (0) 11.17.2023 | ||
| -- | -- | Association Packet Requested (0) 11.10.2023 | ||
| -- | -- | Association Packet Received (0) 11.15.2023 | ||
| -- | -- | Selections Meeting (0) 12.06.2023 | ||
| -- | -- | Selections Sheet Signed (0) 12.28.2023 | 12/6: sent to Chris for signatures | |
| -- | -- | Amendment for Upgrades (B,S,L,T,BCP) (0) 01.22.2024 | 1/22: sent to Jerry for signature | |
| -- | -- | Deposit For Upgrades Received (0) 01.22.2024 | ||
| -- | -- | Building Permit (30) * 11.06.2023 | ||
| -- | -- | Order Roof & Floor Trusses (1) 01.25.2024 | ||
| -- | -- | Order Windows & Doors (0) 02.12.2024 | ||
| -- | -- | Stake Out Home (1) 12.26.2023 | ||
| -- | -- | Excavate (2) 12.26.2023 | ||
| -- | -- | Inspection (Footers) (1) 12.26.2023 | ||
| -- | -- | Inspection (Concrete Wall) (1) 12.26.2023 | ||
| -- | -- | Pour Footers (1) * 12.26.2023 | ||
| -- | -- | Set Forms (2) 12.26.2023 | ||
| -- | -- | Pour Foundation Walls (1) 12.26.2023 | ||
| -- | -- | Plumb Slab (2) 12.26.2023 | ||
| -- | -- | Inspection (Plumbing Under Slab) (1) 01.04.2024 | ||
| -- | -- | Inspection (Conduit Under Slab) (1) 01.04.2024 | ||
| -- | -- | Prepare Slab (1) 01.04.2024 | ||
| -- | -- | Inspection (Slab) (1) 01.04.2024 | ||
| -- | -- | Inspection (Drain Tile) (0) 01.04.2024 | ||
| -- | -- | Pour Slab (1) * 01.04.2024 | ||
| -- | -- | Settlement Agent Confirmed (0) 01.24.2024 | ||
| -- | -- | Framing I (9) 01.29.2024 | ||
| -- | -- | Order Steps (0) 02.14.2024 | ||
| -- | -- | Order Tubs / Showers (0) 02.14.2024 | ||
| -- | -- | Framing II (8) 01.29.2024 | ||
| -- | -- | Framing III (8) * 02.14.2024 | ||
| -- | -- | Verify Window & Roof Structure (0) 02.14.2024 | ||
| -- | -- | Install Stairs (0) * 02.14.2024 | ||
| -- | -- | Windows & Doors (0) * 02.14.2024 | ||
| -- | -- | House Number and Status in Window (0) 03.04.2024 | ||
| -- | -- | Roofing (0) * 03.04.2024 | ||
| -- | -- | Order Cabinets (0) 03.23.2024 | ||
| -- | -- | Order Appliances (0) 05.20.2024 | STANDARD | |
| -- | -- | Deck (0) 02.14.2024 | ||
| -- | -- | Gutters (0) 04.24.2024 | ||
| -- | -- | Driveway (0) * 05.08.2024 | ||
| -- | -- | Patio (0) 04.27.2024 | ||
| -- | -- | Privacy Divider / Fence (0) * 04.27.2024 | ||
| -- | -- | Sod / Seed / Landscaping (0) 05.22.2024 | ||
| -- | -- | HVAC Rough In (4) 02.21.2024 | In process 2/14 | |
| -- | -- | Rough In Microwave Vent (0) 03.02.2024 | ||
| -- | -- | Plumbing Rough In (4) 03.16.2024 | In process 3/13 | |
| -- | -- | Electric Rough In (4) 03.16.2024 | In process 3/13 | |
| -- | -- | Inspection (Rough In HVAC) (1) 03.21.2024 | ||
| -- | -- | Inspection (Rough In Plumbing) (1) 03.21.2024 | ||
| -- | -- | Inspection (Rough In Electric) (1) 03.21.2024 | ||
| -- | -- | Inspection (Framing) (1) * 03.21.2024 | ||
| -- | -- | Inspection (Deck Piers) (0) 05.20.2024 | ||
| -- | -- | Exterior Vinyl (0) * 04.27.2024 | ||
| -- | -- | Exterior Stone (0) 05.08.2024 | ||
| -- | -- | Insulation (2) * 03.30.2024 | ||
| -- | -- | Inspection (Insulation) (1) 03.30.2024 | ||
| -- | -- | Inspection (Electric Service) (0) 04.11.2024 | ||
| -- | -- | Set Electric Meter (0) * 05.02.2024 | ||
| -- | -- | Inspection (Main Sewer Line) (0) 03.21.2024 | ||
| -- | -- | Inspection (Main Water Line) (0) 03.21.2024 | ||
| -- | -- | Order Interior Doors & Trim (0) 04.12.2024 | ||
| -- | -- | Drywall (Hang) (4) * 03.30.2024 | ||
| -- | -- | Loan Approval (0) 06.11.2024 | Melissa Hoover, Mission Mortgage (96% LTV) | |
| -- | -- | Deed Preparation (0) 05.20.2024 | ||
| -- | -- | Drywall (Tape, Block, Skim, Sand) (6) * 04.06.2024 | In process 4/3 | |
| -- | -- | Paint 1 (1) 04.06.2024 | ||
| -- | -- | Garage Door (0) 05.08.2024 | ||
| -- | -- | House Numbers (0) 05.15.2024 | ||
| -- | -- | Mailbox (0) 05.18.2024 | ||
| -- | -- | Cabinet Installation (2) * 04.19.2024 | Install April 19 | |
| -- | -- | Granite Installation (1) * 04.27.2024 | ||
| -- | -- | Interior Trim - Install (3) * 04.19.2024 | In process 4/17 | |
| -- | -- | Order Plumbing / Lighting Fixtures (0) 05.13.2024 | ||
| -- | -- | Interior Trim - Paint (1) 05.04.2024 | ||
| -- | -- | Luxury Vinyl Plank (3) * 05.11.2024 | In process 5/8 | |
| -- | -- | Luxury Vinyl Tile (0) 05.11.2024 | In process 5/8 | |
| -- | -- | Paint 2 (3) 05.11.2024 | ||
| -- | -- | Cover Floors (1) 06.01.2024 | ||
| -- | -- | Deliver Plumbing / Lighting Fixtures (0) 05.13.2024 | ||
| -- | -- | Shoe Moulding (0) 05.18.2024 | ||
| -- | -- | Shelving, Door Knobs, Fire Extinguisher (0) * 06.01.2024 | In process 5/29 | |
| -- | -- | Install Coded Lockbox (add extra keys) (0) 06.05.2024 | ||
| -- | -- | Pay Water / Sewer Taps (0) 05.16.2024 | ||
| -- | -- | Set Water Meter (0) * 05.30.2024 | ||
| -- | -- | Electric Trim Out (3) * 06.01.2024 | Standard Black. In process 5/29 | |
| -- | -- | Ceiling Fans (0) 05.26.2024 | Master | |
| -- | -- | HVAC Trim Out (1) * 06.05.2024 | ||
| -- | -- | Blower Door Test (1) 06.17.2024 | 6/6 | |
| -- | -- | Plumbing Trim Out (2) * 06.12.2024 | Standard Black. In process 6/9 | |
| -- | -- | Install Appliances (0) * 06.12.2024 | Leisa- being delivered Monday, June 10th | |
| -- | -- | Paint 3 (2) * 05.15.2024 | ||
| -- | -- | Carpet (2) 05.11.2024 | ||
| -- | -- | Appraiser Confirms Construction Completion (0) 06.20.2024 | ||
| -- | -- | Inspection (Final HVAC) (1) 06.17.2024 | ||
| -- | -- | Inspection (Final Plumbing) (1) 06.17.2024 | ||
| -- | -- | Inspection (Final Electric) (1) 06.17.2024 | ||
| -- | -- | Inspection (Final Building) (2) * 06.17.2024 | Thurs, June 13 | |
| -- | -- | Pre Walk Through (0) 06.17.2024 | ||
| -- | -- | Stain Hardwood Stairs (1) * 06.01.2024 | In process 5/29 | |
| -- | -- | Cleaning (1) 06.17.2024 | ||
| -- | -- | Certificate of Occupancy (1) * 06.20.2024 | ||
| -- | -- | C.O. to Lender (0) 06.20.2024 | ||
| -- | -- | Schedule Closing (0) 06.20.2024 | ||
| -- | -- | Buyer Walk Through (1) * 06.18.2024 | Mon, Jun 17 at 4:00 PM | |
| -- | -- | Payment for Upgrades (0) 06.20.2024 | ||
| -- | -- | Keys to Settlement Agent (0) 06.10.2024 | ||
| -- | -- | Review Settlement Statement (0) 06.21.2024 | ||
| -- | -- | Jerry Signs Closing Documents (0) 06.13.2024 | ||
| -- | -- | Request Trash Tote From POA Manager (0) 06.13.2024 | ||
| -- | -- | Closing (1) 06.21.2024 | Brittany @ West View Title | |
| -- | -- | Remove Coded Lockbox (0) 06.24.2024 | ||